NPRR #950 · Revision Request
NPRR950 Switchable Generation Resources Providing Black Start Service
- PRS Sep 12 '19
- TAC Sep 25 '19
- BOARD Oct 8 '19
- PUCT —
ReasonAddresses current operational issues
Created2019-07-17
Approved2019-10-08
Sections Affected
3.14.216.5.4and 22D
Summary
This Nodal Protocol Revision Request (NPRR) will prohibit any Switchable Generation Resource (SWGR) contracted to provide Black Start Service (BSS) from generating in any Control Area other than ERCOT.
Timeline
- May 30
-
Jul 17
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS“to table NPRR950 and refer the issue to ROS” — Passed→ Language Consideration
- Aug 8
- Aug 15
- Sep 5
-
Sep 12
PRS PRS MeetingPRSRecommended for Approval Urgent status Amended by the Aug 8 '19 ERCOT comments Forwarded → TAC“to grant NPRR950 Urgent status. PRS then unanimously voted to recommend approval of NPRR950 as amended by the 8/8/19 ERCOT comments, and to forward to TAC NPRR950 and the Impact Analysis” — Passed→ Revision Request Consideration
-
Sep 25
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR950 as recommended by PRS in the 9/12/19 PRS Report” — Passed→ Revision Request Consideration
-
Oct 8
BOARD Board of Directors MeetingBOARDApproved“to approve NPRR950 as recommended by TAC in the 9/25/19 TAC Report” — Passed
-
—
Posted since the last meeting