NPRR #1169 · Revision Request

NPRR1169  Expansion of Generation Resources Qualified to Provide Firm Fuel Supply Service in Phase 2 of the Service

Approved Urgent sponsor ERCOT posted 2023-03-29 ercot.com
ReasonAddresses current operational issues
Created2023-04-13
Approved2023-06-29
Sections Affected
1.3.1.12.13.14.56.6.14.1and 8.1.1.2.1.6
Summary
This Nodal Protocol Revision Request (NPRR) expands the qualifications by which a Generation Resource may be an FFSS Resource (FFSSR) or an alternate to include those meeting the following characteristics: the Generation Entity that owns the Generation Resource (or an Affiliate) must own and have good title to sufficient natural gas in the offsite storage facility for the offered Generation Resource to deliver the offered MW for at least the duration specified in the Request for Proposal (RFP) and must commit to maintain such quantity of gas in storage at all times during the obligation period; the Generation Entity (or an Affiliate) must either own, or have a Firm Gas Storage Agreement for, sufficient natural gas storage capacity for the offered Generation Resource to deliver the offered MW for at least the duration specified in the RFP; the Generation Entity for the Generation Resource (or an Affiliate) must have entered into a Firm Transportation Agreement on a Qualifying Pipeline; and a number of ongoing compliance obligations must be satisfied, including a requirement that the Generation Entity for the FFSSR must provide a report to ERCOT with certain information and data if the FFSSR fails to deploy due to a Force Majeure Event. Revisions in this NPRR also include categorizing certain information provided to ERCOT as Protected Information; adding definitions; and addressing requirements for recovery of replacement-fuel costs if ERCOT approves restocking of fuel after deployment of an FFSSR.
Action Log 5 milestones
Amendments
DateBodyMotionResult
May 10 '23PRS To recommend approval of NPRR1169 as amended by the 5/9/23 ERCOT comments as revised by PRS and to forward to TAC NPRR1169 and the 3/29/23 Impact AnalysisPassed
May 23 '23TAC To recommend approval of NPRR1169 as recommended by PRS in the 5/10/23 PRS Report as amended by the 5/22/23 Calpine comments as revised by TACPassed
Jun 20 '23BOARD To recommend approval of NPRR1169 as recommended by TAC in the 5/23/23 TAC Report as amended by the 6/12/23 ERCOT commentsPassed
Ballots
DateBodyResultYesNoAbstain
May 23 '23 TAC 28 0 1 xls
May 10 '23 PRS Motion Carries 7 0 1 xls
Apr 13 '23 PRS Motion Carries 7 0 0 xls
Documents 21
NameTypePostedClassification
1169NPRR-01 Expansion of Generation Resources Qualified to Provide Firm Fuel Supply Service in Phase 2 of the Service 032923 docx Mar 29 '23 Revision Request
1169NPRR-02 Impact Analysis 032923 docx Mar 29 '23 Staff Report
1169NPRR-03 HEN Comments 040723 docx Apr 7 '23 Revision Request Comments
1169NPRR-04 Calpine Comments 041223 docx Apr 12 '23 Revision Request Comments
1169NPRR-05 LCRA Comments 041223 docx Apr 12 '23 Revision Request Comments
1169NPRR-06 PRS Ballot 041323 xls Apr 17 '23 Revision Request Ballot
1169NPRR-07 PRS Report 041323 docx Apr 17 '23 Committee Report
1169NPRR-08 TIEC Comments 050823 docx May 8 '23 Revision Request Comments
1169NPRR-09 Calpine Comments 050923 docx May 9 '23 Revision Request Comments
1169NPRR-10 ERCOT Comments 050923 docx May 9 '23 Revision Request Comments
1169NPRR-11 PRS Ballot 051023 xls May 11 '23 Revision Request Ballot
1169NPRR-12 PRS Report 051023 docx May 11 '23 Committee Report
1169NPRR-13 Calpine Comments 052223 docx May 22 '23 Revision Request Comments
1169NPRR-14 ERCOT Comments 052223 docx May 22 '23 Revision Request Comments
1169NPRR-15 TAC Ballot 052323 xls May 26 '23 Revision Request Ballot
1169NPRR-16 TAC Report 052323 docx May 26 '23 Committee Report
1169NPRR-17 ERCOT Comments 061223 docx Jun 12 '23 Revision Request Comments
1169NPRR-18 Calpine Comments 061323 docx Jun 13 '23 Revision Request Comments
1169NPRR-19 ERCOT Comments 061423 docx Jun 14 '23 Revision Request Comments
1169NPRR-20 Board Report 062023 docx Jun 20 '23 Committee Report
1169NPRR-21 PUCT Report 062923 docx Jun 29 '23 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Jun 20 '23 Board of Directors Meeting BOARD Concluded
Jun 19 '23 Reliability and Markets Committee RELIABILITYMARKETS Concluded
Jun 5 '23 Special TAC Meeting - Webex Only TAC Concluded
May 23 '23 TAC Meeting - Webex Only TAC Concluded
May 10 '23 PRS Meeting PRS Concluded
Apr 13 '23 PRS Meeting PRS Concluded