NPRR #428 · Revision Request
NPRR428 Energy Offer Curve Requirements for Generation Resources Assigned Non-Spin Responsibility
ReasonTo address the Commission’s discussion raised at the October 27, 2011 Public Utility Commission of Texas (PUCT) Open Meeting regarding Project No. 37897, PUC Proceeding Relating to Resource and Reserve Adequacy and Shortage Pricing.
Created2011-11-17
Approved2011-12-12
Sections Affected
6.4.3.1
Summary
This Nodal Protocol Revision Request (NPRR) adds a requirement for the Energy Offer Curve to be at or above $120 for On-Line Non-Spinning Reserve (Non-Spin) capacity and at or above $180 for Off-Line Non-Spin capacity. If Non-Spin Ancillary Service Resource Responsibility is reassigned to a Generation Resource during the Adjustment Period in accordance with Section 6.4.6, QSE-Requested Decommitment of Resources and Changes to Ancillary Service Resource Responsibility of Resources, the Qualified Scheduling Entity (QSE) shall submit an Energy Offer Curve that meets the requirements of Section 6.4.3.1 for the Generation Resource newly assigned Ancillary Service Resource Responsibility for Non-Spin prior to the end of the Adjustment Period. If the Ancillary Service Resource Responsibility for Non-Spin is reassigned in accordance with Section 6.4.6 from a Generation Resource that experiences a Forced Outage, Derate, or Startup Loading Failure during the Operating Period, the QSE shall submit an Energy Offer Curve that meets the requirements of Section 6.4.3.1 as soon as reasonably practicable after the event. QSE updates to an Energy Offer Curve entered at the end of the Adjustment Period become effective in ERCOT systems at the next Operating Period. Therefore, if Non-Spin is moved from one Generation Resource to another in the QSE's portfolio during an Operating Hour, any change to the Energy Offer Curve will be effective in the next Operating Period. There will not be any validation rules to verify the requirements added by this NPRR. The onus is on all QSEs to make the submission/telemetry changes needed to implement these new requirements.
Action Log 3 milestones
-
Nov 17
PRSRecommended for Approval→ TAC Consideration
-
Dec 1
TACRecommended for Approval→ ERCOT Board Consideration
-
Dec 12
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Nov 17 '11 | PRS | To recommend approval of NPRR428 as revised by PRS; an effective date of January 5, 2012; and to forward NPRR428 to TAC | Passed |
| Dec 1 '11 | TAC | To recommend approval of NPRR428 as recommended by PRS in the 11/17/11 PRS Report, as amended by the 11/29/11 ERCOT comments and as revised by TAC | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 428NPRR-01 Energy Offer Curve Requirements for Generation Resour | doc | Nov 9 '11 | Revision Request |
| 428NPRR-02 Impact Analysis 110911 | doc | Nov 9 '11 | Staff Report |
| 428NPRR-03 Austin Energy Comments 111611 | doc | Nov 16 '11 | Revision Request Comments |
| 428NPRR-04 PRS Report 111711 | doc | Nov 21 '11 | Committee Report |
| 428NPRR-05 ERCOT Comments 112911 | doc | Nov 29 '11 | Revision Request Comments |
| 428NPRR-06 STEC Comments 113011 | doc | Nov 30 '11 | Revision Request Comments |
| 428NPRR-07 TAC Report 120111 | doc | Dec 2 '11 | Committee Report |
| 428NPRR-08 Board Report 121211 | doc | Dec 12 '11 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 12 '11 | Board of Directors Meeting | BOARD | Concluded |
| Dec 1 '11 | TAC Meeting | TAC | Concluded |
| Nov 17 '11 | PRS Meeting | PRS | Concluded |