ReasonThe PCRR refund option is meant to settle at the lesser of the scheduled output of a Generation Resource or the MW value of the PCRR. As the output schedules of Generation Resources that are not in ERCOT are not available to ERCOT, the PCRR refund option is not applicable when the source is on the non-ERCOT side of a DC Tie.
Created2011-07-21
Approved2011-08-16
Sections Affected
7.4.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the ability to request refund option Pre-Assigned Congestion Revenue Rights (PCRRs) across high voltage Direct Current Ties (DC Ties).
Action Log 3 milestones
Documents 6
NameTypePostedClassification
390NPRR-01 Clarification of the Applicability of the Use of the doc Jul 6 '11 Revision Request
390NPRR-02 Impact Analysis 070611 doc Jul 6 '11 Staff Report
390NPRR-03 Urgency Vote Ballot 070811 xls Jul 11 '11 Revision Request Ballot
390NPRR-04 PRS Report 072111 doc Jul 22 '11 Committee Report
390NPRR-05 TAC Report 080411 doc Aug 5 '11 Committee Report
390NPRR-06 Board Report 081611 doc Aug 16 '11 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Aug 16 '11 Board of Directors Meeting BOARD Concluded
Aug 4 '11 TAC Meeting TAC Concluded