NPRR #556 · Revision Request

NPRR556  Resource Adequacy During Transmission Equipment Outage

Approved Urgent sponsor Tenaska Power Services posted 2013-07-10 ercot.com
ReasonTo address Resource adequacy issues due to Network Operations Model problems.
Created2013-07-18
Approved2014-02-11
Sections Affected
3.10.7.2
Summary
This Nodal Protocol Revision Request (NPRR) adds a requirement for the Network Operations Model so that Resources that are being served by temporary equipment can participate in the ERCOT market as in normal operations.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Dec 19 '13PRS To recommend approval of NPRR556 as amended by the 12/16/13 ROS comments and to bring the Impact Analysis back to PRS for review.Passed
Documents 19
NameTypePostedClassification
556NPRR-01 Resource Adequacy During Transmission Equipment Outag doc Jul 11 '13 Revision Request
556NPRR-02 NDSWG Comments 071613 doc Jul 16 '13 Revision Request Comments
556NPRR-03 PRS Report 071813 doc Jul 22 '13 Committee Report
556NPRR-04 ERCOT Comments 080213 doc Aug 2 '13 Revision Request Comments
556NPRR-05 Calpine Comments 080513 doc Aug 5 '13 Revision Request Comments
556NPRR-06 WMS Comments 081513 doc Aug 15 '13 Revision Request Comments
556NPRR-07 ROS Comments 081913 doc Aug 19 '13 Revision Request Comments
556NPRR-08 OWG Comments 090913 doc Sep 9 '13 Revision Request Comments
556NPRR-09 ERCOT Comments 090913 doc Sep 9 '13 Revision Request Comments
556NPRR-10 Tenaska Power Services Comments 091713 doc Sep 17 '13 Revision Request Comments
556NPRR-11 OWG Comments 092313 doc Sep 23 '13 Revision Request Comments
556NPRR-12 ERCOT Comments 102913 doc Oct 29 '13 Revision Request Comments
556NPRR-13 ROS Comments 111813 doc Nov 18 '13 Revision Request Comments
556NPRR-14 ROS Comments 121613 doc Dec 26 '13 Revision Request Comments
556NPRR-15 PRS Report 121913 doc Dec 26 '13 Committee Report
556NPRR-16 Impact Analysis 011514 doc Jan 15 '14 Staff Report
556NPRR-17 PRS Report 011614 doc Jan 20 '14 Committee Report
556NPRR-18 TAC Report 012814 doc Jan 29 '14 Committee Report
556NPRR-19 Board Report 021114 doc Feb 17 '14 Committee Report
Meetings That Took It Up 22
DateMeetingCommitteeStatus
Feb 11 '14 Board of Directors Meeting BOARD Concluded
Jan 28 '14 TAC Meeting TAC Concluded
Jan 16 '14 PRS Meeting PRS Concluded
Jan 8 '14 WMS Meeting WMS Concluded
Dec 19 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Dec 12 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Dec 11 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Nov 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Nov 14 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Nov 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Nov 5 '13 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Oct 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Oct 15 '13 Network Data Support Working Group (NDSWG) Meeting NDSWG Concluded
Sep 19 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Sep 18 '13 Operations Working Group (OWG) Meetings OWG Concluded
Sep 12 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Sep 4 '13 Network Data Support Working Group (NDSWG) NDSWG Concluded
Aug 22 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 21 '13 Operations Working Group (OWG) Meetings OWG Concluded
Aug 15 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Aug 14 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jul 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded