NPRR #570 · Revision Request
NPRR570 Reduce RTM Settlement Timeline to Operating Day Plus Five
ReasonThis NPRR addresses concerns raised in regards to the impact of the increase to the high SWCAP pursuant to the adoption of amendments to P.U.C. Subst. R. 25.505. COPS held two workshops, on 8/29/13 and 9/10/13, to discuss how to reduce the RTM Settlement timeline further, given the successful implementation of NPRR509, Shortened RTM Settlement Timeline. Market Participants reached a compromise to continue with a two phased approach as in NPRR509 with an objective of RTM Initial Settlement on Operating Day plus five by 6/1/2014. COPS continues to discuss aspects related to impacts, tradeoffs, benefits, and potential solutions for RTM Settlement on a faster timeline.
Created2013-10-17
Approved2013-11-19
Sections Affected
2.19.5.29.5.49.5.510.8.1.2
Summary
This NPRR proposes a phased approach to change the posting date for the Real-Time Market (RTM) Initial Settlement Statement from seven days after the Operating Day to five days after the Operating Day and changes the posting date of the Final Settlement Statement from the 57th day after the Operating Day to the 55th day after the Operating Day.
Action Log 3 milestones
-
Oct 17
PRSRecommended for Approval→ TAC for consideration.
-
Nov 7
TACRecommended for Approval→ ERCOT Board for consideration.
-
Nov 19
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 17 '13 | PRS | To recommend approval of NPRR570 as amended by the 10/10/13 COPS comments and to forward NPRR570 to TAC. | Passed |
| Nov 7 '13 | TAC | To recommend approval of NPRR570 as recommended by PRS in the 10/17/13 PRS Report and as amended by the 10/31/13 ERCOT comments with an effective date of 1/1/14 for phase one and a recommended priority of 2014 and rank of 1030 for phase two targeting a 5/1/14 effective date. All Market Segments were present for the vote. | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 570NPRR-01 Reduce RTM Settlement Timeline to Operating Day Plus | doc | Sep 30 '13 | Revision Request |
| 570NPRR-02 COPS Comments 101013 | doc | Oct 10 '13 | Revision Request Comments |
| 570NPRR-03 PRS Report 101713 | doc | Oct 21 '13 | Committee Report |
| 570NPRR-04 Credit Work Group Comments 103113 | doc | Oct 31 '13 | Revision Request Comments |
| 570NPRR-05 ERCOT Comments 103113 | doc | Oct 31 '13 | Revision Request Comments |
| 570NPRR-06 Impact Analysis 110613 | doc | Nov 5 '13 | Staff Report |
| 570NPRR-07 TAC Report 110713 | doc | Nov 7 '13 | Committee Report |
| 570NPRR-08 Board Report 111913 | doc | Nov 22 '13 | Committee Report |
Meetings That Took It Up 13
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 16 '14 | COPS Meeting | COPS | Concluded |
| May 14 '14 | COPS Meeting | COPS | Concluded |
| Apr 8 '14 | Board of Directors Meeting | BOARD | Concluded |
| Mar 27 '14 | TAC Meeting | TAC | Concluded |
| Mar 17 '14 | COPS Meeting | COPS | Concluded |
| Feb 5 '14 | WMS Meeting | WMS | Concluded |
| Dec 3 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Nov 19 '13 | Board of Directors Meeting | BOARD | Concluded |
| Nov 7 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Oct 30 '13 | Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting | CREDITWG | Concluded |
| Oct 17 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |
| Oct 16 '13 | Retail Market Subcommittee (RMS) Meeting | RMS | Concluded |
| Oct 8 '13 | Commercial Operations Subcommittee (COPS) Meeting | COPS | Concluded |