NPRR #511 · Revision Request
NPRR511 Correction to Emergency Energy Settlement Language
ReasonTo correct language inserted in Section 6.6.9 via NPRR325, Price Correction During SCED Process Failure, which was approved by the ERCOT Board on March 22, 2011. QSGRs which receive a manual override from ERCOT operations, according to paragraph (4) of Section 6.6.9, are already On-Line and therefore should only be compensated per the Energy Offer Curve price capped by the Mitigated Offer Cap with the O&M adjustment described in paragraph (d) of Section 4.4.9.4.1, Mitigated Offer Cap, removed. The intent of the additional O&M adjustment in the Mitigated Offer Cap is to reimburse the QSGRs when they are dispatched by SCED to come On-Line as described in paragraph (3) of Section 6.6.9. Additionally, consolidating paragraph (8) of Section 3.8.3 with paragraph (4) of Section 6.6.9 will remove redundancy.
Created2013-01-17
Approved2013-05-14
Sections Affected
3.8.36.6.9
Summary
This NPRR clarifies the Settlement of QSGRs when ERCOT Operations issues a manual override.
Action Log 5 milestones
-
Jan 17
PRSDeferred/Tabled→ PRS Consideration
-
Feb 21
PRSRecommended for Approval→ TAC Consideration
-
Mar 7
TACDeferred/Tabled→ TAC Consideration
-
May 2
TACRecommended for Approval→ ERCOT Board Consideration
-
May 14
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Feb 21 '13 | PRS | To recommend approval of NPRR511 as revised by PRS. | Passed |
| May 2 '13 | TAC | To recommend approval of NPRR511 as recommended by PRS in the 2/21/13 PRS Report and as amended by the 4/15/13 WMS comments. | Passed |
Documents 11
| Name | Type | Posted | Classification |
|---|---|---|---|
| 511NPRR-01 Correction to Emergency Energy Settlement Language 01 | doc | Jan 2 '13 | Revision Request |
| 511NPRR-02 Impact Analysis 010213 | doc | Jan 2 '13 | Staff Report |
| 511NPRR-03 PRS Report 011713 | doc | Jan 21 '13 | Committee Report |
| 511NPRR-04 ERCOT Comments 020413 | doc | Feb 19 '13 | Revision Request Comments |
| 511NPRR-05 PRS Report 022113 | doc | Feb 22 '13 | Committee Report |
| 511NPRR-06 Luminant Energy Comments 030413 | doc | Mar 4 '13 | Revision Request Comments |
| 511NPRR-07 ERCOT Comments 030513 | doc | Mar 5 '13 | Revision Request Comments |
| 511NPRR-08 TAC Report 030713 | doc | Mar 8 '13 | Committee Report |
| 511NPRR-09 WMS Comments 041513 | doc | Apr 15 '13 | Revision Request Comments |
| 511NPRR-10 TAC Report 050213 | doc | May 3 '13 | Committee Report |
| 511NPRR-11 Board Report 051413 | doc | May 14 '13 | Committee Report |
Meetings That Took It Up 9
| Date | Meeting | Committee | Status |
|---|---|---|---|
| May 14 '13 | Board of Directors Meeting | BOARD | Concluded |
| May 2 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Apr 12 '13 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Mar 21 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Mar 13 '13 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Mar 7 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Feb 27 '13 | Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting | CREDITWG | Concluded |
| Feb 21 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Jan 17 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |