NPRR #365 · Revision Request
NPRR365 Change in Resource Outage Approvals from Eight to 45 Days (formerly "Change in Resource Outage Approvals from Eight to 90 Days")
ReasonThis NPRR gives ERCOT the ability to coordinate Resource Outages received with less than a 45-day notice with Transmission Outages. This NPRR also proposes to more clearly define ERCOT’s requirements for withdrawing approval (or acceptance) of Resource Outages if reliability of the ERCOT System is at risk.
Created2011-05-19
Approved2011-09-20
Sections Affected
3.1.13.1.4.43.1.63.1.6.43.1.6.53.1.6.63.1.6.83.1.6.93.1.6.10
Summary
Consistent with Recommendation 6B of the March 15, 2011, Report of the Rotating Blackout Operations Task Force of the ERCOT Board, this Nodal Protocol Revision Request (NPRR) revises the deadline for ERCOT approval of Resource Outages from an eight-day notice to a 45-day notice while aligning the new Resource Outage timelines to match those of Transmission Outages.
Action Log 4 milestones
-
May 19
PRSDeferred/Tabled→ PRS Language Consideration
-
Aug 18
PRSRecommended for Approval→ TAC Consideration
-
Sep 1
TACRecommended for Approval→ TAC Consideration of priority and rank
-
Sep 20
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Aug 18 '11 | PRS | To recommend approval of NPRR365 as amended by the 8/12/11 ROS comments and as revised by PRS and to forward NPRR365 to TAC | Passed |
| Sep 1 '11 | TAC | To recommend approval of NPRR365 as recommended by PRS in the 8/18/11 PRS Report and as revised by TAC via roll call vote. | Passed |
Documents 22
| Name | Type | Posted | Classification |
|---|---|---|---|
| 365NPRR-01 Change in Resource Outage Approvals from Eight to 90 | doc | May 4 '11 | Revision Request |
| 365NPRR-02 Impact Analysis 050411 | doc | May 4 '11 | Staff Report |
| 365NPRR-03 Calpine Comments 051211 | doc | May 12 '11 | Revision Request Comments |
| 365NPRR-04 ROS Comments 051711 | doc | May 17 '11 | Revision Request Comments |
| 365NPRR-05 NRG Texas Comments 051811 | doc | May 18 '11 | Revision Request Comments |
| 365NPRR-06 PRS Report 051911 | doc | May 23 '11 | Committee Report |
| 365NPRR-07 Topaz Power Group Comments 060111 | doc | Jun 1 '11 | Revision Request Comments |
| 365NPRR-08 WMS Comments 062011 | doc | Jun 20 '11 | Revision Request Comments |
| 365NPRR-09 ROS Comments 062111 | doc | Jun 21 '11 | Revision Request Comments |
| 365NPRR-10 AEP Comments 071111 | doc | Jul 11 '11 | Revision Request Comments |
| 365NPRR-11 WMS Comments 071811 | doc | Jul 18 '11 | Revision Request Comments |
| 365NPRR-12 Oncor Comments 072111 | doc | Jul 21 '11 | Revision Request Comments |
| 365NPRR-13 NPRR365 Discussion Group Comments 080511 | doc | Aug 5 '11 | Revision Request Comments |
| 365NPRR-14 ERCOT Comments 081211 | doc | Aug 12 '11 | Revision Request Comments |
| 365NPRR-15 ROS Comments 081211 | doc | Aug 12 '11 | Revision Request Comments |
| 365NPRR-16 PRS Report 081811 | doc | Aug 23 '11 | Committee Report |
| 365NPRR-17 ERCOT Comments 082611 | doc | Aug 26 '11 | Revision Request Comments |
| 365NPRR-18 Preliminary Impact Analysis 083111 | doc | Aug 31 '11 | Staff Report |
| 365NPRR-19 TAC Report 090111 | doc | Sep 6 '11 | Committee Report |
| 365NPRR-20 TAC Roll Call Vote 090111 | xls | Sep 6 '11 | Revision Request Ballot |
| 365NPRR-21 Impact Analysis 091311 | doc | Sep 13 '11 | Staff Report |
| 365NPRR-22 Board Report 092011 | doc | Sep 23 '11 | Committee Report |
Meetings That Took It Up 29
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Nov 13 '12 | Board of Directors Meeting | BOARD | Concluded |
| Sep 7 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Aug 15 '12 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Aug 9 '12 | Joint QMWG and ETWG Meeting | QMWG | Concluded |
| Jul 19 '12 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Jul 12 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Jun 13 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| May 16 '12 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| Sep 20 '11 | Board of Directors Meeting | BOARD | Concluded |
| Sep 1 '11 | TAC Meeting | TAC | Concluded |
| Aug 18 '11 | PRS Meeting | PRS | Concluded |
| Aug 11 '11 | ROS Meeting | ROS | Concluded |
| Aug 10 '11 | WMS Meeting | WMS | Concluded |
| Aug 8 '11 | QMWG Meeting | QMWG | Concluded |
| Aug 1 '11 | NPRR365 Discussion | QMWG | Concluded |
| Jul 21 '11 | PRS Meeting | PRS | Concluded |
| Jul 20 '11 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| Jul 13 '11 | WMS Meeting | WMS | Concluded |
| Jul 11 '11 | QMWG Meeting | QMWG | Concluded |
| Jun 23 '11 | PRS Meeting | PRS | Concluded |
| Jun 16 '11 | ROS Meeting | ROS | Concluded |
| Jun 15 '11 | WMS Meeting | WMS | Concluded |
| Jun 15 '11 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| Jun 13 '11 | QMWG Meeting | QMWG | Concluded |
| Jun 1 '11 | Joint OWG/QMWG Meeting | OWG | Concluded |
| May 19 '11 | PRS Meeting | PRS | Concluded |
| May 18 '11 | Operations Working Group (OWG) Meeting | OWG | Concluded |
| May 12 '11 | ROS Meeting | ROS | Concluded |
| May 11 '11 | WMS Meeting | WMS | Concluded |