NPRR #591 · Revision Request

NPRR591  As-Built Clarification and Corrections Related to NPRR568 and NPRR555

Approved Urgent sponsor ERCOT posted 2014-01-09 ercot.com
ReasonThis NPRR aligns the Protocols with the necessary implementation of the Settlement provisions of NPRR568, and provides additional data for QSE shadow Settlement. This NPRR also corrects NPRR555 language to reflect approval of NPRR568.
Created2014-01-16
Approved2014-02-11
Sections Affected
6.4.3.1.16.5.7.6.2.36.7.48.1.1.2.1.7
Summary
This NPRR proposes changes that clarify ERCOT’s intended implementation of the Settlement formulas in NPRR568 and that align the Protocols with the Settlement mechanisms that ERCOT’s system design and requirements analysis has concluded are essential to implement NPRR568. In effect this NPRR provides "as-built" modifications to the requirements of NPRR568. This NPRR proposes the following clarifying and corrective language in Section 6.7.4: 1) Repairs an erroneous reference made in paragraph (3); 2) Details the Settlement inputs to the Off-Line reserve calculation that will be utilized in Phase 1 implementation of NPRR568 in lieu of the RTOFF30 telemetry, which will be available in Phase 2; 3) Removes Real-Time On-Line Non-Spin Schedule for Generation Resources (RTOLNSRS) from the calculation of the On-Line and Off-Line reserves because it has no impact on the calculated result for the Real-Time Ancillary Service imbalance quantity (as currently written, it is added into the Qualified Scheduling Entity’s (QSE’s) value for On-Line capacity (RTOLCAP) but subsequently subtracted back out of the value during the calculation of the QSE’s imbalance quantity (RTASOLIMB), thus having no impact on the calculated value); 4) Clarifies intermediate calculations for QSE-level data that ERCOT, through its design discussions, has determined must be performed within the Settlement system rather than in the Market Management System (MMS), thereby providing additional billing determinants necessary for shadow Settlement (calculated values include: RTASOFF, RTRUCNBBRESP, RTNCLRNSRESP, RTCLRNSRESP, RTRMRRESP, RTNCLRRRS, RTOLHSL, RTMGQ, RTCLRREG, RTCLRRRS, RTNCLRNS, RTCLRNS, RTRUCRESP, RTCLRNPF, and RTCLRLSL); and 5) Makes additional clarifying edits to various variable definitions, in light of the additional settlement data points. This NPRR also corrects one reference to "OFF10" in Section 8.1.1.2.1.7 that should have been a reference to "OFF30." In addition, this NPRR updates grey-boxed language associated with NPRR555 to reflect the subsequent approval of NPRR568. In new Section 6.4.3.1.1, RTM Energy Bid Criteria, references to Protocol sections that were deleted by NPRR568 have been deleted. Also, in Section 6.5.7.6.2.3, references to "ONRL Resource Status" have been deleted from the NPRR555 grey box, as this Resource Status will not be used by Load Resources providing Non-Spin following NPRR555 implementation.
Action Log 3 milestones
Amendments
DateBodyMotionResult
Jan 16 '14PRS To recommend approval of NPRR591 as revised by PRS and to forward NPRR591 to TAC.Passed
Documents 5
NameTypePostedClassification
591NPRR-01 As-Built Clarification and Corrections Related to NPR doc Jan 9 '14 Revision Request
591NPRR-02 Impact Analysis 010914 doc Jan 9 '14 Staff Report
591NPRR-03 PRS Report 011614 doc Jan 28 '14 Committee Report
591NPRR-04 TAC Report 012814 doc Jan 29 '14 Committee Report
591NPRR-05 Board Report 021114 doc Feb 14 '14 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Feb 11 '14 Board of Directors Meeting BOARD Concluded
Jan 28 '14 TAC Meeting TAC Concluded
Jan 16 '14 PRS Meeting PRS Concluded