PGRR #121 · Revision Request

PGRR121  Related to NOGRR272, Advanced Grid Support Requirements for Inverter-Based ESRs

Approved Urgent sponsor ERCOT posted 2024-10-31 ercot.com
ReasonStrategic Plan Objective 1
Created2024-12-05
Approved2025-11-06
Sections Affected
6.2
Summary
This Planning Guide Revision Request (PGRR) establishes model quality test and unit model validation requirements for inverter-based Energy Storage Resources (ESRs) with a Standard Generation Interconnection Agreement (SGIA) executed on or after April 1, 2026.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Aug 7 '25ROS to recommend approval of PGRR121 as amended by the 6/4/25 ERCOT commentsPassed
Aug 27 '25TAC to recommend approval of PGRR121 as recommended by ROS in the 8/7/25 ROS Report as amended by the 8/22/25 ERCOT comments; and the 10/31/24 Impact AnalysisPassed
Ballots
DateBodyResultYesNoAbstain
Aug 27 '25 TAC Motion Passes 27 0 3 xls
Aug 7 '25 ROS Motion Carries 6.5 1 4 xls
Jul 10 '25 ROS Motion Carries 7.5 0 0 xls
Dec 5 '24 ROS Motion Carries 7.5 0 0 xls
Documents 15
NameTypePostedClassification
121PGRR-01 Related to NOGRR272, Advanced Grid Support Requirements for Inverter-Based ESRs 103124 docx Oct 31 '24 Revision Request
121PGRR-02 Impact Analysis 103124 docx Oct 31 '24 Staff Report
121PGRR-03 ROS Ballot 120524 xls Dec 9 '24 Revision Request Ballot
121PGRR-04 ROS Report 120524 docx Dec 9 '24 Committee Report
121PGRR-05 ERCOT Comments 060425 docx Jun 4 '25 Revision Request Comments
121PGRR-06 ROS Ballot 071025 xls Jul 15 '25 Revision Request Ballot
121PGRR-07 ROS Report 071025 docx Jul 15 '25 Committee Report
121PGRR-08 ROS Ballot 080725 xls Aug 12 '25 Revision Request Ballot
121PGRR-09 ROS Report 080725 docx Aug 12 '25 Committee Report
121PGRR-10 ERCOT Comments 082225 docx Aug 22 '25 Revision Request Comments
121PGRR-11 Tesla Comments 082225 docx Aug 22 '25 Revision Request Comments
121PGRR-12 TAC Ballot 082725 xls Sep 2 '25 Revision Request Ballot
121PGRR-13 TAC Report 082725 docx Sep 2 '25 Committee Report
121PGRR-14 Board Report 092225 docx Sep 24 '25 Committee Report
121PGRR-15 PUCT Report 110625 docx Nov 10 '25 Committee Report
Meetings That Took It Up 17
DateMeetingCommitteeStatus
Sep 22 '25 Board of Directors Meeting BOARD Concluded
Aug 27 '25 TAC Meeting TAC Concluded
Aug 7 '25 ROS Meeting ROS Concluded
Jul 10 '25 ROS Meeting - Webex Only ROS Concluded
Jun 5 '25 ROS Meeting - Webex Only ROS Concluded
May 1 '25 ROS Meeting ROS Concluded
Apr 3 '25 ROS Meeting - Webex Only ROS Concluded
Mar 6 '25 ROS Meeting ROS Concluded
Feb 21 '25 IBRWG Meeting - Webex Only IBRWG Concluded
Feb 13 '25 DWG Meeting - Webex Only DWG Concluded
Feb 6 '25 ROS Meeting - Webex Only ROS Concluded
Jan 17 '25 IBRWG Meeting - Webex Only IBRWG Concluded
Jan 9 '25 ROS Meeting - Webex Only ROS Concluded
Dec 13 '24 IBRWG Meeting - Webex Only IBRWG Concluded
Dec 11 '24 DWG Meeting - Webex Only DWG Concluded
Dec 5 '24 ROS Meeting - Webex Only ROS Concluded
Nov 15 '24 IBRWG Meeting - Webex Only IBRWG Concluded