NPRR #533 · Revision Request
NPRR533 PCRR Eligibility Requirements (formerly "Clarification of PCRR Eligibility Requirements")
ReasonAdditional clarity is needed in the ERCOT Protocols on the governing rules for PCRR eligibility as customer relationships have changed, resources are upgraded/mothballed/retired, and contracts are extended or terminated. ERCOT submits this NPRR to clarify the circumstances in which PCRRs will continue to be eligible versus when that eligibility is partially or totally forfeited.
Created2013-04-18
Approved2014-04-08
Sections Affected
3.4.27.47.4.17.4.1.1 (new)7.4.1.3 (new)7.4.1.3.1 (new)7.4.1.3.2 (new)7.4.27.4.2.1 (new)7.4.2.2 (new)
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the eligibility for Pre-Assigned Congestion Revenue Rights (PCRRs) subject to changes over time in contracts, Entity relationships, and resource status and capabilities.
Action Log 4 milestones
-
Apr 18
PRSDeferred/Tabled→ PRS language consideration
-
Feb 13
PRSRecommended for Approval→ TAC consideration of NPRR533
-
Feb 27
TACRecommended for Approval→ ERCOT Board consideration of NPRR533
-
Apr 8
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Feb 27 '14 | TAC | To recommend approval of NPRR533 as recommended by PRS in the 2/13/14 PRS Report, as amended by the 2/26/14 San Bernard Electric Cooperative comments and as revised by TAC. | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Feb 27 '14 | TAC | Motion Fails | 11 | 13 | 5 | xls |
| Feb 27 '14 | TAC | Motion Fails | 11 | 13 | 5 | xls |
| Feb 13 '14 | PRS | Motion Fails | 3.08333 | 3.91667 | 6 | xls |
| Feb 13 '14 | PRS | Motion Fails | 2.29167 | 4.70833 | 9 | xls |
Documents 32
Meetings That Took It Up 19