NPRR #1308 · Revision Request
NPRR1308 Board Priority - Related to NOGRR282, Large Computational Load Ride-Through Requirements
ReasonStrategic Plan Objective 1
Created2025-12-10
Approved2026-07-09
Sections Affected
2.1 and 2.2
Summary
This Nodal Protocol Revision Request (NPRR) defines Large Computational Load (LCL).
Action Log 5 milestones
-
Dec 10
PRSDeferred/Tabled→ PRS for consideration
-
Apr 15
PRSRecommended for Approval→ TAC for consideration
-
Apr 29
TACRecommended for Approval→ Board for consideration
-
Jun 2
BOARDRecommended for Approval→ PUCT for consideration
-
Jul 9
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Apr 15 '26 | PRS | To recommend approval of NPRR1308 as amended by the 4/13/26 ERCOT comments and to forward to TAC NPRR1308 and the 11/14/25 Impact Analysis | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Apr 29 '26 | TAC | Motion Passes | 24 | 2 | 4 | xls |
| Apr 15 '26 | PRS | Motion Carries | 6.5 | 0.5 | 0 | xls |
| Apr 2 '26 | ROS | Motion Carries | 6.75 | 0.5 | 3 | xls |
| Jan 8 '26 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
| Dec 10 '25 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 18
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1308NPRR-01 Board Priority - Related to NOGRR282, Large Electronic Load Ride-Through Requirements 111425 | docx | Nov 14 '25 | Revision Request |
| 1308NPRR-02 Impact Analysis 111425 | docx | Nov 14 '25 | Staff Report |
| 1308NPRR-03 Google Comments 120425 | docx | Dec 4 '25 | Revision Request Comments |
| 1308NPRR-04 ERCOT Comments 121025 | docx | Dec 10 '25 | Revision Request Comments |
| 1308NPRR-05 PRS Ballot 121025 | xls | Dec 14 '25 | Revision Request Ballot |
| 1308NPRR-06 PRS Report 121025 | docx | Dec 14 '25 | Committee Report |
| 1308NPRR-07 ROS Ballot 010826 | xls | Jan 8 '26 | Revision Request Ballot |
| 1308NPRR-08 ROS Comments 010826 | docx | Jan 8 '26 | Revision Request Comments |
| 1308NPRR-09 Data Center Coalition Comments 020926 | docx | Feb 9 '26 | Revision Request Comments |
| 1308NPRR-10 ROS Ballot 040226 | xls | Apr 8 '26 | Revision Request Ballot |
| 1308NPRR-11 ROS Comments 040826 | docx | Apr 8 '26 | Revision Request Comments |
| 1308NPRR-12 ERCOT Comments 041326 | docx | Apr 13 '26 | Revision Request Comments |
| 1308NPRR-13 PRS Ballot 041526 | xls | Apr 20 '26 | Revision Request Ballot |
| 1308NPRR-14 PRS Report 041526 | docx | Apr 20 '26 | Committee Report |
| 1308NPRR-15 TAC Ballot 042926 | xls | May 4 '26 | Revision Request Ballot |
| 1308NPRR-16 TAC Report 042926 | docx | May 4 '26 | Committee Report |
| 1308NPRR-17 Board Report 060226 | docx | Jun 3 '26 | Committee Report |
| 1308NPRR-18 PUCT Report 070926 | docx | Jul 11 '26 | Committee Report |
Meetings That Took It Up 13
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 1 '26 | Board of Directors Meeting | BOARD | Concluded |
| Apr 29 '26 | TAC Meeting | TAC | Concluded |
| Apr 15 '26 | PRS Meeting | PRS | Concluded |
| Apr 2 '26 | ROS Meeting | ROS | Concluded |
| Mar 11 '26 | PRS Meeting | PRS | Concluded |
| Mar 5 '26 | ROS Meeting | ROS | Concluded |
| Feb 11 '26 | PRS Meeting | PRS | Concluded |
| Feb 5 '26 | ROS Meeting | ROS | Concluded |
| Jan 14 '26 | PRS Meeting | PRS | Concluded |
| Jan 8 '26 | ROS Meeting | ROS | Concluded |
| Dec 10 '25 | PRS Meeting | PRS | Concluded |
| Dec 8 '25 | Board of Directors Meeting | BOARD | Concluded |
| Nov 20 '25 | LLWG Meeting | LLWG | Concluded |