NPRR #390 · Revision Request
NPRR390 Clarification of the Applicability of the Use of the Refund Option
ReasonThe PCRR refund option is meant to settle at the lesser of the scheduled output of a Generation Resource or the MW value of the PCRR. As the output schedules of Generation Resources that are not in ERCOT are not available to ERCOT, the PCRR refund option is not applicable when the source is on the non-ERCOT side of a DC Tie.
Created2011-07-21
Approved2011-08-16
Sections Affected
7.4.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the ability to request refund option Pre-Assigned Congestion Revenue Rights (PCRRs) across high voltage Direct Current Ties (DC Ties).
Action Log 3 milestones
-
Jul 21
PRSRecommended for Approval→ TAC consideration of NPRR390
-
Aug 4
TACRecommended for Approval→ ERCOT Board consideration of NPRR390
-
Aug 16
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 390NPRR-01 Clarification of the Applicability of the Use of the | doc | Jul 6 '11 | Revision Request |
| 390NPRR-02 Impact Analysis 070611 | doc | Jul 6 '11 | Staff Report |
| 390NPRR-03 Urgency Vote Ballot 070811 | xls | Jul 11 '11 | Revision Request Ballot |
| 390NPRR-04 PRS Report 072111 | doc | Jul 22 '11 | Committee Report |
| 390NPRR-05 TAC Report 080411 | doc | Aug 5 '11 | Committee Report |
| 390NPRR-06 Board Report 081611 | doc | Aug 16 '11 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Aug 16 '11 | Board of Directors Meeting | BOARD | Concluded |
| Aug 4 '11 | TAC Meeting | TAC | Concluded |
| Jul 21 '11 | PRS Meeting | PRS | Concluded |