NPRR #555 · Revision Request

NPRR555  Load Resource Participation in Security-Constrained Economic Dispatch

Approved Urgent sponsor ERCOT posted 2013-07-03 ercot.com
ReasonERCOT has authored this NPRR as way of contributing to ongoing efforts by policymakers and Market Participants to help limit Real-Time price reversal when actions are taken by ERCOT for reliability purposes (in this case, deployment of Load Resources providing Non-Spin).
Created2013-07-18
Approved2013-09-17
Sections Affected
2.12.23.2.53.63.6.1 (new)3.6.2 (new)3.7.1.23.9.13.10.7.23.17.36.36.3.16.4.3 (new)6.4.3.1 (new)6.4.3.1.1 (new)6.4.3.1.2 (new)6.4.3.26.4.3.36.5.5.26.5.7.1.126.5.7.26.5.7.36.5.7.46.5.7.56.5.7.6.2.26.5.7.6.2.36.6.56.6.5.16.6.5.1.16.6.5.1.26.6.5.1.1.3 (new)6.6.5.1.1.4 (new)6.6.5.26.6.5.48.1.1.28.1.1.4.18.1.1.4.3
Summary
This NPRR enables Demand response from Controllable Load Resources, as re-defined, to be Dispatched by Security-Constrained Economic Dispatch (SCED) based on a Real-Time Market (RTM) Energy Bid. This NPRR clarifies the initial rules for participation in the RTM by newly-defined "Aggregate Load Resources" (ALRs), consisting of multiple metered sites within a single ERCOT Load Zone. Controllable Load Resources, including ALRs, must be capable of responding to five-minute SCED Base Point instructions, which could instruct Load changes in either direction (up or down) if the Controllable Load Resource’s bid sets the Locational Marginal Price (LMP). The NPRR, along with associated Other Binding Documents, also establishes a long-term solution for Controllable Load Resource provision of Non-Spinning Reserve (Non-Spin) Service by allowing participating Controllable Load Resources providing Non-Spin to be Dispatched economically. Initial participation will be limited to Load Serving Entity (LSE) QSEs (the only QSEs that can submit bids to buy energy) and Controllable Load Resources capable of responding to five-minute SCED Base Points. Future enhancements to the market will be necessary to accommodate direct participation by third-party Demand response aggregators and Load Resources with "block" offers or bids. Additionally, as drafted, NPRR555 will not accommodate Load Resources with ramp periods longer than five minutes, nor will it accommodate the provision of Ancillary Services by Controllable Load Resources with temporal constraints such as minimum or maximum run times. As submitted, the NPRR proposes uniform performance and compliance metrics for any Load Resource participating in SCED; however, ERCOT encourages Market Participants to consider whether establishing more relaxed metrics for Load Resources that are not carrying an Ancillary Service Resource Responsibility would attract more participation.
Action Log 4 milestones
Amendments
DateBodyMotionResult
Sep 5 '13TAC To recommend approval of NPRR555 as recommended by PRS in the 8/22/13 PRS Report and as amended by the 8/29/13 ERCOT comments.Passed
Documents 29
NameTypePostedClassification
555NPRR-01 Load Resource Participation in Security-Constrained E doc Jul 3 '13 Revision Request
555NPRR-02 Preliminary Impact Analysis 070313 doc Jul 3 '13 Staff Report
555NPRR-03 ERCOT Steel Mills Comments 071113 doc Jul 11 '13 Revision Request Comments
555NPRR-04 PRS Report 071813 doc Jul 19 '13 Committee Report
555NPRR-05 ERCOT Comments 072413 doc Jul 24 '13 Revision Request Comments
555NPRR-06 Luminant Comments 080613 doc Aug 6 '13 Revision Request Comments
555NPRR-07 Comverge Comments 080613 doc Aug 6 '13 Revision Request Comments
555NPRR-08 Calpine Comments 080713 doc Aug 8 '13 Revision Request Comments
555NPRR-09 Johnson Controls Comments 080713 doc Aug 7 '13 Revision Request Comments
555NPRR-10 Morgan Stanley Comments 081313 doc Aug 13 '13 Revision Request Comments
555NPRR-11 Comverge Comments 081313 doc Aug 13 '13 Revision Request Comments
555NPRR-12 Oncor Comments 081313 doc Aug 13 '13 Revision Request Comments
555NPRR-13 ERCOT Comments 081413 doc Aug 14 '13 Revision Request Comments
555NPRR-14 ERCOT Comments - Attachment 081413 doc Aug 14 '13 Revision Request Comments
555NPRR-15 Citigroup Energy Comments 081413 doc Aug 14 '13 Revision Request Comments
555NPRR-16 Calpine Comments 081413 doc Aug 14 '13 Revision Request Comments
555NPRR-17 WMS Comments 081513 doc Aug 15 '13 Revision Request Comments
555NPRR-18 WMS Voting Ballot 081513 xls Aug 15 '13 Revision Request Ballot
555NPRR-19 ROS Comments 081913 doc Aug 19 '13 Revision Request Comments
555NPRR-20 CPS Energy Comments 082013 doc Aug 20 '13 Revision Request Comments
555NPRR-21 Comverge Comments 082113 doc Aug 21 '13 Revision Request Comments
555NPRR-22 PRS Report 082213 doc Aug 26 '13 Committee Report
555NPRR-23 ERCOT Comments 082913 doc Aug 29 '13 Revision Request Comments
555NPRR-24 Johnson Controls Comments 090313 doc Sep 3 '13 Revision Request Comments
555NPRR-25 ERCOT Comments 090413 doc Sep 4 '13 Revision Request Comments
555NPRR-26 Impact Analysis 090513 doc Sep 4 '13 Staff Report
555NPRR-27 TAC Report 090513 doc Sep 5 '13 Committee Report
555NPRR-28 Johnson Controls Comments 091113 doc Sep 11 '13 Revision Request Comments
555NPRR-29 Board Report 091713 doc Sep 18 '13 Committee Report
Meetings That Took It Up 20
DateMeetingCommitteeStatus
Jun 4 '14 TDTWG Meeting TDTWG Concluded
Apr 24 '14 TAC Meeting TAC Concluded
Apr 3 '14 ROS Meeting ROS Concluded
Apr 2 '14 TDTWG WebEx Meeting TDTWG Concluded
Mar 19 '14 OWG Meeting OWG Concluded
Mar 5 '14 TDTWG Meeting TDTWG Concluded
Feb 17 '14 OWG Meeting OWG Concluded
Feb 11 '14 Board of Directors Meeting BOARD Concluded
Jan 28 '14 TAC Meeting TAC Concluded
Jan 16 '14 PRS Meeting PRS Concluded
Sep 17 '13 Board of Directors Meeting BOARD Concluded
Sep 5 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Aug 28 '13 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting CREDITWG Concluded
Aug 22 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 15 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Aug 14 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Aug 8 '13 Loads in SCED Workshop DSWG Concluded
Jul 29 '13 Network Data Support Working Group (NDSWG) Meeting by WebEx only NDSWG Concluded
Jul 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 10 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded