NOGRR #62 · Revision Request
NOGRR062 Require Voltage Ride-Through Capability for IRRs
ReasonThis NOGRR is being proposed for the following reasons: Due to the expected IRRs to be placed in service over the next few years, lack of VRT capability could pose ERCOT reliability issues in the event of voltage excursions. Concern of sudden voltage changes causing tripping of units without VRT capability. Additionally, although the VRT study indicated there was no need to retrofit existing Wind-powered Generation Resources to add VRT capability, the concern remains if more units without VRT capability are placed in service, especially in west Texas where many existing WGRs do not have VRT capability.
Created2011-03-10
Sections Affected
2.9.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) proposes a requirement for Voltage Ride-Through (VRT) capability for new IRRs
Action Log 2 milestones
-
Mar 10
ROSRecommended for Approval
-
Apr 7
TACApproved
Documents 5
| Name | Type | Posted | Classification |
|---|---|---|---|
| 062NOGRR-01 Require Voltage Ride-Through Capability for IRRs 030 | doc | Mar 3 '11 | Revision Request |
| 062NOGRR-02 Impact Analysis 030311 | doc | Mar 3 '11 | Committee Report |
| 062NOGRR-03 Urgency Vote 030811 | xls | Mar 8 '11 | Revision Request Ballot |
| 062NOGRR-04 ROS Report 031011 | doc | Mar 11 '11 | Committee Report |
| 062NOGRR-05 TAC Report 040711 | doc | Apr 12 '11 | Committee Report |
Meetings That Took It Up 2
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Apr 7 '11 | TAC Meeting | TAC | Concluded |
| Mar 10 '11 | ROS Meeting | ROS | Concluded |