NPRR #1101 · Revision Request
NPRR1101 Create Non-Spin Deployment Groups made up of Generation Resources Providing Off-Line Non-Spinning Reserve and Load Resources that are Not Controllable Load Resources Providing Non-Spinning Reserve
ReasonAddresses current operational issues. Market efficiencies or enhancements
Created2021-11-10
Approved2021-12-16
Sections Affected
6.5.7.6.2.3
Summary
This NPRR modifies the deployment grouping requirements for Load Resources that are not Controllable Load Resources (“NCLRs”) providing Non-Spinning Reserve (Non-Spin) to include Generation Resources providing Off-Line Non-Spin. This deployment grouping process only addresses NCLR and Off-Line Generation Resources. Other Resources providing Non-Spin are not addressed in the proposed revisions.
Action Log 4 milestones
-
Nov 10
PRSRecommended for Approval→ TAC for consideration
-
Nov 29
TACRecommended for Approval→ Board for consideration
-
Dec 10
BOARDRecommended for Approval→ PUCT for Consideration
-
Dec 16
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Nov 29 '21 | TAC | To recommend approval of NPRR1101 as recommended by PRS in the 11/10/21 PRS Report as amended by the 11/19/21 ERCOT comment. | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Nov 29 '21 | TAC | Motion Passes | 29 | 0 | 0 | xls |
| Nov 10 '21 | PRS | Motion Carries | 7 | 0 | 1 | xls |
| Nov 10 '21 | PRS | Motion Carries | 7 | 0 | 1 | xls |
Documents 11
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1101NPRR-01 Create Non-Spin Deployment Groups made up of Generation Resources Providing Off-Line Non-Spinning Reserve and Not Controllable Load Resources Providing Non-Spinning Reserve 102021 | docx | Oct 20 '21 | Revision Request |
| 1101NPRR-02 Preliminary Impact Analysis 102021 | docx | Oct 20 '21 | Staff Report |
| 1101NPRR-03 Impact Analysis 110821 | docx | Nov 8 '21 | Staff Report |
| 1101NPRR-04 PRS Ballot 111021 | xls | Nov 12 '21 | Revision Request Ballot |
| 1101NPRR-05 PRS Ballot 111021 | xls | Nov 12 '21 | Revision Request Ballot |
| 1101NPRR-06 PRS Report 111021 | docx | Nov 12 '21 | Committee Report |
| 1101NPRR-07 ERCOT Comments 111921 | docx | Nov 19 '21 | Revision Request Comments |
| 1101NPRR-08 TAC Ballot 112921 | xls | Nov 30 '21 | Revision Request Ballot |
| 1101NPRR-09 TAC_Report 112921 | docx | Nov 30 '21 | Committee Report |
| 1101NPRR-10 Board Report 121021 | docx | Dec 10 '21 | Committee Report |
| 1101NPRR-11 PUCT Report 121621 | docx | Dec 20 '21 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jan 21 '22 | DSWG Meeting by Webex Only | DSWG | Concluded |
| Nov 29 '21 | TAC Meeting by Webex Only | TAC | Concluded |
| Nov 10 '21 | PRS Meeting by Webex Only | PRS | Concluded |