NPRR #396 · Revision Request
NPRR396 Reduce Standard O&M Costs
ReasonAt the time of submittal of this NPRR, verifiable costs have been submitted for relatively few Resources, and of those Qualified Scheduling Entities (QSEs) or Resource Entities that have submitted verifiable costs, most have elected to utilize standard O&M costs. NPRR225 permitted Market Participants to use standard O&M costs in the verifiable costs process for the first year of the Nodal Market so as to permit Market Participants additional time to collect and submit actual O&M data and to allow QSEs and Resource Entities to focus on the Nodal Go-Live process. This NPRR provides an additional incentive to submit verifiable costs that include actual O&M data during the years subsequent to 2011.
Created2011-08-18
Approved2011-09-20
Sections Affected
5.6.1
Summary
This Nodal Protocol Revision Request (NPRR) reduces the standard Operations and Maintenance (O&M) costs permitted to be used in lieu of actual, verifiable O&M costs by NPRR225, Standard Cost Option in Verifiable Costs, which was approved by the ERCOT Board in June 2010.
Action Log 3 milestones
-
Aug 18
PRSRecommended for Approval→ TAC consideration of NPRR396
-
Sep 1
TACRecommended for Approval→ ERCOT Board consideration of NPRR396
-
Sep 20
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Sep 1 '11 | TAC | To recommend approval of NPRR396 as amended by the 8/26/11 Austin Energy comments. | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 396NPRR-01 Reduce Standard O&M Costs 071911 | doc | Jul 19 '11 | Revision Request |
| 396NPRR-02 WMS Comments 081211 | doc | Aug 12 '11 | Revision Request Comments |
| 396NPRR-03 PRS Report 081811 | doc | Aug 22 '11 | Committee Report |
| 396NPRR-04 ERCOT Comments 082411 | doc | Aug 25 '11 | Revision Request Comments |
| 396NPRR-05 Impact Analysis 082411 | doc | Aug 24 '11 | Staff Report |
| 396NPRR-06 Austin Energy Comments 082611 | doc | Aug 26 '11 | Revision Request Comments |
| 396NPRR-07 TAC Report 090111 | doc | Sep 2 '11 | Committee Report |
| 396NPRR-08 Board Report 092011 | doc | Sep 21 '11 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Sep 20 '11 | Board of Directors Meeting | BOARD | Concluded |
| Sep 1 '11 | TAC Meeting | TAC | Concluded |
| Aug 18 '11 | PRS Meeting | PRS | Concluded |
| Aug 10 '11 | WMS Meeting | WMS | Concluded |