NPRR #1087 · Revision Request
NPRR1087 Prohibit Participation of Critical Loads as Load Resources or ERS Resources
ReasonAddresses current operational issues
Created2021-08-12
Approved2021-10-28
Sections Affected
2.13.6.1and 3.14.3.1
Summary
This NPRR defines “Critical Load” and adds language in Section 3.6.1 to prohibit the registration and participation of such Loads as Load Resources or ERS Resources. The revisions proposed in this NPRR also require any Resource Entity that owns or controls a currently registered Load Resource to ensure and attest that the Load Resource is not located behind an Electric Service Identifier (ESI ID) for a Critical Load, or if it is located behind such an ESI ID, that the Load Resource itself is not the Critical Load or else has available backup generation or another technology that will ensure the Load’s continued availability during an emergency deployment. If a Resource Entity cannot provide the required attestation for any currently registered Load Resource after a reasonable submission period, the Load Resource will not be permitted to submit any offer to provide Ancillary Services. Any Resource Entity seeking to register a new Load Resource will also be required to submit such an attestation as a condition of registration. This NPRR also requires a Qualified Scheduling Entity (QSE) representing an ERS Resource to ensure and attest that the ERS Resource is not located behind an ESI ID for a Critical Load, or if it is located behind such an ESI ID, that the ERS Resource itself is not the Critical Load or else has available backup generation or another technology that ensures the ERS Resource’s continued availability during emergency deployment. To foreclose the possibility that backup generation supporting one or more Critical Loads could be offered as an ERS Generator, this NPRR also requires the QSE to ensure and attest that the ERS Resource offered does not support a Critical Load.
Action Log 5 milestones
-
Aug 12
PRSDeferred/Tabled→ PRS for consideration
-
Sep 16
PRSRecommended for Approval→ TAC for consideration
-
Sep 29
TACRecommended for Approval→ Board for consideration
-
Oct 22
BOARDRecommended for Approval→ PUCT for consideration
-
Oct 28
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Sep 16 '21 | PRS | To recommend approval of NPRR1087 as amended by the 9/3/21 ERCOT comments; and to forward to TAC NPRR1087 and the Impact Analysis | Passed |
| Sep 29 '21 | TAC | To recommend approval of NPRR1087 as recommended by PRS in the 9/16/21 PRS Report as amended by the 9/24/21 Enel X comments and the Revised Impact Analysis | Passed |
| Oct 22 '21 | BOARD | To recommend approval of NPRR1087 as recommended by TAC in the 9/29/21 TAC Report as amended by the 10/21/21 ERCOT comments and the Revised Impact Analysis | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Sep 29 '21 | TAC | Motion Passes | 29 | 1 | 0 | xls |
| Sep 16 '21 | PRS | Motion Carries | 5.5 | 0.5 | 0 | xls |
| Aug 12 '21 | PRS | Motion Carries | 6 | 1 | 1 | xls |
Documents 25
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Oct 22 '21 | Board of Directors Special Meeting | BOARD | Concluded |
| Sep 29 '21 | TAC Meeting by Webex Only | TAC | Concluded |
| Sep 16 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Aug 19 '21 | Workshop (Webex only) - NPRR1087, Prohibit Participate of Critical Loads and Generation Resource Support Loads as Load Resources or ERS Resources | Concluded | |
| Aug 12 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Jul 30 '21 | DSWG Meeting by Webex Only | DSWG | Concluded |