NPRR #1107 · Revision Request
NPRR1107 Addition of Weatherization Inspection Fees to the ERCOT Fee Schedule and Clarification of Generation Interconnection Request Fees
ReasonRegulatory requirements
Created2021-11-10
Approved2021-12-16
Sections Affected
ERCOT Fee Schedule
Summary
This Nodal Protocol Revision Request (NPRR) adds new fees for weatherization inspections conducted by ERCOT to the ERCOT Fee Schedule. This NPRR further clarifies that the existing GINR fees apply to all generation interconnection projects regardless of whether they will interconnect at the transmission or distribution level.
Action Log 5 milestones
-
Nov 10
PRSDeferred/Tabled→ Language Consideration
-
Nov 17
PRSRecommended for Approval→ Revision Request Consideration
-
Nov 29
TACRecommended for Approval→ Revision Request Consideration
-
Dec 10
BOARDRecommended for Approval→ Revision Request Consideration
-
Dec 16
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Nov 17 '21 | PRS | to recommend approval of NPRR1107 as amended by the 11/16/21 TIEC comments and to forward to TAC NPRR1107 and the Impact Analysis with a recommended effective date of upon PUCT approval and a recommended sunset date of September 1, 2022 | Passed |
| Nov 29 '21 | TAC | to recommend approval of NPRR1107 as recommended by PRS in the 11/17/21 PRS Report as amended by the 11/23/21 ERCOT comments and the Revised Impact Analysis | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Nov 29 '21 | TAC | Motion Passes | 27 | 0 | 2 | xls |
| Nov 17 '21 | PRS | Motion Carries | 6.32143 | 0.678571 | 3 | xls |
| Nov 10 '21 | PRS | Motion Carries | 7 | 0 | 0 | xls |
| Nov 10 '21 | PRS | Motion Carries | 4.3 | 0.7 | 7 | xls |
Documents 16
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Nov 29 '21 | TAC Meeting by Webex Only | TAC | Concluded |
| Nov 17 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Nov 10 '21 | PRS Meeting by Webex Only | PRS | Concluded |