NPRR #303 · Revision Request
NPRR303 Requirement to Post PTP Options Cleared in DAM or Taken to Real-Time
ReasonThe posting of these cleared quantities by hour by Settlement Point are necessary for Market Participants to adequately evaluate the results of the DAM including the accuracy of the Network Operations Model used for the DAM.
Created2011-01-20
Approved2011-03-22
Sections Affected
4.5.3
Summary
This Nodal Protocol Revision Request (NPRR) adds language to specify the need for ERCOT to post quantities of Point-to-Point (PTP) Options and PTP Options with Refund that were not cleared in the Day-Ahead Market (DAM) and taken to Real-Time for Settlement.
Action Log 4 milestones
-
Jan 20
PRSRecommended for Approval→ PRS Impact Analysis review
-
Feb 17
PRSRecommended for Approval→ TAC consideration of NPRR303
-
Mar 3
TACRecommended for Approval→ ERCOT Board consideration of NPRR303
-
Mar 22
BOARDApproved
Documents 9
| Name | Type | Posted | Classification |
|---|---|---|---|
| 303NPRR-01 Requirement to Post PTP Options Cleared in DAM or Tak | doc | Dec 16 '10 | Revision Request |
| 303NPRR-02 WMS Comments 011311 | doc | Jan 13 '11 | Revision Request Comments |
| 303NPRR-03 PRS Report 012011 | doc | Jan 24 '11 | Committee Report |
| 303NPRR-04 Impact Analysis 021011 | doc | Feb 11 '11 | Staff Report |
| 303NPRR-05 Cost Benefit Analysis 021011 | xls | Feb 10 '11 | Staff Report |
| 303NPRR-06 PRS Report 021711 | doc | Feb 21 '11 | Committee Report |
| 303NPRR-07 Revised Impact Analysis 022411 | doc | Feb 24 '11 | Staff Report |
| 303NPRR-08 TAC Report 030311 | doc | Mar 4 '11 | Committee Report |
| 303NPRR-09 Board Report 032211 | doc | Mar 22 '11 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Mar 3 '11 | TAC Meeting | TAC | Concluded |
| Feb 17 '11 | PRS Meeting | PRS | Concluded |
| Jan 26 '11 | Joint CWG/MCWG Meeting | CREDITWG | Concluded |
| Jan 20 '11 | PRS Meeting | PRS | Concluded |
| Jan 12 '11 | WMS Meeting | WMS | Concluded |