NPRR #1328 · Revision Request
NPRR1328 Establishment of Generation Firming Program
ReasonRegulatory requirements
Created2026-04-15
Sections Affected
1.3.1.12.12.29.5.323V (new)28 (new)28.1 (new)28.2 (new)28.2.1 (new)28.2.2 (new)28.3 (new)28.3.1 (new)28.3.2 (new)28.4 (new)28.5 (new)28.5.1 (new)28.5.2 (new)28.6 (new)28.7 (new)28.8 (new)28.9 (new)28.10 (new)
Summary
This Nodal Protocol Revision Request (NPRR) incorporates the new Generation Firming Program requirements, as required by Public Utility Regulatory Act (PURA) § 39.1592 and the Public Utility Commission of Texas’ (PUCT) rule adopted in 16 Texas Administrative Code § 25.65. The obligation to participate in the Generation Firming Program applies to all Generation Resources with an original Standard Generation Interconnection Agreement (SGIA) executed on or after January 1, 2027, beginning one year after the Generation Resource’s Resource Commissioning Date. Such Generation Resources are required to operate, or be available to operate, at or above the Generation Resource’s Seasonal Average Generation Capability during the Low Operation Reserve Hours in each Firming Season. Generation Resources can satisfy this obligation either through their own performance or via a Firming Transfer with another eligible Resource. This NPRR provides details on the administration of the Generation Firming Program, including definitions, timing requirements, processes for submitting Firming Transfers to ERCOT, specific calculations for measuring performance and applying exemptions, and associated market-facing reporting.
Action Log 1 milestones
-
Apr 15
PRSDeferred/Tabled→ PRS for consideration
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Jul 8 '26 | WMS | Motion Carries | 7.5 | 0 | 0 | xls |
| May 8 '26 | WMS | Motion Carries | 7.5 | 0 | 0 | xls |
| Apr 15 '26 | PRS | Motion Carries | 7 | 0 | 0 | xls |
| Apr 15 '26 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 15
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1328NPRR-01 Establishment of Generation Firming Program 040226 | docx | Apr 2 '26 | Revision Request |
| 1328NPRR-02 Impact Analysis 040226 | docx | Apr 2 '26 | Staff Report |
| 1328NPRR-03 ERCOT Comments 041426 | docx | Apr 14 '26 | Revision Request Comments |
| 1328NPRR-04a PRS Ballot 041526 | xls | Apr 20 '26 | Revision Request Ballot |
| 1328NPRR-04b PRS Ballot 041526 | xls | Apr 20 '26 | Revision Request Ballot |
| 1328NPRR-05 PRS Report 041526 | docx | Apr 20 '26 | Committee Report |
| 1328NPRR-06 TCPA Comments 050726 | docx | May 7 '26 | Revision Request Comments |
| 1328NPRR-07 WMS Ballot 050826 | xls | May 11 '26 | Revision Request Ballot |
| 1328NPRR-08 WMS Comments 051126 | docx | May 11 '26 | Revision Request Comments |
| 1328NPRR-09 TCPA Comments 051926 | docx | May 19 '26 | Revision Request Comments |
| 1328NPRR-10 TSSA Comments 052226 | docx | May 22 '26 | Revision Request Comments |
| 1328NPRR-11 APA and ACP Comments 062226 | docx | Jun 22 '26 | Revision Request Comments |
| 1328NPRR-12 ERCOT Comments 070126 | docx | Jul 1 '26 | Revision Request Comments |
| 1328NPRR-13 WMS Ballot 070826 | xls | Jul 8 '26 | Revision Request Ballot |
| 1328NPRR-14 WMS Comments 070826 | docx | Jul 8 '26 | Revision Request Comments |
Meetings That Took It Up 8
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 15 '26 | PRS Meeting | PRS | Scheduled |
| Jul 8 '26 | WMS Meeting - Webex Only | WMS | Concluded |
| Jun 29 '26 | WMWG Meeting - Webex Only | WMWG | Concluded |
| Jun 10 '26 | PRS Meeting | PRS | Concluded |
| Jun 3 '26 | WMS Meeting | WMS | Concluded |
| May 8 '26 | WMS Meeting | WMS | Concluded |
| May 6 '26 | PRS Meeting | PRS | Concluded |
| Apr 15 '26 | PRS Meeting | PRS | Concluded |