NPRR #485 · Revision Request

NPRR485  Clarification for Fuel Adder Provisions

Approved Urgent sponsor Luminant posted 2012-10-01 ercot.com
ReasonClarifies the Nodal Protocol language to allow for consistent application of fuel adders as provided to ERCOT through the verifiable cost process.
Created2012-10-18
Approved2012-11-13
Sections Affected
4.4.9.4.15.6.1.15.6.1.2
Summary
This Nodal Protocol Revision Request (NPRR) will provide for consistent application of the fuel adder that is meant to compensate Resources for the actual cost of transporting and purchasing fuel on the spot market across Mitigated Offer Caps and Reliability Unit Commitment (RUC) instructions, as well as, allow for Resource-specific verifiable costs to be submitted and verified by ERCOT. The Verifiable Cost Manual is currently undergoing updates to provide for consistent application of the value of X across Mitigated Offer Caps and RUC instructions, where the value of X is meant to compensate Resources for the actual cost of transporting and purchasing fuel purchased on the spot market. The fuel adder ($/MMBtu) cost may be submitted for each Resource and verified by ERCOT. The current default value of $0.50/MMBtu will continue to be used by ERCOT when no specific fuel adder has been provided for a Resource. Slight clean-up language is also needed to point to the Verifiable Cost Manual for methodology used to verify those costs, and to define the methodologies used to account for the fuel costs above the Houston Ship Channel price.
Action Log 3 milestones
Documents 6
NameTypePostedClassification
485NPRR-01 Clarification for Fuel Adder Provisions 100112 doc Oct 1 '12 Revision Request
485NPRR-02 Calpine Comments 101212 doc Oct 12 '12 Revision Request Comments
485NPRR-03 PRS Report 101812 doc Oct 23 '12 Committee Report
485NPRR-04 Impact Analysis 102512 doc Oct 25 '12 Staff Report
485NPRR-05 TAC Report 110112 doc Nov 2 '12 Committee Report
485NPRR-06 Board Report 111312 doc Nov 14 '12 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Dec 5 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Nov 13 '12 Board of Directors Meeting BOARD Concluded
Nov 7 '12 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Nov 1 '12 Technical Advisory Committee (TAC) Meeting TAC Concluded
Oct 18 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded