RMGRR068  Out-Flow Power from Distributed Renewable Generation Facilities

Approved Urgent sponsor Rob Bevill on behalf of Texas SET Working Group posted 2008-09-29 ercot.com
ReasonHB 3693, PURA §§39.914 and 39.916, and P.U.C. Subst. R. 25.213
Created2008-10-01
Sections Affected
7.14
Summary
This RMGRR adds a new section that describes the process by which owners of Distributed Renewable Generation (DRG) may receive credit (via their Retail Electric Provider’s (REP’s) Qualified Scheduling Entity (QSE)) for out-flow power delivered to the grid. Most importantly, this section describes the metering that is required and how the monthly out-flow generation value will be transported on the Texas SET (Texas SET) 867_03, Monthly Usage, and 867_02, Historical Usage, transactions without changing the Texas SET Implementation Guides -- i.e., no "Texas SET change." In addition, this new section will also broadly describe the settlement processes that will be used to account for out-flow power. These settlement processes are detailed in Protocol Revision Request (PRR) 756 and Load Profiling Guide Revision Request (LPGRR) 030.
Action Log 3 milestones
Amendments
DateBodyMotionResult
Oct 15 '08RMS To recommend approval of RMGRR068 as revised by RMS.Passed
Documents 5
NameTypePostedClassification
068RMGRR-01 Out-Flow Power from Distributed Renewable Generation doc Sep 29 '08 Revision Request
068RMGRR-02 Urgency Vote Ballot 100108 xls Oct 2 '08 Revision Request Ballot
068RMGRR-03 Impact Analysis 101408 doc Oct 14 '08 Staff Report
068RMGRR-04 RMS Recommendation Report 101508 doc Oct 17 '08 Committee Report
068RMGRR-05 TAC Action Report 110608 doc Nov 10 '08 Committee Report
Meetings That Took It Up 2
DateMeetingCommitteeStatus
Nov 6 '08 TAC Meeting TAC Concluded
Oct 15 '08 RMS Meeting RMS Concluded