NPRR #1282 · Revision Request

NPRR1282  Ancillary Service Duration under Real-Time Co-Optimization

Approved Urgent sponsor ERCOT posted 2025-04-29 ercot.com
ReasonGeneral system and/or process improvement(s)
Created2025-05-14
Approved2025-07-31
Sections Affected
2.25.5.28.1.1.2.1.18.1.1.2.1.28.1.1.2.1.38.1.1.3.18.1.1.3.2and 8.1.1.3.4
Summary
This Nodal Protocol Revision Request (NPRR) makes changes to the duration requirements for the following Ancillary Services in preparation for Real-Time Co-optimization plus Batteries (RTC+B): Updates duration requirements for Regulation Service and Responsive Reserve (RRS) to thirty minutes; and updates duration requirement for ERCOT Contingency Reserve Service (ECRS) to one hour. This NPRR also updates the requirement for Reliability Unit Commitment (RUC) studies to use a one-hour duration for all Ancillary Service types, excluding Fast Frequency Response (FFR). The changes proposed in this NPRR have no system impacts because these Ancillary Service durations are being incorporated as parameters in the current RTC+B business requirements.
Action Log 4 milestones
Ballots
DateBodyResultYesNoAbstain
May 28 '25 TAC Motion Fails 11 18 0 xls
May 28 '25 TAC Motion Passes 26 2 1 xls
May 14 '25 PRS Motion Carries 4.875 2.125 2 xls
May 14 '25 PRS Motion Carries 7 0 1 xls
May 1 '25 ROS Motion Carries 7.5 0 0 xls
Documents 21
NameTypePostedClassification
1282NPRR-01 Ancillary Service Duration Under Real-Time Co-Optimization 042925 docx Apr 29 '25 Revision Request
1282NPRR-02 Impact Analysis 042925 docx Apr 29 '25 Staff Report
1282NPRR-03 TSSA Comments 050425 docx May 4 '25 Revision Request Comments
1282NPRR-04 Jupiter Power Comments 050725 doc May 7 '25 Revision Request Comments
1282NPRR-05 ERCOT Comments 051225 docx May 12 '25 Revision Request Comments
1282NPRR-06 Joint Commenters Comments 051225 docx May 12 '25 Revision Request Comments
1282NPRR-07 IMM Comments 051325 docx May 13 '25 Revision Request Comments
1282NPRR-08 TSSA Comments 051325 docx May 13 '25 Revision Request Comments
1282NPRR-09a PRS Ballot 051425 xls May 15 '25 Revision Request Ballot
1282NPRR-09b PRS Ballot 051425 xls May 15 '25 Revision Request Ballot
1282NPRR-10 PRS Report 051425 docx May 15 '25 Committee Report
1282NPRR-11 APA Comments 052725 docx May 27 '25 Revision Request Comments
1282NPRR-12 TAC Ballot 052825 xls Jun 2 '25 Revision Request Ballot
1282NPRR-13 TAC Report 052825 docx Jun 2 '25 Committee Report
1282NPRR-14 Jupiter Power Comments 061825 docx Jun 18 '25 Revision Request Comments
1282NPRR-15 ERCOT Comments 061825 docx Jun 18 '25 Revision Request Comments
1282NPRR-16 Plus Power Comments 061925 docx Jun 19 '25 Revision Request Comments
1282NPRR-17 HGP Comments 062025 docx Jun 20 '25 Revision Request Comments
1282NPRR-18 Tesla Comments 062325 docx Jun 23 '25 Revision Request Comments
1282NPRR-19 Board Report 062425 docx Jun 24 '25 Committee Report
1282NPRR-20 PUCT Report 073125 docx Aug 4 '25 Committee Report
Meetings That Took It Up 7
DateMeetingCommitteeStatus
Jun 23 '25 Board of Directors Meeting BOARD Concluded
Jun 18 '25 RTCBTF Meeting RTCBTF Concluded
May 28 '25 TAC Meeting - Webex Only TAC Concluded
May 21 '25 RTCBTF Meeting RTCBTF Concluded
May 14 '25 PRS Meeting PRS Concluded
May 8 '25 RTCBTF Meeting - Webex Only RTCBTF Concluded
May 1 '25 ROS Meeting ROS Concluded