NPRR1113  Clarification of Regulation-Up Schedule for Controllable Load Resources in Ancillary Service Imbalance

Approved Urgent sponsor ERCOT posted 2021-12-22 ercot.com
  1. PRS Jan 13 '22
  2. TAC Jan 31 '22
  3. BOARD Mar 7 '22
  4. PUCT Mar 31 '22
ReasonAddresses current operational issues
Created2022-01-13
Approved2022-03-31
Sections Affected
6.7.5
Summary
This Nodal Protocol Revsion Request (NPRR) adjusts the definitions in Section 6.7.5 to prohibit double-counting of the Regulation-Up (Reg-Up) Ancillary Service Schedule when calculating capacity in the Ancillary Service Imbalance Settlement for Controllable Load Resources available to Security-Constrained Economic Dispatch (SCED).