| NOGRR282 ! Board Priority - Large Computational Load Ride-Through Requirements |
ERCOT |
Approved |
Nov 14 '25 |
Jul 9 '26 |
| NOGRR283 ! Board Priority - Related to NPRR1309, Dispatchable Reliability Reserve Service Ancillary Service |
ERCOT |
Approved |
Nov 20 '25 |
Jul 9 '26 |
| NPRR1308 ! Board Priority - Related to NOGRR282, Large Computational Load Ride-Through Requirements |
ERCOT |
Approved |
Nov 14 '25 |
Jul 9 '26 |
| NPRR1309 ! Board Priority - Dispatchable Reliability Reserve Service Ancillary Service |
ERCOT |
Approved |
Nov 20 '25 |
Jul 9 '26 |
| NPRR1315 ! Changes to Process of Evaluating the Potential Needs for Additional Capacity and Mitigated Offer Cap |
ERCOT |
Approved |
Dec 19 '25 |
Jul 9 '26 |
| NPRR1330 ! Mitigated Offer Caps for RMR Units |
ERCOT |
Approved |
Apr 21 '26 |
Jul 9 '26 |
| PGRR133 ! Clarifying Legacy Generation Breaker Control for PGRR115 Implementation |
Vistra |
Approved |
Oct 30 '25 |
Jul 9 '26 |
| NPRR1325 ! Related to PGRR145, Batch Zero Process for Large Load Interconnections |
ERCOT |
Approved |
Mar 4 '26 |
Jun 18 '26 |
| PGRR145 ! Batch Zero Process for Large Load Interconnections |
ERCOT |
Approved |
Mar 4 '26 |
Jun 18 '26 |
| NPRR1323 ! Correction to Inadvertent Removal of Real-Time MCPC Capping for NPRR1290 Phase 2 |
ERCOT |
Approved |
Feb 24 '26 |
May 29 '26 |
| NPRR1328 ! Establishment of Generation Firming Program |
ERCOT |
PRS for consideration (PRS) |
Apr 2 '26 |
Apr 15 '26 |
| NPRR1311 ! Correction to Real-Time Reliability Deployment Price Adders for Ancillary Services under Load Shed for RTC+B |
ERCOT |
Approved |
Nov 25 '25 |
Mar 26 '26 |
| PGRR131 ! Requirements for Interconnection Cost Reporting for Transmission-Connected Generators |
ERCOT |
Approved |
Aug 26 '25 |
Jan 15 '26 |
| NPRR1310 ! Dispatchable Reliability Reserve Service Plus Energy Storage Resource Participation and Release Factor |
ERCOT |
PRS for consideration (PRS) |
Nov 20 '25 |
Dec 10 '25 |
| NOGRR272 ! Advanced Grid Support Requirements for Inverter-Based ESRs |
ERCOT |
Approved |
Oct 31 '24 |
Nov 6 '25 |
| NOGRR278 ! Related to NPRR1290, Gap Resolutions and Clarifications for the Implementation of RTC+B |
ERCOT |
Approved |
Jul 16 '25 |
Nov 6 '25 |
| PGRR121 ! Related to NOGRR272, Advanced Grid Support Requirements for Inverter-Based ESRs |
ERCOT |
Approved |
Oct 31 '24 |
Nov 6 '25 |
| NOGRR277 ! Related to NPRR1282, Ancillary Service Duration under Real-Time Co-Optimization |
ERCOT |
Approved |
Apr 29 '25 |
Jul 31 '25 |
| NPRR1282 ! Ancillary Service Duration under Real-Time Co-Optimization |
ERCOT |
Approved |
Apr 29 '25 |
Jul 31 '25 |
| PGRR125 ! Update of LSIPA Compliance Attestation |
ERCOT |
Approved |
Mar 25 '25 |
Jul 31 '25 |
| NOGRR274 ! Conform Nodal Operating Guide to Revisions Implemented for NPRR1217, Remove Verbal Dispatch Instruction (VDI) Requirement for Deployment and Recall of Load Resources and Emergency Response Service (ERS) Resources |
ERCOT |
Approved |
Feb 26 '25 |
May 15 '25 |
| NPRR1268 ! RTC – Modification of Ancillary Service Demand Curves |
IMM |
Approved |
Jan 28 '25 |
May 15 '25 |
| NPRR1269 ! RTC+B Three Parameters Policy Issues |
ERCOT |
Approved |
Jan 28 '25 |
May 15 '25 |
| NPRR1270 ! Additional Revisions Required for Implementation of RTC |
ERCOT |
Approved |
Jan 28 '25 |
May 15 '25 |
| NPRR1273 ! Appropriate Accounting for ESRs in PRC Calculation |
ERCOT |
Approved |
Feb 12 '25 |
May 15 '25 |
| NPRR1247 ! Incorporation of Congestion Cost Savings Test in Economic Evaluation of Transmission Projects |
ERCOT |
Approved |
Aug 9 '24 |
Jan 16 '25 |
| NOGRR245 ! Inverter-Based Resource (IBR) Ride-Through Requirements |
ERCOT |
Approved |
Jan 11 '23 |
Sep 26 '24 |
| NPRR1219 ! Methodology Revisions and New Definitions for the Report on Capacity, Demand and Reserves in the ERCOT Region (CDR) |
ERCOT |
Approved |
Mar 5 '24 |
Sep 26 '24 |
| NPRR1230 ! Methodology for Setting Transmission Shadow Price Caps for an IROL in SCED |
ERCOT |
Approved |
May 7 '24 |
Sep 26 '24 |
| NPRR1224 ! ECRS Manual Deployment Triggers |
ERCOT |
Rejected |
Mar 27 '24 |
Jul 25 '24 |
| NPRR1228 ! Continued One-Winter Procurements for Firm Fuel Supply Service (FFSS) |
ERCOT |
Approved |
May 2 '24 |
Jul 25 '24 |
| NPRR1179 ! Fuel Purchase Requirements for Resources Submitting RUC Fuel Costs |
ERCOT |
Approved |
May 4 '23 |
Apr 11 '24 |
| NPRR1186 ! Improvements Prior to the RTC+B Project for Better ESR State of Charge Awareness, Accounting, and Monitoring |
ERCOT |
Approved |
Jun 22 '23 |
Apr 11 '24 |
| NPRR1199 ! Implementation of Lone Star Infrastructure Protection Act (LSIPA) Requirements |
ERCOT |
Approved |
Sep 6 '23 |
Apr 11 '24 |
| RMGRR179 ! TDSP Temporary Emergency Electric Energy Facility (TEEEF) Deployment Transactional Processing |
Texas SET |
Approved |
Dec 22 '23 |
Apr 11 '24 |
| NPRR1204 ! Considerations of State of Charge with Real-Time Co-Optimization Implementation |
ERCOT |
Approved |
Oct 10 '23 |
Feb 1 '24 |
| RMGRR176 ! Addition of Market Processes Specific to LP&L |
LRITF |
Approved |
Oct 23 '23 |
Feb 1 '24 |
| NPRR1203 ! Implementation of Dispatchable Reliability Reserve Service |
ERCOT |
Withdrawn |
Sep 27 '23 |
Dec 4 '23 |
| NPRR1209 ! Board Priority – State Of Charge Ancillary Service Failed Quantity Allocations under NPRR1149 |
ERCOT |
Withdrawn |
Nov 8 '23 |
Nov 9 '23 |
| NOGRR253 ! Related to NPRR1178, Expectations for Resources Providing ERCOT Contingency Reserve Service |
ERCOT |
Approved |
May 3 '23 |
Jun 29 '23 |
| NPRR1169 ! Expansion of Generation Resources Qualified to Provide Firm Fuel Supply Service in Phase 2 of the Service |
ERCOT |
Approved |
Mar 29 '23 |
Jun 29 '23 |
| NPRR1177 ! Enhance Exceptional Fuel Cost Process |
Constellation |
Approved |
Apr 27 '23 |
Jun 29 '23 |
| NPRR1178 ! Expectations for Resources Providing ERCOT Contingency Reserve Service |
ERCOT |
Approved |
May 3 '23 |
Jun 29 '23 |
| COPMGRR049 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| LPGRR072 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| NOGRR248 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| PGRR104 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| RMGRR173 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| RRGRR034 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| SMOGRR026 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| VCMRR036 ! Related to NPRR1157, Incorporation of PUCT Approval into Revision Request Process |
ERCOT |
Approved |
Feb 22 '23 |
May 11 '23 |
| LPGRR071 ! Reduced Timing Requirement for Submittal of Usage and Demand Values by Opt-In Entities |
ERCOT |
Approved |
Feb 22 '23 |
Apr 27 '23 |
| NOGRR243 ! Implementation of Seasonal Load Shed Tables |
Joint TOs |
Approved |
Sep 29 '22 |
Jan 26 '23 |
| NPRR1138 ! Communication of Capability and Status of Online IRRs at 0 MW Output |
ERCOT |
Approved |
May 25 '22 |
Jan 26 '23 |
| NPRR1152 ! Remove Requirements to Submit Emergency Operations Plans, Weatherization Plans, and Declarations of Summer/Winter Weather Preparedness |
ERCOT |
Approved |
Oct 20 '22 |
Jan 26 '23 |
| NPRR1154 ! Include Alternate Resource in the Availability Plan for the Firm Fuel Supply Service |
LCRA |
Approved |
Nov 3 '22 |
Jan 26 '23 |
| RMGRR170 ! Inadvertent Gain Process Updates |
TDTMS |
Approved |
Sep 27 '22 |
Dec 15 '22 |
| SCR823 ! ERCOT Mass System “County Name” File Updates for Texas SET V5.0 Implementation |
Texas SET Working Group |
Approved |
Sep 13 '22 |
Nov 3 '22 |
| NPRR1112 ! Elimination of Unsecured Credit Limits |
ERCOT |
Approved |
Dec 22 '21 |
Sep 15 '22 |
| NPRR1142 ! ERS Changes to Reflect Updated PUCT Rule Changes re SUBST. R. 25.507 |
ERCOT |
Approved |
Jul 14 '22 |
Aug 25 '22 |
| NPRR1100 ! Allow Generation Resources and Energy Storage Resources to Serve Customer Load When the Customer and the Resource are Disconnected from the ERCOT System |
Tesla |
Approved |
Oct 6 '21 |
Jul 14 '22 |
| NPRR1129 ! Posting ESI IDs of Transmission-Voltage Customer Opt-Outs |
ERCOT |
Approved |
Apr 12 '22 |
Jul 14 '22 |
| NPRR1130 ! Weatherization Inspection Fees Sunset Date Extension |
ERCOT |
Approved |
Apr 22 '22 |
Jul 14 '22 |
| NOGRR239 ! WAN Data Protection Responsibilities |
ERCOT |
Approved |
Jan 19 '22 |
May 12 '22 |
| NPRR1108 ! ERCOT Shall Approve or Deny All Resource Planned Outage Requests |
ERCOT |
Approved |
Nov 9 '21 |
May 12 '22 |
| NPRR1122 ! Clarifications for PURA Subchapter M Securitization Default Charges |
ERCOT |
Approved |
Feb 24 '22 |
May 12 '22 |
| NPRR1123 ! Clarifications for PURA Subchapter N Securitization Uplift Charges |
ERCOT |
Approved |
Feb 24 '22 |
May 12 '22 |
| NPRR1124 ! Recovering Actual Fuel Costs through RUC Guarantee |
ERCOT |
Approved |
Mar 9 '22 |
May 12 '22 |
| NPRR1125 ! Use of Financial Security for Securitization Default Charge and Securitization Uplift Charge Invoices and Escrow Deposit Requests |
ERCOT |
Approved |
Mar 11 '22 |
May 12 '22 |
| NPRR1097 ! Create Resource Forced Outage Report |
ERCOT |
Approved |
Sep 29 '21 |
Mar 31 '22 |
| NPRR1111 ! Related to SCR819, Improving IRR Control to Manage GTC Stability Limits |
ERCOT |
Approved |
Dec 13 '21 |
Mar 31 '22 |
| NPRR1113 ! Clarification of Regulation-Up Schedule for Controllable Load Resources in Ancillary Service Imbalance |
ERCOT |
Approved |
Dec 22 '21 |
Mar 31 '22 |
| NPRR1114 ! Securitization – PURA Subchapter N Uplift Charges |
ERCOT |
Approved |
Dec 29 '21 |
Mar 31 '22 |
| NPRR1120 ! Create Firm Fuel Supply Service |
ERCOT |
Approved |
Jan 31 '22 |
Mar 31 '22 |
| SCR819 ! Improving IRR Control to Manage GTC Stability Limits |
ERCOT |
Approved |
Dec 13 '21 |
Mar 31 '22 |
| NOGRR236 ! Related to NPRR1105, Option to Deploy Distribution Voltage Reduction Measures Prior to Energy Emergency Alert (EEA) |
ERCOT |
Approved |
Nov 4 '21 |
Dec 16 '21 |
| NOGRR237 ! Related to NPRR1106, Deployment of Emergency Response Service (ERS) Prior to Declaration of Energy Emergency Alert (EEA) |
ERCOT |
Approved |
Nov 4 '21 |
Dec 16 '21 |
| NPRR1091 ! Changes to Address Market Impacts of Additional Non-Spin Procurement |
Shell Energy North America |
Approved |
Aug 2 '21 |
Dec 16 '21 |
| NPRR1101 ! Create Non-Spin Deployment Groups made up of Generation Resources Providing Off-Line Non-Spinning Reserve and Load Resources that are Not Controllable Load Resources Providing Non-Spinning Reserve |
ERCOT |
Approved |
Oct 20 '21 |
Dec 16 '21 |
| NPRR1103 ! Securitization – PURA Subchapter M Default Charges |
ERCOT |
Approved |
Nov 1 '21 |
Dec 16 '21 |
| NPRR1104 ! As-Built Definition of Real Time Liability Extrapolated (RTLE) |
ERCOT |
Approved |
Nov 2 '21 |
Dec 16 '21 |
| NPRR1105 ! Option to Deploy Distribution Voltage Reduction Measures Prior to Energy Emergency Alert (EEA) |
ERCOT |
Approved |
Nov 4 '21 |
Dec 16 '21 |
| NPRR1106 ! Deployment of Emergency Response Service (ERS) Prior to Declaration of Energy Emergency Alert (EEA) |
ERCOT |
Approved |
Nov 4 '21 |
Dec 16 '21 |
| NPRR1107 ! Addition of Weatherization Inspection Fees to the ERCOT Fee Schedule and Clarification of Generation Interconnection Request Fees |
ERCOT |
Approved |
Nov 9 '21 |
Dec 16 '21 |
| NPRR1109 ! Process for Reinstating Decommissioned Generation Resources |
ERCOT |
Approved |
Nov 9 '21 |
Dec 16 '21 |
| NOGRR232 ! Related to NPRR1093, Load Resource Participation in Non-Spinning Reserve |
ERCOT |
Approved |
Sep 1 '21 |
Oct 28 '21 |
| NPRR1087 ! Prohibit Participation of Critical Loads as Load Resources or ERS Resources |
ERCOT |
Approved |
Jul 19 '21 |
Oct 28 '21 |
| NPRR1090 ! ERS Winter Storm Uri Lessons Learned Changes and Other ERS Items |
ERCOT |
Approved |
Jul 28 '21 |
Oct 28 '21 |
| NPRR1093 ! Load Resource Participation in Non-Spinning Reserve |
ERCOT |
Approved |
Sep 1 '21 |
Oct 28 '21 |
| NPRR1073 ! Market Entry/Participation by Principals of Counter-Parties with Financial Obligations |
Morgan Stanley... |
Approved |
Apr 5 '21 |
Aug 19 '21 |
| NPRR1078 ! Clarification of Potential Uplift |
Reliant Energy... |
Approved |
May 20 '21 |
Aug 19 '21 |
| NPRR1083 ! Modification of Uplift Allocation Rules to Address Role of Central Counter-Party Clearinghouses |
ICE NGX Canada Inc. |
Approved |
Jun 25 '21 |
Aug 19 '21 |
| NPRR1086 ! Recovery, Charges, and Settlement for Operating Losses During an LCAP Effective Period |
ERCOT |
Approved |
Jul 14 '21 |
Aug 19 '21 |
| SCR815 ! MarkeTrak Administrative Enhancements |
TDTMS |
Approved |
Jun 30 '21 |
Aug 19 '21 |
| NPRR1080 ! Limiting Ancillary Service Price to System-Wide Offer Cap |
ERCOT and IMM |
Approved |
Jun 3 '21 |
Jun 28 '21 |
| NPRR1081 ! Revisions to Real-Time Reliability Deployment Price Adder to Consider Firm Load Shed |
ERCOT and IMM |
Approved |
Jun 3 '21 |
Jun 28 '21 |
| NPRR1074 ! “mp” Definition Revision |
Morgan Stanley... |
Approved |
Apr 6 '21 |
Jun 8 '21 |
| NPRR1075 ! Update Telemetered HSL and/or MPC for ESRs in Real-Time to Meet Ancillary Service Resource Responsibility |
Key Capture Energy |
Approved |
Apr 28 '21 |
Jun 8 '21 |
| NPRR1069 ! Align Ancillary Service Responsibility for ESRs with NPRR987 |
ERCOT |
Approved |
Mar 1 '21 |
Apr 13 '21 |
| SMOGRR024 ! Implement NPRR1020 |
Tesla |
Approved |
Nov 24 '20 |
Feb 9 '21 |
| NOGRR211 ! RTC – NOG 2 and 9: System Operations and Control Requirements and Monitoring Programs |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1007 ! RTC – NP 3: Management Activities for the ERCOT System |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1008 ! RTC – NP 4: Day-Ahead Operations |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1009 ! RTC – NP 5: Transmission Security Analysis and Reliability Unit Commitment |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1010 ! RTC – NP 6: Adjustment Period and Real-Time Operations |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1011 ! RTC – NP 8: Performance Monitoring |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1012 ! RTC – NP 9: Settlement and Billing |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1013 ! RTC – NP 1, 2, 16, and 25: Overview, Definitions and Acronyms, Registration and Qualification of Market Participants, and Market Suspension and Restart |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1014 ! BESTF-4 Energy Storage Resource Single Model |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1029 ! BESTF-6 DC-Coupled Resources |
ERCOT |
Approved |
Jun 26 '20 |
Dec 8 '20 |
| NPRR1055 ! Market Notice and ERCOT Discretion re Late-Filed NOIE Eligibility Attestations for PTP Obligations with Links to an Option Bid Awards |
ERCOT |
Approved |
Nov 9 '20 |
Dec 8 '20 |
| OBDRR020 ! RTC – Methodology for Setting Maximum Shadow Prices for Network and Power Balance Constraints |
ERCOT |
Approved |
Mar 25 '20 |
Dec 8 '20 |
| NPRR1038 ! BESTF-8 Limited Exemption from Reactive Power Requirements for Certain Energy Storage Resources |
ERCOT |
Approved |
Aug 6 '20 |
Oct 13 '20 |
| SCR811 ! Addition of Intra-Hour PhotoVoltaic Power Forecast to GTBD Calculation |
ERCOT |
Approved |
Jul 29 '20 |
Oct 13 '20 |
| NOGRR218 ! Removal of Annual Disturbance Monitoring Equipment Database Submission Requirement |
System Protection... |
Approved |
Aug 19 '20 |
Sep 23 '20 |
| NPRR1025 ! Remove Real-Time On-Line Reliability Deployment Price from Ancillary Service Imbalance Calculation |
Lower Colorado River... |
Rejected |
Jun 4 '20 |
Sep 23 '20 |
| NPRR1015 ! Clarification of DAM implementation of NPRR863 Phase 2 |
ERCOT |
Approved |
Mar 25 '20 |
Aug 11 '20 |
| NPRR1020 ! Allow Some Integrated Energy Storage Designs to Calculate Internal Loads |
Tesla |
Approved |
Apr 28 '20 |
Aug 11 '20 |
| NPRR1030 ! Modify Allocator for CRR Auction Revenue Distribution |
ERCOT |
Approved |
Jul 1 '20 |
Aug 11 '20 |
| NOGRR204 ! Related to NPRR989, BESTF-1 Energy Storage Resource Technical Requirements |
ERCOT |
Approved |
Dec 16 '19 |
Jun 9 '20 |
| NPRR933 ! Reporting of Demand Response by Retail Electric Providers and Non-Opt-In Entities |
ERCOT |
Approved |
Apr 16 '19 |
Jun 9 '20 |
| NPRR987 ! BESTF-3 Energy Storage Resource Contribution to Physical Responsive Capability and Real-Time On-Line Reserve Capacity Calculations |
ERCOT |
Approved |
Dec 9 '19 |
Jun 9 '20 |
| NPRR989 ! BESTF-1 Energy Storage Resource Technical Requirements |
ERCOT |
Approved |
Dec 16 '19 |
Jun 9 '20 |
| NPRR1006 ! Update Real-Time On-Line Reliability Deployment Price Adder Inputs to Match Actual Data |
TIEC |
Approved |
Mar 3 '20 |
Jun 9 '20 |
| NPRR1018 ! Clarifications Regarding ERCOT Suspension or Termination of a QSE and Participation by a Virtual or Emergency QSE |
ERCOT |
Approved |
Apr 1 '20 |
Jun 9 '20 |
| NPRR1019 ! Pricing and Settlement Changes for Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT |
ERCOT |
Approved |
Apr 1 '20 |
Jun 9 '20 |
| NPRR1021 ! Adjustments to the Default Uplift Invoice Process |
Reliant Energy... |
Approved |
Apr 28 '20 |
Jun 9 '20 |
| NPRR1022 ! Submission of Banking Information |
ERCOT |
Approved |
May 12 '20 |
Jun 9 '20 |
| OBDRR017 ! Related to NPRR987, BESTF-3 Energy Storage Resource Contribution to Physical Responsive Capability and Real-Time On-Line Reserve Capacity Calculations |
ERCOT |
Approved |
Dec 9 '19 |
Jun 9 '20 |
| SCR809 ! Changes to External Telemetry Validations in Resource Limit Calculator |
ERCOT |
Approved |
Jan 10 '20 |
Jun 9 '20 |
| NPRR997 ! Natural Gas Pipeline Coordination Requirements for Resource Entities with Natural Gas Generation Resources |
ERCOT |
Approved |
Feb 7 '20 |
Apr 14 '20 |
| NPRR998 ! ERS Deployment and Recall Messages |
ERCOT |
Approved |
Feb 20 '20 |
Apr 14 '20 |
| RRGRR021 ! Dynamic Model Requirement for TSAT |
ERCOT |
Approved |
Sep 18 '19 |
Feb 26 '20 |
| NPRR986 ! BESTF-2 Energy Storage Resource Energy Offer Curves, Pricing, Dispatch, and Mitigation |
ERCOT |
Approved |
Dec 5 '19 |
Feb 11 '20 |
| NPRR988 ! Correction to Conditions for DAM Award Eligibility for PTP Obligations with Links to an Option |
ERCOT |
Approved |
Dec 11 '19 |
Feb 11 '20 |
| NOGRR197 ! Align Responsive Reserve (RRS) Manual Deployment Requirements with Current Practice |
ERCOT |
Approved |
Oct 1 '19 |
Oct 23 '19 |
| NPRR930 ! Process, Pricing, and Cost Recovery for Delayed Resource Outages |
Citigroup |
Approved |
Mar 28 '19 |
Oct 8 '19 |
| NPRR950 ! Switchable Generation Resources Providing Black Start Service |
ERCOT |
Approved |
May 30 '19 |
Oct 8 '19 |
| NPRR925 ! Increasing Minimum Quantity for PTP Obligation Bids |
ERCOT |
Approved |
Feb 27 '19 |
Apr 9 '19 |
| NPRR915 ! Define Limited Duration Resource and Clarify Telemetered Resource Status Requirements |
Luminant Generation LLC |
Approved |
Dec 21 '18 |
Feb 12 '19 |
| NPRR901 ! Switchable Generation Resource Status Code |
ERCOT |
Approved |
Sep 26 '18 |
Dec 11 '18 |
| RRGRR019 ! Related to NPRR901, Switchable Generation Resource Status Code |
ERCOT |
Approved |
Sep 26 '18 |
Dec 11 '18 |
| NPRR890 ! Correction to Calculation of Real-Time LMPs at Logical Resource Node for On-Line Combined Cycle Generation Resources |
ERCOT |
Approved |
Aug 15 '18 |
Oct 9 '18 |
| VCMRR021 ! Related to NPRR847, Exceptional Fuel Cost Included in the Mitigated Offer Cap |
ERCOT |
Approved |
Apr 25 '18 |
Aug 7 '18 |
| VCMRR020 ! Delay the Fuel Adder Sunset Related to VCMRR014, Revise Fuel Adder Factor for Coal and Lignite Resources |
Reliant Energy... |
Approved |
Mar 22 '18 |
May 24 '18 |
| NPRR868 ! As-Built Hub and Load Zone Calculation |
ERCOT |
Approved |
Mar 1 '18 |
Apr 10 '18 |
| NPRR861 ! Clarification of ERCOT’s Authority to Protect Its Jurisdictional Status |
ERCOT |
Approved |
Dec 21 '17 |
Feb 20 '18 |
| NPRR832 ! Disallow PTP Obligation Bids and DAM Energy Bids that Sink at Private Use Network Settlement Points Without a Load Distribution Factor |
Luminant |
Withdrawn |
May 10 '17 |
Nov 9 '17 |
| NPRR833 ! Modify PTP Obligation Bid Clearing Change |
ERCOT |
Approved |
May 31 '17 |
Aug 8 '17 |
| NPRR827 ! Disallow PTP Obligation Bid Award where Clearing Price exceeds Bid Price by $0.25/MW per hour |
Crescent Power, Inc. |
Approved |
Apr 11 '17 |
Jun 13 '17 |
| NPRR830 ! Revision of 4-Coincident Peak Methodology |
ERCOT |
Approved |
Apr 26 '17 |
Jun 13 '17 |
| NPRR831 ! Inclusion of Private Use Networks in Load Zone Price Calculations |
ERCOT |
Approved |
May 3 '17 |
Jun 13 '17 |
| NPRR818 ! Allow Curtailment of Certain DC Tie Load Prior to Declaring Emergency Condition |
Rainbow Energy... |
Approved |
Feb 1 '17 |
Apr 4 '17 |
| NPRR800 ! Revisions to Credit Exposure Calculations to Use Electricity Futures Market Prices |
ERCOT |
Approved |
Aug 30 '16 |
Feb 14 '17 |
| NOGRR164 ! Alignment with NPRR792, Removing Special Protection System (SPS) and adding Remedial Action Scheme (RAS) |
ERCOT |
Approved |
Jul 27 '16 |
Dec 15 '16 |
| NPRR788 ! RMR Study Modifications |
LCRA |
Approved |
Jul 7 '16 |
Oct 11 '16 |
| NPRR793 ! Clarifications to RMR RUC Commitment and Other RMR Cleanups |
ERCOT |
Approved |
Jul 27 '16 |
Oct 11 '16 |
| NPRR795 ! Provisions for Refunds of Capital Contributions Made in Connection with an RMR Agreement |
ERCOT |
Approved |
Aug 2 '16 |
Oct 11 '16 |
| NPRR784 ! Mitigated Offer Caps for RMR Units |
NRG Texas |
Rejected |
Jun 1 '16 |
Aug 9 '16 |
| NOGRR050 ! Resolution of Reporting Issues Related to NPRR219 |
DeAnn Walker on... |
Approved |
Aug 12 '10 |
Jun 14 '16 |
| NPRR766 ! Alignment of System-Wide Discount Factor Description with Operational Adjustments to RDF |
ERCOT |
Approved |
Apr 18 '16 |
Jun 14 '16 |
| RMGRR137 ! Timeline and Completion Process for Correcting Customer Billing Contact Information Files |
Texas SET Working Group |
Approved |
Apr 22 '16 |
May 26 '16 |
| VCMRR014 ! Revise Fuel Adder Factor for Coal and Lignite Resources |
Paul Vinson on... |
Approved |
Apr 27 '16 |
May 26 '16 |
| VCMRR011 ! Timeline for Reviewing Resources Verifiable Costs for Five Year Updates |
ERCOT |
Approved |
Sep 30 '15 |
Oct 29 '15 |
| NPRR680 ! Allow QSEs to Self-Arrange AS Quantities Greater Than Their AS Obligation |
ERCOT |
Approved |
Jan 28 '15 |
Jun 9 '15 |
| NPRR698 ! Clarifications to NPRR595, RRS Load Resource Treatment In ORDC |
ERCOT |
Approved |
Apr 29 '15 |
Jun 9 '15 |
| NOGRR140 ! Posting of the ERCOT Geomagnetic Disturbance Operating Plan |
CenterPoint Energy |
Approved |
Nov 4 '14 |
Jan 29 '15 |
| VCMRR005 ! Fuel Index Price for Resource Definition and Real-Time Make-Whole Payments for Exceptional Fuel Cost Events |
RCWG |
Approved |
Oct 27 '14 |
Dec 18 '14 |
| NPRR664 ! Fuel Index Price for Resource Definition and Real-Time Make-Whole Payments for Exceptional Fuel Cost Events |
RCWG |
Approved |
Oct 22 '14 |
Dec 9 '14 |
| NPRR666 ! Clarification for the CRR Balancing Account |
ERCOT |
Approved |
Oct 30 '14 |
Dec 9 '14 |
| NPRR340 ! Introduction and Definition of Duration-Limited Resources (formerly "Unannounced HSL test for Duration-Limited Resources") |
Praveen Kathpalon on... |
Withdrawn |
Mar 21 '11 |
Oct 23 '14 |
| NPRR643 ! Clarification of MIS Postings for Outages Upon Implementation of SCR774, Enhancement to Outage Scheduler and Reports |
ERCOT |
Approved |
Jul 30 '14 |
Oct 14 '14 |
| RRGRR003 ! Modifications to Improve Wind Forecasting |
ERCOT |
Approved |
Jun 20 '14 |
Oct 14 '14 |
| RRGRR004 ! Steam Pressure Curve Information for Implementation of Regional Reliability Standard BAL-001-TRE-1 |
ERCOT |
Approved |
Aug 15 '14 |
Sep 25 '14 |
| VCMRR004 ! Caps for Energy Storage Resources |
Chamisa Energy |
Approved |
Jul 30 '14 |
Aug 28 '14 |
| NPRR626 ! Reliability Deployment Price Adder (formerly "ORDC Price Reversal Mitigation Enhancements") |
Luminant Energy Company, LLC |
Approved |
May 16 '14 |
Aug 12 '14 |
| NPRR631 ! Corrections to Definition of Credible Single Contingency |
ERCOT |
Approved |
Jun 17 '14 |
Aug 12 '14 |
| NPRR605 ! Ancillary Service Make-Whole Payments Under a Watch |
Exelon Generation |
Rejected |
Mar 17 '14 |
May 29 '14 |
| NOGRR130 ! Alignment with NPRR555 and NPRR434 |
ERCOT |
Approved |
Mar 13 '14 |
Apr 24 '14 |
| RMGRR120 ! Sharyland Updates |
BJ Flowers on behalf... |
Approved |
Jan 20 '14 |
Apr 24 '14 |
| NPRR533 ! PCRR Eligibility Requirements (formerly "Clarification of PCRR Eligibility Requirements") |
ERCOT |
Approved |
Mar 29 '13 |
Apr 8 '14 |
| NPRR576 ! Changing Non-Spin Service to be Dispatched by ERCOT (formerly "Changing Non-Spin Service to an Off-Line Service") |
GDF Suez NA Inc. |
Approved |
Oct 24 '13 |
Apr 8 '14 |
| NPRR596 ! External Load Serving Entities |
ERCOT |
Approved |
Jan 29 '14 |
Apr 8 '14 |
| NPRR598 ! Clarify Inputs to PRC and ORDC |
ERCOT |
Approved |
Feb 12 '14 |
Apr 8 '14 |
| NPRR602 ! Exemption for Sharyland Brady Load Transition |
Reliant Energy... |
Approved |
Mar 10 '14 |
Apr 8 '14 |
| NPRR603 ! ERS Settlement and Service Types |
ERCOT |
Approved |
Mar 10 '14 |
Apr 8 '14 |
| NOGRR127 ! Synchronization with NPRR564, Thirty-Minute Emergency Response Service (ERS) and Other ERS Revisions |
ERCOT |
Approved |
Jan 21 '14 |
Feb 27 '14 |
| NPRR556 ! Resource Adequacy During Transmission Equipment Outage |
Tenaska Power Services |
Approved |
Jul 10 '13 |
Feb 11 '14 |
| NPRR591 ! As-Built Clarification and Corrections Related to NPRR568 and NPRR555 |
ERCOT |
Approved |
Jan 9 '14 |
Feb 11 '14 |
| NPRR571 ! ERS Weather-Sensitive Loads Requirements |
Earth Networks |
Approved |
Oct 2 '13 |
Dec 10 '13 |
| NPRR575 ! Clarification of the RUC Resource Buy-Back Provision for Ancillary Services |
GDF Suez NA Inc. |
Approved |
Oct 23 '13 |
Dec 10 '13 |
| NPRR578 ! Restores RUC Decommitment Charge Language Deleted in NPRR416 |
ERCOT |
Approved |
Nov 6 '13 |
Dec 10 '13 |
| NPRR579 ! Amendment to the Minimum PTP Option Bid Price Approval Timeline |
ERCOT |
Approved |
Nov 6 '13 |
Dec 10 '13 |
| COPMGRR036 ! Alignment with NPRR570, Reduce RTM Settlement Timeline to Operating Day Plus Five |
Harika Basaran and... |
Approved |
Sep 30 '13 |
Dec 3 '13 |
| RRGRR001 ! Section 2, Resource Registration Glossary |
Brenda Hampton on... |
Approved |
Nov 11 '13 |
Dec 3 '13 |
| NPRR550 ! Modifications to Planning Reserve Margin Inputs |
GATF |
Approved |
Jun 27 '13 |
Nov 19 '13 |
| NPRR564 ! Thirty-Minute Emergency Response Service (ERS) and Other ERS Revisions |
ERCOT |
Approved |
Aug 21 '13 |
Nov 19 '13 |
| NPRR568 ! Real-Time Reserve Price Adder Based on Operating Reserve Demand Curve |
ERCOT |
Approved |
Sep 19 '13 |
Nov 19 '13 |
| NPRR570 ! Reduce RTM Settlement Timeline to Operating Day Plus Five |
Harika Basaran and... |
Approved |
Sep 30 '13 |
Nov 19 '13 |
| LPGRR050 ! Changes the Review of Additional Validations from a Quarterly Review to an Annual Review |
Ed Echols on behalf... |
Approved |
Sep 30 '13 |
Nov 7 '13 |
| NPRR524 ! Resource Limits in Providing Ancillary Service |
GDF Suez Energy... |
Approved |
Mar 5 '13 |
Sep 17 '13 |
| NPRR532 ! Performance Measurement and Verification and Telemetry Requirements for Load Resources Providing Non-Spin |
DSWG |
Approved |
Mar 26 '13 |
Sep 17 '13 |
| NPRR552 ! Additional Counter-Party Criteria |
ERCOT |
Approved |
Jul 3 '13 |
Sep 17 '13 |
| NPRR554 ! Clarification of Future Credit Exposure Calculation |
ERCOT |
Approved |
Jul 3 '13 |
Sep 17 '13 |
| NPRR555 ! Load Resource Participation in Security-Constrained Economic Dispatch |
ERCOT |
Approved |
Jul 3 '13 |
Sep 17 '13 |
| NPRR557 ! Clarification of Treatment of Holidays for RTM Settlement Timeline (formerly "Administrative Changes for August 1, 2013 Nodal Protocols") |
ERCOT |
Approved |
Jul 11 '13 |
Sep 17 '13 |
| NPRR551 ! Posting of Annual Planning Model |
ERCOT |
Approved |
Jul 1 '13 |
Sep 16 '13 |
| NOGRR119 ! Revisions to Load Shed Table |
ERCOT |
Approved |
Jun 18 '13 |
Jul 2 '13 |
| NPRR444 ! Supplemental Reliability Deployments |
Morgan Stanley Capital Group |
Rejected |
Feb 22 '12 |
May 14 '13 |
| NPRR511 ! Correction to Emergency Energy Settlement Language |
ERCOT |
Approved |
Jan 2 '13 |
May 14 '13 |
| NPRR514 ! Seasonal Generation Resource |
Luminant Energy Company LLC |
Approved |
Feb 4 '13 |
May 14 '13 |
| NPRR530 ! Transfers of Specific NOIEs Within a NOIE Load Zone to a Competitive Load Zone |
The City of Georgetown |
Approved |
Mar 20 '13 |
May 14 '13 |
| NPRR534 ! Clarification of QSE Responsibilities to Provide Service in NOIE Territory |
STEC, CPS Energy,... |
Approved |
Apr 3 '13 |
May 14 '13 |
| NPRR487 ! QSGR Dispatch Adjustment |
Luminant Energy LLC |
Approved |
Oct 3 '12 |
Mar 19 '13 |
| NPRR509 ! Shortened RTM Settlement Timeline |
Harika Basaran on... |
Approved |
Dec 20 '12 |
Mar 19 '13 |
| NPRR518 ! Removal of Notification Requirement for Disclosures of Protected Information Required by CFTC |
ERCOT |
Approved |
Feb 6 '13 |
Mar 19 '13 |
| NPRR520 ! Real-Time Mitigation Rules and Creation of a Real-Time Constraint Competitiveness Test |
ERCOT |
Approved |
Feb 6 '13 |
Mar 19 '13 |
| NPRR521 ! Transitional CRR Auction Capacity Value for Initial CRR Long-Term Auction Sequence |
ERCOT |
Approved |
Feb 15 '13 |
Mar 19 '13 |
| SCR773 ! Addition of Regulation Feedback to Generation to be Dispatched Calculation |
David Kee on behalf... |
Approved |
Jan 30 '13 |
Mar 19 '13 |
| NPRR506 ! Correction of Reconfiguration SASM Language Inconsistency |
ERCOT |
Approved |
Dec 5 '12 |
Jan 15 '13 |
| NPRR507 ! Correction of PTP Obligation Settlement Language Related to NPRR322 and NPRR470 |
ERCOT |
Approved |
Dec 6 '12 |
Jan 15 '13 |
| NPRR461 ! Energy Storage Settlements Consistent With PUCT Project 39917 |
ERCOT |
Approved |
May 2 '12 |
Dec 11 '12 |
| NPRR497 ! Corrections to NPRR400 |
ERCOT |
Approved |
Oct 31 '12 |
Dec 11 '12 |
| NPRR501 ! Correct ERS Self-Provision Settlement Calculation |
ERCOT |
Approved |
Nov 14 '12 |
Dec 11 '12 |
| NPRR485 ! Clarification for Fuel Adder Provisions |
Luminant |
Approved |
Oct 1 '12 |
Nov 13 '12 |
| NOGRR095 ! Type 2 Special Protection System Submissions |
Calpine |
Rejected |
May 10 '12 |
Nov 1 '12 |
| NPRR464 ! SASM Procurement Reporting |
NRG Texas Power LLC |
Approved |
May 15 '12 |
Sep 18 '12 |
| NPRR470 ! Real-Time PTP Option Modeling Language Cleanup |
ERCOT |
Approved |
Aug 2 '12 |
Sep 18 '12 |
| NPRR472 ! Implementation Clarifications for Consideration of DC Tie Lines and Outages in CCTs |
ERCOT |
Approved |
Aug 8 '12 |
Sep 18 '12 |
| NPRR477 ! Exception for Block Load Transfers at Presidio |
American Electric... |
Approved |
Aug 17 '12 |
Sep 18 '12 |
| NOGRR099 ! SPS Procedure Changes for Consistency with NERC Reliability Standards |
NPGRTF |
Withdrawn |
May 30 '12 |
Sep 7 '12 |
| NPRR459 ! Better Matching Forward Collateralization with Forward Risk in the Real-Time Market |
NRG |
Approved |
May 1 '12 |
Jul 17 '12 |
| NPRR468 ! Alignment of System-Wide Offer Cap and Scarcity Pricing Mechanism Language with PUCT Substantive Rules |
ERCOT |
Approved |
Jun 13 '12 |
Jul 17 '12 |
| NPRR469 ! Modifications to CCTs |
M. Wagner at the... |
Approved |
Jun 15 '12 |
Jul 17 '12 |
| NPRR453 ! Separation of Year 1 and Year 2 of the Annual CRR Auctions by Timing |
ERCOT |
Approved |
Apr 2 '12 |
Jun 19 '12 |
| NPRR463 ! CRR Auction Structure Enhancements |
DC Energy Texas LLC |
Approved |
May 7 '12 |
Jun 19 '12 |
| NOGRR092 ! Synchronization with NPRR451 |
ERCOT |
Approved |
Apr 5 '12 |
Jun 7 '12 |
| NPRR442 ! Energy Offer Curve Requirement for Generation Resources Providing Reliability Must-Run Service |
Morgan Stanley |
Approved |
Feb 3 '12 |
May 15 '12 |
| NPRR448 ! Clarification of Database Query Results |
Kathryn Thurman on... |
Approved |
Mar 7 '12 |
Apr 17 '12 |
| NPRR449 ! Reduce Maximum CRR Transaction Limit in Auctions |
WMS |
Approved |
Mar 13 '12 |
Apr 17 '12 |
| NPRR450 ! Revise Requirements for Contracts to Procure Additional Capacity to Alleviate Emergency Conditions (formerly "Revise Board Approval Requirement for Contracts to Procure Additional Capacity to Alleviate Emergency Conditions") |
ERCOT |
Approved |
Mar 14 '12 |
Apr 17 '12 |
| NPRR451 ! Implementation of New P.U.C. Subst. Rule 25.507, Electric Reliability Council of Texas (ERCOT) Emergency Response Service (ERS) |
ERCOT |
Approved |
Mar 15 '12 |
Apr 17 '12 |
| NPRR432 ! Deployment of Resources to Alleviate Anticipated Emergency Conditions (formerly "Deployment of Resources to Alleviate Imminent Emergency Conditions") |
ERCOT |
Approved |
Dec 2 '11 |
Feb 21 '12 |
| NPRR434 ! Increase the Capacity Limitation of a Generation Resource Providing RRS |
Robert Helton on... |
Approved |
Dec 27 '11 |
Feb 21 '12 |
| NPRR435 ! Requirements for Energy Offer Curves in the Real Time SCED for Generation Resources Committed in RUC |
ERCOT |
Approved |
Jan 3 '12 |
Feb 21 '12 |
| NPRR437 ! Allow Aggregation of Multiple Generators Into A Single Resource For Market and Engineering Modeling |
ERCOT |
Approved |
Jan 23 '12 |
Feb 21 '12 |
| NOGRR087 ! Reinsertion of Network Operations Modeling Requirements |
Planning Working Group (PLWG) |
Approved |
Nov 30 '11 |
Jan 5 '12 |
| NPRR351 ! SCED Look-Ahead Step 1: Pricing: Calculate Non-Binding Prices and Basepoints for Initial Research into SCED Look-Ahead and allow Consumers to have a Forward Price Projection (formerly "Calculate and Post Projected Non-Binding LMPs for the Next 15 Minutes") |
WMS |
Approved |
Apr 13 '11 |
Dec 12 '11 |
| NPRR426 ! Standing Non-Spin Deployment in the Operating Hour for Generation Resources Providing On-Line Non-Spin |
ERCOT |
Approved |
Nov 9 '11 |
Dec 12 '11 |
| NPRR427 ! Energy Offer Curve Requirements for Generation Resources Assigned Reg-Up and RRS |
ERCOT |
Approved |
Nov 9 '11 |
Dec 12 '11 |
| NPRR428 ! Energy Offer Curve Requirements for Generation Resources Assigned Non-Spin Responsibility |
ERCOT |
Approved |
Nov 9 '11 |
Dec 12 '11 |
| NOGRR082 ! Synchronization with NPRR258 and Alignment of Primary Frequency Response Test Procedures |
ERCOT |
Approved |
Oct 7 '11 |
Dec 1 '11 |
| NPRR315 ! Revision of Responsive Reserve Measure to High Emergency Limit (formerly "Revision of Responsive Reserve Measure to Net Dependable Capability) |
Morgan Stanley |
Rejected |
Feb 2 '11 |
Dec 1 '11 |
| NPRR400 ! Eliminate Unsecured Credit for CRR Auctions and for Future Credit Exposure and Eliminate Netting of FCE with CCE |
ERCOT |
Approved |
Aug 3 '11 |
Oct 18 '11 |
| NPRR365 ! Change in Resource Outage Approvals from Eight to 45 Days (formerly "Change in Resource Outage Approvals from Eight to 90 Days") |
ERCOT |
Approved |
May 4 '11 |
Sep 20 '11 |
| NPRR396 ! Reduce Standard O&M Costs |
City of Eastland |
Approved |
Jul 19 '11 |
Sep 20 '11 |
| NOGRR069 ! Relay Misoperation Reporting Changes for Consistency with ERO-RAPA Proposal |
SPWG |
Approved |
Apr 6 '11 |
Sep 1 '11 |
| NPRR347 ! Single Daily Settlement Invoice and Updates to Credit Calculations, including addition of a Minimum Collateral Exposure Component (formerly "Counter-Party Invoice and Single Daily Settlement Invoice") |
ERCOT |
Approved |
Apr 6 '11 |
Aug 16 '11 |
| NPRR357 ! Revisions to Collateral Requirements Concerning CRR Auctions (formerly "Multi-Month CRR Auction and Revisions to Collateral Requirements") |
Luminant |
Approved |
May 4 '11 |
Aug 16 '11 |
| NPRR369 ! Black Start Service Requirement Revisions |
ERCOT |
Approved |
May 18 '11 |
Aug 16 '11 |
| NPRR388 ! Clarification of Quick Start Generation Resource Performance Criteria |
Luminant Energy |
Approved |
Jul 6 '11 |
Aug 16 '11 |
| NPRR390 ! Clarification of the Applicability of the Use of the Refund Option |
ERCOT |
Approved |
Jul 6 '11 |
Aug 16 '11 |
| NPRR392 ! Credit Review During CRR Auction |
ERCOT |
Approved |
Jul 14 '11 |
Aug 16 '11 |
| NPRR376 ! CRR Volume Limitation Enhancements |
DC Energy |
Approved |
Jun 7 '11 |
Jul 19 '11 |
| NPRR387 ! Hydro RRS Deployment Under Frequency Relay Set Point |
LCRA |
Approved |
Jun 15 '11 |
Jul 19 '11 |
| NPRR312 ! Clarification of QSE Requirements for Split Generation Resources |
ERCOT |
Approved |
Feb 1 '11 |
Jul 18 '11 |
| NOGRR068 ! Hydro-Responsive Reserve |
ERCOT |
Approved |
Mar 31 '11 |
Jul 7 '11 |
| NPRR367 ! Shaping of PTP Options Taken to Real-Time to Match Forecasted Load |
CPS Energy |
Rejected |
May 12 '11 |
Jun 23 '11 |
| NPRR368 ! Clarification of the Purpose of Point-to-Point Options |
CPS Energy |
Rejected |
May 12 '11 |
Jun 23 '11 |
| NPRR371 ! Telemetered LSL for QSGR |
Topaz Power |
Withdrawn |
May 31 '11 |
Jun 23 '11 |
| NPRR322 ! Real-Time PTP Option Modeling |
Luminant Energy Company LLC |
Approved |
Feb 10 '11 |
Jun 21 '11 |
| SCR765 ! Public Aggregated Wind Dashboard |
Jackie Ashbaugh on... |
Approved |
Apr 18 '11 |
Jun 21 '11 |
| NPRR352 ! Real-Time HSL Telemetry for WGRs |
ERCOT |
Approved |
Apr 13 '11 |
May 17 '11 |
| SCR764 ! Public Access to Select MIS Dashboards |
Jackie Ashbaugh on... |
Approved |
Apr 7 '11 |
May 17 '11 |
| NPRR350 ! Change to the Security Classification of the System Ancillary Service Capacity Monitor Dashboard |
Jackie Ashbaugh on... |
Approved |
Apr 11 '11 |
May 16 '11 |
| NPRR316 ! Negative Self-Arranged Ancillary Services Quantity (formerly "Negative Self-Arranged Ancillary Services") |
Morgan Stanley |
Approved |
Feb 2 '11 |
Apr 19 '11 |
| NPRR320 ! Minimum PTP Option Bid and Settlement (formerly "Minimum PTP Option Bids and CRR Auction Fees") |
Bob Wittmeyer |
Approved |
Feb 8 '11 |
Apr 19 '11 |
| NPRR329 ! Security Classification Changes for Extracts/Reports |
MIS User Group |
Approved |
Feb 23 '11 |
Apr 19 '11 |
| NPRR331 ! Addition of the Balance of the Year PCRR Allocation |
ERCOT |
Approved |
Feb 25 '11 |
Apr 19 '11 |
| NPRR335 ! TSP Request for Interval Data |
Jennifer Bevill on... |
Approved |
Mar 1 '11 |
Apr 19 '11 |
| NPRR339 ! Modifications to Heuristic Rules to Determine LMP at De-energized Electrical Bus and Treatment of CRR Offers at De-energized Settlement Points |
ERCOT |
Approved |
Mar 17 '11 |
Apr 19 '11 |
| NPRR341 ! Remove Ancillary Service Offers from SASM that do not Meet the Lead Time |
ERCOT |
Approved |
Mar 23 '11 |
Apr 19 '11 |
| NPRR342 ! Notification and Actions to Address Outcomes Inconsistent With Efficient Operation of the ERCOT Market |
ERCOT |
Approved |
Mar 30 '11 |
Apr 19 '11 |
| NPRR343 ! CRR Bid and PTP Obligation Bid Criteria Change |
ERCOT |
Approved |
Mar 29 '11 |
Apr 19 '11 |
| NOGRR062 ! Require Voltage Ride-Through Capability for IRRs |
ERCOT |
Approved |
Mar 3 '11 |
Apr 7 '11 |
| NOGRR057 ! Daily Report Containing Loss of Generation Greater than 450 MW |
LCRA |
Approved |
Jan 6 '11 |
Mar 22 '11 |
| NPRR303 ! Requirement to Post PTP Options Cleared in DAM or Taken to Real-Time |
Luminant Energy Company, LLC |
Approved |
Dec 16 '10 |
Mar 22 '11 |
| NPRR305 ! Timeline for Calculating the Value of X |
VCWG |
Approved |
Jan 11 '11 |
Mar 22 '11 |
| NPRR307 ! Change SASM Offer Procedures |
Morgan Stanley |
Approved |
Jan 11 '11 |
Mar 22 '11 |
| NPRR323 ! Correct DAM Credit Exposure Language and Enable Qualified Expiring CRRs to Offset PTP Bid Exposure |
Tenaska Power Services |
Approved |
Feb 10 '11 |
Mar 22 '11 |
| NPRR325 ! Price Correction During SCED Process Failure |
ERCOT |
Approved |
Feb 10 '11 |
Mar 22 '11 |
| SCR760 ! Recommended Changes Needed for Information Model Manager and Topology Processor for Planning Models |
Wesley Woitt on... |
Approved |
Nov 4 '10 |
Mar 22 '11 |
| LPGRR044 ! Addition of Distributed Generation (DG) Load Profiles |
Ernie Podraza on... |
Approved |
Jan 31 '11 |
Mar 3 '11 |
| COPMGRR023 ! Creating Section 6, Commercial System Model and Subsection 8.3 Settlement Detail |
Michelle Trenary on... |
Withdrawn |
Nov 2 '10 |
Feb 3 '11 |
| NPRR302 ! Correct Fuel Type Language for Mitigated Offer Cap |
Morgan Stanley |
Approved |
Dec 7 '10 |
Jan 18 '11 |
| OBDRR001 ! Texas SET Implementation Guides Revision Process |
Jennifer Frederick... |
Approved |
Dec 13 '10 |
Jan 18 '11 |
| NPRR293 ! Requirement to Post PTP Obligation Quantities Awarded in DAM (formerly "Requirement to Post CRR Option and Obligation Quantities Cleared in DAM or Taken to Real Time") |
Luminant Energy Company, LLC |
Approved |
Nov 3 '10 |
Dec 14 '10 |
| NPRR295 ! Synchronization of Protocol for Generation Resource Designation as Mothballed or Decommissioned |
ERCOT |
Approved |
Nov 11 '10 |
Dec 14 '10 |
| RMGRR091 ! Accelerated Disconnect and Reconnect for Customers with Advanced Meters |
Jennifer Frederick... |
Approved |
Oct 21 '10 |
Dec 8 '10 |
| RMGRR092 ! Changes to Implement an Interim Solution for Critical Care Status and Secondary Contact Information |
Jennifer Frederick... |
Approved |
Nov 3 '10 |
Dec 8 '10 |
| LPGRR041 ! Distributed Generation (DG) to Sync with NPRR208 Language Effective on Nodal Go-Live |
Ernie Podraza and Ed... |
Approved |
Sep 23 '10 |
Nov 4 '10 |
| NOGRR048 ! Synchronization with OGRR240, CREZ Facility Protection and Control Requirements |
AEPSC |
Approved |
Jul 23 '10 |
Nov 4 '10 |
| NOGRR051 ! Synchronization with OGRR192 and OGRR238 |
ERCOT |
Approved |
Aug 17 '10 |
Oct 7 '10 |
| NOGRR053 ! Synchronization with OGRR226, Generation Resource Response Time Requirement |
Frank Owens on... |
Approved |
Sep 15 '10 |
Oct 7 '10 |
| PGRR001 ! Planning Guide -- Section 2, Process for Planning Guide Revision |
Planning Working Group (PLWG) |
Approved |
Jun 2 '10 |
Jul 20 '10 |
| RMGRR087 ! Meter Tampering Business Processes |
Michael Matlock and... |
Approved |
May 11 '10 |
Jun 15 '10 |
| LPGRR037 ! Replace Wording Truncated from LPGRR035 |
PWG |
Approved |
Dec 30 '09 |
Feb 4 '10 |
| LPGRR035 ! Addition of Time Of Use Schedules (TOUS) to Profiles with Interval Data Recorder (IDR) Meter Data Type Codes for Advanced Meters |
Chris Rowley with TXU Energy |
Approved |
Sep 14 '09 |
Nov 5 '09 |
| NOGRR030 ! Synchronization -- Total Transmission Capacity Correction |
ERCOT |
Approved |
Sep 3 '09 |
Oct 1 '09 |
| RMGRR080 ! Define E-mail Address Format for the Detail Record in the Customer Billing Contact Information File |
Jennifer Frederick... |
Approved |
Sep 1 '09 |
Oct 1 '09 |
| NOGRR025 ! Monitoring Programs for QSEs, TSPs, and ERCOT |
ERCOT |
Approved |
Feb 6 '09 |
Sep 15 '09 |
| RMGRR079 ! Changes to Support Revisions to the PUCT POLR and Expedited Switch Rules |
Jennifer Frederick... |
Approved |
Jun 28 '09 |
Aug 18 '09 |
| RMGRR078 ! Adding Additional Fields to the Customer Billing Contact Information File (formerly "Add E-mail Field to the Customer Billing Contact Information File") |
Jennifer Frederick... |
Approved |
May 22 '09 |
Jul 21 '09 |
| RMGRR077 ! Prepay Priority Code 05 -- Disconnect for Non-pay and Reconnect after DNP |
Ed Echols on behalf of Oncor |
Approved |
May 22 '09 |
Jul 9 '09 |
| SCR754 ! Replace Email Delivery of WGRPP Forecasts (formerly "WGRPP Forecasts Posted on Zonal TML") |
ERCOT |
Approved |
Dec 23 '08 |
Apr 22 '09 |
| SCR745 ! Retail Market Outage Evaluation and Resolution |
TXU Electric Delivery |
Approved |
May 12 '05 |
Feb 17 '09 |
| SCR751 ! Nodal -- Power Balance Shadow Price Cap Curve for SCED (formerly titled "Nodal -- Shadow Price Cap") |
Marguerite Wagner on... |
Approved |
Oct 30 '08 |
Jan 20 '09 |
| LPGRR031 ! Profile Decision Tree Changes For Distributed Renewable Generation |
Ernie Podraza on... |
Approved |
Sep 8 '08 |
Nov 17 '08 |
| RMGRR068 ! Out-Flow Power from Distributed Renewable Generation Facilities |
Rob Bevill on behalf... |
Approved |
Sep 29 '08 |
Nov 6 '08 |
| RMGRR063 ! Mass Transition Revisions Resulting from June 2008 Lessons Learned Workshop |
Rob Bevill on behalf... |
Approved |
Jul 29 '08 |
Sep 26 '08 |
| RMGRR064 ! Correcting Retail Market Guide for Leapfrog processes to synch up with ERCOT’s system logic |
Rob Bevill and Kathy... |
Approved |
Jul 29 '08 |
Sep 10 '08 |
| LPGRR030 ! Distributed Renewable Generation Modifications |
Ernest Podraza on... |
Approved |
Mar 26 '08 |
May 20 '08 |
| COPMGRR006 ! Demand Response Solution |
Jennifer Garcia on... |
Withdrawn |
Feb 5 '08 |
Mar 6 '08 |
| RMGRR061 ! POLR to POLR Transfer Process |
Texas SET Working Group |
Rejected |
Jan 28 '08 |
Mar 6 '08 |
| RMGRR058 ! Layout Modification to Customer Billing Contact Information File |
Karen Farley on... |
Approved |
Aug 1 '07 |
Sep 18 '07 |
| LPGRR024 ! Residential (RES) Profile Segment Determination Algorithm Correction |
Carl Raish, ERCOT |
Approved |
Jun 18 '07 |
Jun 28 '07 |
| RMGRR052 ! File Naming Convention for Customer Billing Contact Information |
Market Coordination... |
Approved |
Apr 30 '07 |
Jun 7 '07 |
| LPGRR019 ! Revision of Holidays Tab in Profile Model Spreadsheets |
Profiling Working Group |
Approved |
Jan 23 '07 |
Mar 8 '07 |
| RMGRR050 ! Mass Transition Process for Events Initiated Prior to a Weekend or ERCOT Holiday and Additional Clarifications, |
Kathy Scott and Rob... |
Approved |
Feb 5 '07 |
Mar 8 '07 |
| LPGRR016 ! Load Profile Transition Mitigation |
Profiling Working Group |
Approved |
Oct 13 '06 |
Dec 12 '06 |
| RMGRR047 ! Transfer from Outgoing Provider of Last Resort (POLR) to Incoming POLR upon Termination of POLR Status |
Kathy Scott and Rob... |
Approved |
Nov 1 '06 |
Dec 12 '06 |
| RMGRR046 ! Appendices to Comply with POLR Rule Project 31416 |
Kathy Scott and Rob... |
Approved |
Oct 27 '06 |
Dec 1 '06 |
| RMGRR037 ! Submission of Switch Requests during a Mass Transition Event |
Kathy Scott on... |
Approved |
May 31 '06 |
Jul 6 '06 |
| LPGRR011 ! Correction to LPGRR010 – Load Profile Type Responsibility Change |
ERCOT |
Approved |
Apr 18 '06 |
May 4 '06 |
| LPGRR008 ! Profile ID Assignment Effective Date |
Ernie Prodraza on... |
Approved |
Oct 31 '05 |
Dec 1 '05 |
| RMGRR030 ! Texas SET Version 2.1 Updates |
Kyle Patrick on... |
Approved |
Sep 27 '05 |
Nov 3 '05 |
| RMGRR021 ! Municipal and Cooperative Disconnect Reconnect Process Guide |
DNP |
Approved |
Mar 7 '05 |
Apr 7 '05 |
| SCR730 ! Market Operations Test Environment for Wholesale Market Participants |
TXU |
Approved |
Jul 10 '03 |
Jul 10 '03 |
| SCR724 ! Left-In-Hot CSV Process |
ERCOT |
Approved |
Sep 16 '02 |
Sep 16 '02 |