NPRR #532 · Revision Request

NPRR532  Performance Measurement and Verification and Telemetry Requirements for Load Resources Providing Non-Spin

Approved Urgent sponsor DSWG posted 2013-03-26 ercot.com
ReasonCurrent market rules relating to Load Resource performance evaluation in Ancillary Services are limited to a methodology best described as "meter-before/meter-after" (as defined in North American Energy Standards Board (NAESB) Demand Response Measurement & Verification standards, adopted by the Federal Energy Regulatory Commission (FERC)). Under this existing methodology, a Load reduction in a deployment event is measured from the Load Resource’s static Load level at the time of Dispatch; the Load Resource must maintain such reduction throughout the event. This works well for industrial consumers with high Load factors, but can lead to either over-provision or under-provision of Demand response by other types of consumers, especially weather-sensitive Loads. NAESB and FERC standards also provide for the baseline methodology, which measures and verifies performance by comparing actual Load to a reliable estimate of what the Load would have been in the absence of the deployment.
Created2013-04-18
Approved2013-09-17
Sections Affected
3.9.14.4.7.2.16.5.5.26.5.7.6.2.38.1.1.2.1.38.1.1.3.38.1.1.4.3
Summary
This Nodal Protocol Revision Request (NPRR) enables participation in the Non-Spinning Reserve (Non-Spin) Service market for Load Resources whose provision of Demand response is most accurately measured and verified using a baseline performance evaluation methodology. The NPRR establishes a method for evaluating Non-Spin performance using a baseline methodology, which compares actual Load to a reliable estimate of what the Load would have been in the absence of the deployment. This NPRR also establishes new telemetry requirements for Qualified Scheduling Entities (QSEs) representing Load Resources in the Non-Spin market to allow ERCOT’s systems to monitor the status and performance of those Load Resources in Real-Time.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Jun 20 '13PRS To recommend approval of NPRR532 as amended by the 6/18/13 Citigroup Energy comments.Passed
Sep 5 '13TAC To recommend approval of NPRR532 as recommended by PRS in the 8/22/13 PRS Report and as amended by the 8/29/13 ERCOT comments.Passed
Documents 17
NameTypePostedClassification
532NPRR-01 Performance Measurement and Verification and Telemetr doc Mar 26 '13 Revision Request
532NPRR-02 PRS Report 041813 doc Apr 22 '13 Committee Report
532NPRR-03 WMS Comments 050913 doc May 9 '13 Revision Request Comments
532NPRR-04 Edison Mission Marketing & Trading Comments 061313 doc Jun 13 '13 Revision Request Comments
532NPRR-05 WMS Comments 061413 doc Jun 14 '13 Revision Request Comments
532NPRR-06 ROS Comments 061713 doc Jun 17 '13 Revision Request Comments
532NPRR-07 ROS Voting Ballot 061713 xls Jun 17 '13 Revision Request Ballot
532NPRR-08 Citigroup Energy Comments 061813 doc Jun 21 '13 Revision Request Comments
532NPRR-09 PRS Report 062013 doc Jun 24 '13 Committee Report
532NPRR-10 ERCOT Comments 071813 doc Jul 18 '13 Revision Request Comments
532NPRR-11 PRS Report 071813 doc Jul 22 '13 Committee Report
532NPRR-12 WMS Comments 081913 doc Aug 19 '13 Revision Request Comments
532NPRR-13 Impact Analysis 081913 doc Aug 19 '13 Staff Report
532NPRR-14 PRS Report 082213 doc Aug 26 '13 Committee Report
532NPRR-15 ERCOT Comments 082913 doc Aug 29 '13 Revision Request Comments
532NPRR-17 TAC Report 090513 doc Sep 5 '13 Committee Report
532NPRR-18 Board Report 091713 doc Sep 18 '13 Committee Report
Meetings That Took It Up 14
DateMeetingCommitteeStatus
Sep 17 '13 Board of Directors Meeting BOARD Concluded
Sep 5 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Aug 28 '13 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting CREDITWG Concluded
Aug 22 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 11 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Jul 10 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jun 20 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 13 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Jun 12 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jun 4 '13 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
May 16 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
May 8 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Apr 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded