NPRR #830 · Revision Request
NPRR830 Revision of 4-Coincident Peak Methodology
ReasonAddresses current operational issues.
Created2017-05-11
Approved2017-06-13
Sections Affected
9.17.1
Summary
This Nodal Protocol Revision Request (NPRR) revises the basis of ERCOT’s calculation of the 4-Coincident Peak (4-CP) to a manner consistent with the North American Electric Reliability Corporation (NERC) net energy for Load methodology.
Action Log 3 milestones
-
May 11
PRSRecommended for Approval→ Revision Request Consideration
-
May 25
TACRecommended for Approval→ Revision Request Consideration
-
Jun 13
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| May 11 '17 | PRS | To grant NPRR830 Urgent status. PRS then unanimously voted to recommend approval of NPRR830 as revised by PRS; to forward NPRR830 and the Revised Impact Analysis to TAC with a priority of 2017 and rank of 2010; and a recommended effective date of upon ERCOT Board approval. | Passed |
| May 25 '17 | TAC | To recommend approval of NPRR830 as recommended by PRS in the 5/11/17 PRS Report and as revised by TAC. | Passed |
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 830NPRR-01 Revision of 4 Coincident Peak Methodology 042617 | doc | Apr 26 '17 | Revision Request |
| 830NPRR-02 Impact Analysis 042617 | doc | Apr 26 '17 | Staff Report |
| 830NPRR-03 Revised Impact Analysis 050317 | doc | May 3 '17 | Staff Report |
| 830NPRR-04 PRS Report 051117 | doc | May 17 '17 | Committee Report |
| 830NPRR-05 TAC Report 052517 | doc | May 31 '17 | Committee Report |
| 830NPRR-06 Board Report 061317 | doc | Jun 13 '17 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 13 '17 | Board of Directors Meeting | BOARD | Concluded |
| May 25 '17 | TAC Meeting | TAC | Concluded |
| May 11 '17 | PRS Meeting | PRS | Concluded |