NPRR #390 · Revision Request
NPRR390 Clarification of the Applicability of the Use of the Refund Option
- PRS Jul 21 '11
- TAC Aug 4 '11
- BOARD Aug 16 '11
- PUCT —
ReasonThe PCRR refund option is meant to settle at the lesser of the scheduled output of a Generation Resource or the MW value of the PCRR. As the output schedules of Generation Resources that are not in ERCOT are not available to ERCOT, the PCRR refund option is not applicable when the source is on the non-ERCOT side of a DC Tie.
Created2011-07-21
Approved2011-08-16
Sections Affected
7.4.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the ability to request refund option Pre-Assigned Congestion Revenue Rights (PCRRs) across high voltage Direct Current Ties (DC Ties).
Timeline
- Jul 6
-
Jul 21
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To recommend approval of NPRR390 as submitted and to forward NPRR390 and the Impact Analysis to TAC.” — Passed→ TAC consideration of NPRR390
-
Aug 4
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR390 as recommended by PRS in the 7/21/11 PRS Report.” — Passed→ ERCOT Board consideration of NPRR390
-
Aug 16
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR390 as recommended for approval by TAC in the 8/4/11 TAC Report.” — Passed