NPRR #352 · Revision Request
NPRR352 Real-Time HSL Telemetry for WGRs
- PRS Apr 21 '11
- TAC May 5 '11
- BOARD May 17 '11
- PUCT —
ReasonThe logic that has been implemented per the current Protocol language has resulted in the underestimation of potential wind power output following a release from curtailment for individual WGRs. This in turn has led to larger than desired control and response oscillations when operating near system transmission limits. The proposed language will create a more clear and consistent view of the real power capabilities of WGRs for ERCOT’s Dispatch systems.
Created2011-04-21
Approved2011-05-17
Sections Affected
6.5.5.2
Summary
This Nodal Protocol Revision Request (NPRR) changes the process by which Qualified Scheduling Entities (QSEs) determine the High Sustained Limits (HSLs) to telemeter for Wind-powered Generation Resources (WGRs). The requirement that QSEs set the HSL equal to output immediately following a release from curtailment is removed. Instead QSEs will be expected to use their best judgment to determine the output capability of the WGR with the expectation that the value will consider the net real power of the WGR, turbine availability, weather conditions, and whether the WGR output is being affected by compliance with a Security-Constrained Economic Dispatch (SCED) instruction.
Timeline
- Apr 13
-
Apr 21
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To recommend approval of NPRR352 as submitted and to forward NPRR352 to TAC.” — Passed→ TAC consideration of NPRR352
-
May 5
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR352 as recommended by PRS in the 4/21/11 PRS Report” — Passed→ ERCOT Board Consideration
-
May 17
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR352 as recommended by TAC in the 5/5/11 TAC Report.” — Passed