NPRR #950 · Revision Request

NPRR950  Switchable Generation Resources Providing Black Start Service

Approved Urgent sponsor ERCOT posted 2019-05-30 ercot.com
ReasonAddresses current operational issues
Created2019-07-17
Approved2019-10-08
Sections Affected
3.14.216.5.4and 22D
Summary
This Nodal Protocol Revision Request (NPRR) will prohibit any Switchable Generation Resource (SWGR) contracted to provide Black Start Service (BSS) from generating in any Control Area other than ERCOT.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Sep 12 '19PRS to grant NPRR950 Urgent status. PRS then unanimously voted to recommend approval of NPRR950 as amended by the 8/8/19 ERCOT comments, and to forward to TAC NPRR950 and the Impact AnalysisPassed
Documents 10
NameTypePostedClassification
950NPRR-01 Switchable Generation Resources Providing Black Start Service 053019 doc May 30 '19 Revision Request
950NPRR-02 Impact Analysis 053019 doc May 30 '19 Staff Report
950NPRR-03 PRS Report 071719 doc Jul 22 '19 Committee Report
950NPRR-04 ERCOT Comments 080819 doc Aug 8 '19 Revision Request Comments
950NPRR-05 ROS Comments 080919 doc Aug 9 '19 Revision Request Comments
950NPRR-06 ERCOT Comments 082719 doc Aug 27 '19 Revision Request Comments
950NPRR-07 ROS Comments 090619 doc Sep 6 '19 Revision Request Comments
950NPRR-08 PRS Report 091219 doc Sep 17 '19 Committee Report
950NPRR-09 TAC Report 092519 doc Sep 26 '19 Committee Report
950NPRR-10 Board Report 100819 doc Oct 11 '19 Committee Report
Meetings That Took It Up 7
DateMeetingCommitteeStatus
Oct 8 '19 Board of Directors Meeting BOARD Concluded
Sep 25 '19 TAC Meeting TAC Concluded
Sep 12 '19 PRS Meeting PRS Concluded
Sep 5 '19 ROS Meeting ROS Concluded
Aug 15 '19 PRS Meeting PRS Concluded
Aug 8 '19 ROS Meeting ROS Concluded
Jul 17 '19 PRS Meeting PRS Concluded