PGRR #122 · Revision Request
PGRR122 Reliability Performance Criteria for Loss of Load
- ROS now · Consideration
- TAC
- BOARD
- PUCT
ReasonStrategic Plan Objective 1
Created2024-12-05
Sections Affected
4.1.1.2
Summary
This Planning Guide Revision Request establishes a new reliability performance criteria that no more than 1,000 MW of Load may be lost for any single contingency, and also specifies how loss of Load is calculated for this criteria.
Timeline
- Nov 11
-
Dec 5
ROS ROS Meeting - Webex OnlyROSDeferred/Tabled Referred → DWG Referred → PLWG“To table PGRR122 and refer the issue to the Dynamics Working Group (DWG) and the Planning Working Group (PLWG)” — Passed→ ROS for consideration
- Dec 11
-
Dec 18
Listed without action at 2 meetings (Dec 18 '24 – Jan 9 '25)
- Jan 29
- Feb 6
-
Feb 13
Listed without action at 1 meeting
- Mar 4
-
Mar 6
Listed without action at 5 meetings (Mar 6 '25 – May 1 '25)
- Jun 5
-
Jul 10
Listed without action at 12 meetings (Jul 10 '25 – Jun 4 '26)
- Jun 25
-
Jul 9
Listed without action at 1 meeting
- Aug 6
- Aug 20