NPRR #1109 · Revision Request

NPRR1109  Process for Reinstating Decommissioned Generation Resources

Approved Urgent sponsor ERCOT posted 2021-11-09 ercot.com
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2021-11-10
Approved2021-12-16
Sections Affected
3.14.1.9 and Section 22 Attachment H
Summary
This Nodal Protocol Revision Request (NPRR) allows a Resource Entity to bring a Decommissioned Generation Resource back to service if it submits a Notification of Change of Generation Resource Designation notifying ERCOT of the intended return to service within three years of the date the Generation Resource was removed from the ERCOT Network Operations Model. This NPRR gives ERCOT and the interconnecting Transmission and/or Distribution Service Provider (TDSP) discretion to require any needed studies testing, metering, or facility upgrades to ensure the reliable interconnection of the Generation Resource.
Action Log 5 milestones
Ballots
DateBodyResultYesNoAbstain
Nov 29 '21 TAC Motion Passes 21 2 6 xls
Nov 17 '21 PRS Motion Carries 3.5 1.5 12 xls
Nov 17 '21 PRS Motion Fails 2.75 4.25 9 xls
Nov 10 '21 PRS Motion Carries 7 0 0 xls
Nov 10 '21 PRS Motion Carries 4.3 0.7 7 xls
Documents 11
NameTypePostedClassification
1109NPRR-01 Process for Reinstating Decommissioned Generation Resources 110921 docx Nov 9 '21 Revision Request
1109NPRR-02 Impact Analysis 110921 docx Nov 9 '21 Staff Report
1109NPRR-03 PRS Ballot 111021 xls Nov 15 '21 Revision Request Ballot
1109NPRR-04 PRS Ballot 111021 xls Nov 15 '21 Revision Request Ballot
1109NPRR-05 PRS Report 111021 docx Nov 15 '21 Committee Report
1109NPRR-06 PRS Ballot 111721 xls Nov 22 '21 Revision Request Ballot
1109NPRR-07 PRS Report 111721 docx Nov 22 '21 Committee Report
1109NPRR-08 TAC Ballot 112921 xls Dec 1 '21 Revision Request Ballot
1109NPRR-09 TAC Report 112921 docx Dec 1 '21 Committee Report
1109NPRR-10 Board Report 121021 docx Dec 10 '21 Committee Report
1109NPRR-11 PUCT Report 121621 docx Dec 16 '21 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Nov 29 '21 TAC Meeting by Webex Only TAC Concluded
Nov 17 '21 PRS Meeting by Webex Only PRS Concluded
Nov 10 '21 PRS Meeting by Webex Only PRS Concluded