NPRR #1086 · Revision Request

NPRR1086  Recovery, Charges, and Settlement for Operating Losses During an LCAP Effective Period

Approved Urgent sponsor ERCOT posted 2021-07-14 ercot.com
ReasonMeets Strategic goals / regulatory requirements
Created2021-07-15
Approved2021-08-19
Sections Affected
2.14.4.116.8 (new)6.8.1 (new)6.8.2 (new)6.8.3 (new)6.8.3.1 (new)6.8.3.1.1 (new)6.8.3.2 (new)and 6.8.4 (new)
Summary
This Nodal Protocol Revision Request (NPRR) aligns the Protocols with the order amending 16 TAC § 25.505 in Project No. 51871 (51871 Order), which modifies the value of the Low System-Wide Offer Cap (LCAP) by eliminating a provision that ties the value of LCAP to the natural gas price index, and adding a provision that ensures that a Resource Entity (through its Qualified Scheduling Entity (QSE)) can recover its actual marginal costs when a scarcity pricing situation occurs while the LCAP is in effect (LCAP Effective Period). An LCAP Effective Period occurs when the Peaker Net Margin (PNM) during a calendar year exceeds a threshold of three times the cost of new entry for new generation plants. During an LCAP Effective Period, the System-Wide Offer Cap (SWCAP) will be set to the LCAP for the remainder of the calendar year.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Jul 21 '21PRS To recommend approval of NPRR1086 as amended by the 7/20/21 Luminant comments; and to forward to TAC NPRR1086 and the Impact Analysis with a recommended effective date of upon PUCT approvalPassed
Jul 28 '21TAC To recommend approval of NPRR1086 as recommended by PRS in the 7/21/21 PRS Report as amended by the 7/27/21 TIEC comments; and the Revised Impact AnalysisPassed
Ballots
DateBodyResultYesNoAbstain
Jul 28 '21 TAC Motion Passes 20 3 6 xls
Jul 28 '21 TAC Motion Fails 12 13 4 xls
Jul 21 '21 PRS Motion Carries 3.83333 2.16667 5 xls
Jul 21 '21 PRS Motion Carries 7 0 0 xls
Jul 15 '21 PRS Motion Carries 7 0 1 xls
Jul 15 '21 PRS Motion Carries 6.75 0.25 1 xls
Documents 19
NameTypePostedClassification
1086NPRR-01 Recovery, Charges, and Settlement for Operating Losses During an LCAP Effective Period 071421 docx Jul 14 '21 Revision Request
1086NPRR-02 Impact Analysis 071421 docx Jul 14 '21 Staff Report
1086NPRR-03 Luminant Comments 071421 docx Jul 14 '21 Revision Request Comments
1086NPRR-04 ERCOT Comments 071521 docx Jul 15 '21 Revision Request Comments
1086NPRR-05 PUCT Staff Comments 071521 docx Jul 15 '21 Revision Request Comments
1086NPRR-06 PRS Ballot 071521 xls Jul 19 '21 Revision Request Ballot
1086NPRR-07 PRS Report 071521 docx Jul 19 '21 Committee Report
1086NPRR-08 ERCOT Comments 072021 docx Jul 20 '21 Revision Request Comments
1086NPRR-09 Exelon Comments 072021 docx Jul 20 '21 Revision Request Comments
1086NPRR-10 Luminant Comments 072021 docx Jul 20 '21 Revision Request Comments
1086NPRR-11 PRS Ballot 072121 xls Jul 22 '21 Revision Request Ballot
1086NPRR-12 PRS Report 072121 docx Jul 22 '21 Committee Report
1086NPRR-13 Joint Commenters Comments 072221 docx Jul 22 '21 Revision Request Comments
1086NPRR-14 Revised Impact Analysis 072721 docx Jul 27 '21 Staff Report
1086NPRR-15 TIEC Comments 072721 docx Jul 27 '21 Revision Request Comments
1086NPRR-16 TAC Ballot 072821 xls Jul 30 '21 Revision Request Ballot
1086NPRR-17 TAC Report 072821 docx Aug 3 '21 Committee Report
1086NPRR-18 Board Report 081021 docx Aug 11 '21 Committee Report
1086NPRR-19 PUCT Report 081921 docx Aug 19 '21 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Aug 10 '21 Urgent Board of Directors Meeting – Teleconference Available by Webcast BOARD Concluded
Jul 28 '21 TAC Meeting by Webex Only TAC Concluded
Jul 21 '21 Special PRS Meeting by Webex Only PRS Concluded
Jul 15 '21 PRS Meeting by Webex Only PRS Concluded