NPRR #568 · Revision Request
NPRR568 Real-Time Reserve Price Adder Based on Operating Reserve Demand Curve
ReasonTo implement the concepts presented and address concerns raised at the January 24, 2013 PUCT workshop regarding Docket No. 40000.
Created2013-10-18
Approved2013-11-19
Sections Affected
2.12.23.5.2.13.5.2.23.5.2.33.5.2.43.5.2.63.96.36.3.26.4.3.16.4.3.2 (delete)6.4.3.3 (delete)6.5.5.26.5.7.36.5.9.26.6.16.6.1.16.6.1.26.6.3.16.6.106.7.4 (new)6.7.5 (new)8.1.18.1.1.28.1.1.2.18.1.1.2.1.6 (new)8.1.1.2.1.7 (new)8.1.1.4.4 (new)8.1.1.4.5 (new)9.5.3
Summary
This NPRR requires ERCOT to implement an Operating Reserve Demand Curve (ORDC) in the Real-Time Market (RTM) to determine the Real-Time price adder for Real Time Settlement Point Prices. The Real-Time price adder reflects the price for reserves available in the ERCOT System based on the loss of Load probability at that reserve level. The addition of this price adder to the Real Time Settlement Point Price ensures that the Real Time Settlement Point Price reflects the opportunity cost of reserve scarcity. A new Other Binding Document, "Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder," a draft of which is attached to this NPRR as Attachment 1, will describe the methodologies for developing the ORDC and determining the reserve price adder using the ORDC. It will also list the values of the parameters to be used. Additional details about the methodology and a backcast based on the methodology can be found in filings under Public Utility Commission of Texas (PUCT) Docket No. 40000, Commission Proceeding to Ensure Resource Adequacy in Texas, and Key Documents posted on the Resource Adequacy Task Force home page . Since Real-Time co-optimization of energy and Ancillary Services will not be implemented at this time, to ensure that Resources are indifferent between providing energy and reserves in Real-Time, an Ancillary Service imbalance Settlement will be performed. Reliability Unit Commitment (RUC) Resources and Reliability Must-Run (RMR) Units are removed from this Ancillary Service imbalance payment for their On-Line capacity in Real-Time since making the payment and clawing it back would result in the same financial outcome but with significant changes to the Protocols.
Action Log 3 milestones
-
Oct 18
PRSRecommended for Approval→ TAC consideration of NPRR568
-
Nov 7
TACRecommended for Approval→ ERCOT Board consideration of NPRR568
-
Nov 19
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 18 '13 | PRS | To recommend approval of NPRR568 as amended by the 10/8/13 Morgan Stanley comments, 10/11/13 ERCOT comments, 10/15/13 EMMT comments and 10/16/13 Luminant comments and as revised by PRS with a recommended priority of 2013, rank of 70 and category of Regulatory; to request that the Impact Analysis separate out the impacts associated with each of the following: (A) the 10/11/13 ERCOT comments (including the revision related to Wind-powered Generation Resources introduced in the 10/15/13 EMMT comments), (B) the 10/8/13 Morgan Stanley comments, and (C) the 10/18/13 PRS revisions; to refer the issue of Load Resources providing OFF10 or OFF30 capacity to WMS for assignment to the Demand Side Working Group (DSWG); and to refer review of the verification of Real-Time Production Potential to WMS for assignment to the Qualified Scheduling Entity (QSE) Managers Working Group (QMWG). | Passed |
| Nov 7 '13 | TAC | To recommend approval of the "Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder" as amended by the 11/6/13 ERCOT comments (Attachment 1) and as revised by TAC with a proposed effective date of upon implementation of NPRR568 and to add the methodology to the Other Binding Document List. | Passed |
Documents 26
Meetings That Took It Up 28
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Apr 6 '15 | WMS Meeting | WMS | Concluded |
| Aug 26 '14 | QMWG Meeting | QMWG | Concluded |
| Jul 29 '14 | QMWG Meeting | QMWG | Concluded |
| Jul 9 '14 | WMS Meeting | WMS | Concluded |
| Jul 1 '14 | QMWG Meeting | QMWG | Concluded |
| Jun 26 '14 | TAC Meeting | TAC | Concluded |
| Jun 4 '14 | WMS Meeting | WMS | Concluded |
| May 29 '14 | TAC Meeting | TAC | Concluded |
| May 21 '14 | QMWG Meeting | QMWG | Concluded |
| May 7 '14 | WMS Meeting | WMS | Concluded |
| May 1 '14 | QMWG Meeting | QMWG | Concluded |
| Apr 24 '14 | TAC Meeting | TAC | Concluded |
| Apr 9 '14 | WMS Meeting | WMS | Concluded |
| Mar 27 '14 | TAC Meeting | TAC | Concluded |
| Mar 5 '14 | WMS Meeting | WMS | Concluded |
| Feb 27 '14 | TAC Meeting | TAC | Concluded |
| Feb 12 '14 | COPS Meeting | COPS | Concluded |
| Feb 11 '14 | Board of Directors Meeting | BOARD | Concluded |
| Jan 28 '14 | TAC Meeting | TAC | Concluded |
| Jan 16 '14 | PRS Meeting | PRS | Concluded |
| Jan 8 '14 | WMS Meeting | WMS | Concluded |
| Dec 3 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Nov 19 '13 | Board of Directors Meeting | BOARD | Concluded |
| Nov 7 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Oct 30 '13 | Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting | CREDITWG | Concluded |
| Oct 17 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Oct 9 '13 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Oct 4 '13 | RATF Workshop - NPRR568, Real-Time Reserve Price Adder Based on Operating Reserve Demand Curve | RATF | Concluded |