NPRR #578 · Revision Request
NPRR578 Restores RUC Decommitment Charge Language Deleted in NPRR416
ReasonSection 5.7.6 was unintentionally deleted as part of NPRR416. The language in Section 5.7.6 provides the mechanism to uplift the charges to the Load Serving Entity (LSE) based on Load Ratio Share (LRS) when ERCOT must pay a Resource, as described in Section 5.7.3, Payment When ERCOT Decommits a QSE-Committed Resource.
Created2013-11-21
Approved2013-12-10
Sections Affected
5.5.25.7.6
Summary
This NPRR deletes the grey box in Section 5.7.6 that would remove the Reliability Unit Commitment (RUC) Decommitment Charge upon implementation of NPRR416; and clarifies Settlement treatment of RUC-Committed blocks that span an Operating Day and are opted out.
Action Log 3 milestones
-
Nov 21
PRSRecommended for Approval→ TAC for consideration.
-
Dec 3
TACRecommended for Approval→ ERCOT Board for consideration.
-
Dec 10
BOARDApproved
Documents 5
| Name | Type | Posted | Classification |
|---|---|---|---|
| 578NPRR-01 Restores RUC Decommitment Charge Language Deleted in | doc | Nov 6 '13 | Revision Request |
| 578NPRR-02 Impact Analysis 110613 | doc | Nov 6 '13 | Staff Report |
| 578NPRR-03 PRS Report 112113 | doc | Nov 26 '13 | Committee Report |
| 578NPRR-04 TAC Report 120313 | doc | Dec 3 '13 | Committee Report |
| 578NPRR-05 Board Report 121013 | doc | Dec 12 '13 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 10 '13 | Board of Directors Meeting | BOARD | Concluded |
| Dec 3 '13 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Nov 21 '13 | Protocol Revision Subcommittee (PRS) Meeting | PRS | Concluded |