RMGRR #170 · Revision Request
RMGRR170 Inadvertent Gain Process Updates
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2022-10-11
Approved2022-12-15
Sections Affected
2.12.27.37.3.27.3.2.17.3.2.1.17.3.2.1.27.3.2.1.37.3.2.37.3.2.47.3.2.37.3.2.3.17.3.2.4and 7.3.2.7.1
Summary
This Retail Market Guide Revision Request (RMGRR) addresses the following issues associated with the Inadvertent Gain/Loss (IAG) process: • Defines an IAG; • Clarifies the appropriate use of the IAG process; • Limits the use of the bulk insert template for IAGs; • Requires a Competitive Retailer (CR) experiencing a system processing issue that results in inadvertently gaining greater than 100 Electric Service Identifiers (ESI IDs), and uses the IAG process to resolve the issue, to inform impacted Market Participants, and detail the cause of the issue; • Adds a provision under Section 7.3.2.6, Valid Reject/ Unexecutable Reasons, that allows a losing CR to reject the return of an inadvertently gained ESI ID from the gaining CR if the IAG was inappropriately submitted as described in Section 7.3.2.1, Invalid Use of the IAG Process; and • Introduces the commonly referred to “No Current Occupant” process supported by P.U.C. SUBST. R. 25.488, Procedures for a Premise with No Service Agreement, for scenarios where the losing CR no longer has a valid service agreement with the Customer and must regain an ESI ID.
Action Log 3 milestones
-
Oct 11
RMSRecommended for Approval→ Revision Request Consideration
-
Oct 26
TACRecommended for Approval→ Revision Request Consideration
-
Dec 15
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 26 '22 | TAC | to recommend approval of RMGRR170 as recommended by RMS in the 10/11/22 RMS Report as amended by the 10/24/22 TXU Energy comments and the 10/20/22 Impact Analysis | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Oct 11 '22 | RMS | Motion Carries | 7.5 | 0 | 0 | xls |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 170RMGRR-01 Inadvertent Gain Process Updates | docx | Sep 27 '22 | Revision Request |
| 170RMGRR-02 RMS Ballot 101122 | xls | Oct 13 '22 | Revision Request Ballot |
| 170RMGRR-03 RMS Report 101122 | docx | Oct 14 '22 | Committee Report |
| 170RMGRR-04 Impact Analysis 102022 | docx | Oct 20 '22 | Staff Report |
| 170RMGRR-05 TXU Energy Comments 102422 | docx | Oct 24 '22 | Revision Request Comments |
| 170RMGRR-06 TAC Ballot 102622 | xls | Oct 31 '22 | Revision Request Ballot |
| 170RMGRR-07 TAC Report 102622 | docx | Oct 31 '22 | Committee Report |
| 170RMGRR-08 PUCT Report 121522 | docx | Dec 16 '22 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| May 16 '23 | TDTMS WG Meeting - Webex Only | TDTMS | Concluded |
| Oct 26 '22 | TAC Meeting by Webex Only | TAC | Concluded |
| Oct 11 '22 | RMS Meeting | RMS | Concluded |