NPRR #426 · Revision Request

NPRR426  Standing Non-Spin Deployment in the Operating Hour for Generation Resources Providing On-Line Non-Spin

Approved Urgent sponsor ERCOT posted 2011-11-09 ercot.com
ReasonTo address concerns raised at the October 27, 2011 PUCT Open Meeting regarding Project No. 37897.
Created2011-11-17
Approved2011-12-12
Sections Affected
6.5.7.6.2.3
Summary
This Nodal Protocol Revision Request (NPRR) requires Qualified Scheduling Entity (QSE) action that routinely releases certain On-Line Non-Spinning Reserve (Non-Spin) energy to Security-Constrained Economic Dispatch (SCED) without the need for ERCOT to issue a Non-Spin deployment instruction. The changes in Section 6.5.7.6.2.3 do not invalidate any other existing requirements contained in this section. Those Generation Resources not subject to the provisions contained in paragraph (5) of Section 6.5.7.6.2.3 must respond to any Non-Spin deployment or recall instruction issued by ERCOT Operators in accordance with the Technical Advisory Committee (TAC)-approved Non-Spinning Reserve Service Deployment and Recall Procedure. There will not be any validation rules to verify the requirements added by this NPRR. The onus is on all QSEs to make the submission/telemetry changes needed to implement these new requirements.
Action Log 3 milestones
Amendments
DateBodyMotionResult
Nov 17 '11PRS To recommend approval of NPRR426 as revised by PRS, to recommend an effective date of January 5, 2012, and to forward NPRR426 to TAC.Passed
Documents 6
NameTypePostedClassification
426NPRR-01 Standing Non-Spin Deployment in the Operating Hour fo doc Nov 9 '11 Revision Request
426NPRR-02 Impact Analysis 110911 doc Nov 9 '11 Staff Report
426NPRR-03 Austin Energy Comments 111611 doc Nov 16 '11 Revision Request Comments
426NPRR-04 PRS Report 111711 doc Nov 21 '11 Committee Report
426NPRR-05 TAC Report 120111 doc Dec 1 '11 Committee Report
426NPRR-06 Board Report 121211 doc Dec 12 '11 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Dec 12 '11 Board of Directors Meeting BOARD Concluded
Dec 7 '11 WMS Meeting WMS Concluded
Dec 1 '11 TAC Meeting TAC Concluded
Nov 17 '11 PRS Meeting PRS Concluded