NPRR #303 · Revision Request

NPRR303  Requirement to Post PTP Options Cleared in DAM or Taken to Real-Time

Approved Urgent sponsor Luminant Energy Company, LLC posted 2010-12-16 ercot.com
ReasonThe posting of these cleared quantities by hour by Settlement Point are necessary for Market Participants to adequately evaluate the results of the DAM including the accuracy of the Network Operations Model used for the DAM.
Created2011-01-20
Approved2011-03-22
Sections Affected
4.5.3
Summary
This Nodal Protocol Revision Request (NPRR) adds language to specify the need for ERCOT to post quantities of Point-to-Point (PTP) Options and PTP Options with Refund that were not cleared in the Day-Ahead Market (DAM) and taken to Real-Time for Settlement.
Action Log 4 milestones
Documents 9
NameTypePostedClassification
303NPRR-01 Requirement to Post PTP Options Cleared in DAM or Tak doc Dec 16 '10 Revision Request
303NPRR-02 WMS Comments 011311 doc Jan 13 '11 Revision Request Comments
303NPRR-03 PRS Report 012011 doc Jan 24 '11 Committee Report
303NPRR-04 Impact Analysis 021011 doc Feb 11 '11 Staff Report
303NPRR-05 Cost Benefit Analysis 021011 xls Feb 10 '11 Staff Report
303NPRR-06 PRS Report 021711 doc Feb 21 '11 Committee Report
303NPRR-07 Revised Impact Analysis 022411 doc Feb 24 '11 Staff Report
303NPRR-08 TAC Report 030311 doc Mar 4 '11 Committee Report
303NPRR-09 Board Report 032211 doc Mar 22 '11 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Mar 3 '11 TAC Meeting TAC Concluded
Feb 17 '11 PRS Meeting PRS Concluded
Jan 26 '11 Joint CWG/MCWG Meeting CREDITWG Concluded
Jan 20 '11 PRS Meeting PRS Concluded
Jan 12 '11 WMS Meeting WMS Concluded