NPRR #396 · Revision Request

NPRR396  Reduce Standard O&M Costs

Approved Urgent sponsor City of Eastland posted 2011-07-19 ercot.com
ReasonAt the time of submittal of this NPRR, verifiable costs have been submitted for relatively few Resources, and of those Qualified Scheduling Entities (QSEs) or Resource Entities that have submitted verifiable costs, most have elected to utilize standard O&M costs. NPRR225 permitted Market Participants to use standard O&M costs in the verifiable costs process for the first year of the Nodal Market so as to permit Market Participants additional time to collect and submit actual O&M data and to allow QSEs and Resource Entities to focus on the Nodal Go-Live process. This NPRR provides an additional incentive to submit verifiable costs that include actual O&M data during the years subsequent to 2011.
Created2011-08-18
Approved2011-09-20
Sections Affected
5.6.1
Summary
This Nodal Protocol Revision Request (NPRR) reduces the standard Operations and Maintenance (O&M) costs permitted to be used in lieu of actual, verifiable O&M costs by NPRR225, Standard Cost Option in Verifiable Costs, which was approved by the ERCOT Board in June 2010.
Action Log 3 milestones
Amendments
DateBodyMotionResult
Sep 1 '11TAC To recommend approval of NPRR396 as amended by the 8/26/11 Austin Energy comments.Passed
Documents 8
NameTypePostedClassification
396NPRR-01 Reduce Standard O&M Costs 071911 doc Jul 19 '11 Revision Request
396NPRR-02 WMS Comments 081211 doc Aug 12 '11 Revision Request Comments
396NPRR-03 PRS Report 081811 doc Aug 22 '11 Committee Report
396NPRR-04 ERCOT Comments 082411 doc Aug 25 '11 Revision Request Comments
396NPRR-05 Impact Analysis 082411 doc Aug 24 '11 Staff Report
396NPRR-06 Austin Energy Comments 082611 doc Aug 26 '11 Revision Request Comments
396NPRR-07 TAC Report 090111 doc Sep 2 '11 Committee Report
396NPRR-08 Board Report 092011 doc Sep 21 '11 Committee Report
Meetings That Took It Up 4
DateMeetingCommitteeStatus
Sep 20 '11 Board of Directors Meeting BOARD Concluded
Sep 1 '11 TAC Meeting TAC Concluded
Aug 18 '11 PRS Meeting PRS Concluded
Aug 10 '11 WMS Meeting WMS Concluded