NPRR #930 · Revision Request

NPRR930  Process, Pricing, and Cost Recovery for Delayed Resource Outages

Approved Urgent sponsor Citigroup posted 2019-03-28 ercot.com
ReasonAddresses current operational issues. Meets Strategic goals. Market efficiencies or enhancements.
Created2019-04-11
Approved2019-10-08
Sections Affected
2.12.23.1.4.63.1.6.95.15.5.25.6.5 (new)5.6.5.1 (new)5.6.5.2 (new)5.6.5.3 (new)5.7.25.7.45.86.5.7.36.5.9.3.1.1 (new)and 9.5.6
Summary
This Nodal Protocol Revision Request (NPRR) requires ERCOT to use an Outage Adjustment Evaluation (OAE) process to delay accepted or approved Outages after issuing an Advance Action Notice (AAN) to describe the need and providing time for Qualified Scheduling Entities (QSEs) to adjust their Outage plans. A Resource that receives an Outage Schedule Adjustment (OSA) as a result of an OAE will be made whole to its actual costs incurred due to delaying or canceling and rescheduling the Outage and committing the Resource, as appropriate. In addition, it sets an offer floor for the Resource at $4,500/MWh. Together, these changes will encourage Resources to self-commit to avoid the opportunity cost of offering at a very high price, while making them whole if they do follow ERCOT’s instructions. A QSE with a Resource that is unable to return to service due to reliability reasons may update its Outage to a Forced Outage so that it may continue its Outage plans to support the Resource’s longevity and availability during critical Load periods.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Aug 15 '19PRS To recommend approval of NPRR930 as amended by the 8/14/19 Joint comments as revised by PRS; and to forward to TACPassed
Ballots
DateBodyResultYesNoAbstain
Aug 15 '19 PRS 9 7 3 xls
Documents 24
NameTypePostedClassification
930NPRR-01 Weekly RUC Modifications for Forecasted Emergency Conditions 032819 doc Mar 28 '19 Revision Request
930NPRR-02 Citigroup Comments 040419 doc Apr 4 '19 Revision Request Comments
930NPRR-03 ERCOT Comments 040919 doc Apr 9 '19 Revision Request Comments
930NPRR-04 PRS Report 041119 doc Apr 16 '19 Committee Report
930NPRR-05 Citigroup Comments 050819 doc May 8 '19 Revision Request Comments
930NPRR-06 PRS Report 050919 doc May 10 '19 Committee Report
930NPRR-07 Luminant Comments 051019 doc May 10 '19 Revision Request Comments
930NPRR-08 ERCOT Comments 061019 doc Jun 10 '19 Revision Request Comments
930NPRR-09 PRS Report 061319 doc Jun 14 '19 Committee Report
930NPRR-10 Joint Comments 062419 doc Jun 24 '19 Revision Request Comments
930NPRR-11 Reliant Comments 070119 doc Jul 1 '19 Revision Request Comments
930NPRR-12 ERCOT Comments 071219 doc Jul 12 '19 Revision Request Comments
930NPRR-13 LCRA Comments 071219 doc Jul 12 '19 Revision Request Comments
930NPRR-14 STEC Comments 071519 doc Jul 15 '19 Revision Request Comments
930NPRR-15 ERCOT Comments 080119 doc Aug 1 '19 Revision Request Comments
930NPRR-16 TIEC Comments 081219 doc Aug 12 '19 Revision Request Comments
930NPRR-17 Joint Comments 081419 doc Aug 14 '19 Revision Request Comments
930NPRR-18 PRS Report 081519 doc Aug 20 '19 Committee Report
930NPRR-19 PRS Voting Ballot 081519 xls Aug 20 '19 Revision Request Ballot
930NPRR-20 Credit WG Comments 082119 doc Aug 21 '19 Revision Request Comments
930NPRR-21 Impact Analysis 092419 doc Sep 24 '19 Staff Report
930NPRR-22 ERCOT Comments 092419 doc Sep 24 '19 Revision Request Comments
930NPRR-23 TAC Report 092519 doc Sep 26 '19 Committee Report
930NPRR-24 Board Report 100819 doc Oct 9 '19 Committee Report
Meetings That Took It Up 10
DateMeetingCommitteeStatus
Oct 8 '19 Board of Directors Meeting BOARD Concluded
Sep 25 '19 TAC Meeting TAC Concluded
Aug 15 '19 PRS Meeting PRS Concluded
Jul 17 '19 PRS Meeting PRS Concluded
Jun 25 '19 MSWG Meeting MSWG Concluded
Jun 13 '19 PRS Meeting PRS Concluded
May 16 '19 NPRR930 Workshop Concluded
May 9 '19 PRS Meeting PRS Concluded
Apr 24 '19 Outage Activity Related to OCN Workshop Concluded
Apr 11 '19 PRS Meeting PRS Concluded