NPRR #1019 · Revision Request
NPRR1019 Pricing and Settlement Changes for Switchable Generation Resources (SWGRs) Instructed to Switch to ERCOT
- PRS May 15 '20
- TAC May 29 '20
- BOARD Jun 9 '20
- PUCT —
Created2020-04-20
Approved2020-06-09
Sections Affected
3.9.16.4.4.2 (delete)6.5.7.36.6.12and 6.6.12.1
Summary
This NPRR addresses the switching of Switchable Generation Resources (SWGRs) from a non-ERCOT Control Area to the ERCOT the Control Area. Specifically, this NPRR makes the following changes: • Proposes that ERCOT systems automatically create a proxy Energy Offer Curve with a price floor of $4,500/MWh for each Reliability Unit Commitment (RUC)-committed SWGR as opposed to requiring Qualified Scheduling Entities (QSEs) to submit Energy Offer Curves reflecting the $4,500/MWh floor. • Includes a lost revenue cost component to the Switchable Generation Cost Guarantee (SWCG) to ensure that Combined-Cycle Generation Resource SWGRs are made whole to their costs when switching from a non-ERCOT Control Area to the ERCOT Control Area.
Timeline
- Apr 1
- Apr 16
-
Apr 20
PRS PRS Email Vote re NPRR975, NPRR987, NPRR989, NPRR1006, NPRR1018, and NPRR1019PRSRecommended for Approval Amended by the Apr 9 '20 GSEC comments“to recommend approval of NPRR1019 as amended by the 4/9/20 GSEC comments” — Passed→ Impact Analysis Consideration
- May 13
-
May 15
PRS PRS Email Vote re NPRR933, NPRR987, NPRR989, NPRR1000, NPRR1006, NPRR1018, NPRR1019, NPRR1021, NPRR1022, SCR809, and SCR810PRSRecommended for Approval Urgent status Forwarded → TAC priority 2020 · rank 3030“to grant NPRR1019 Urgent status, and to endorse and forward to TAC the 4/20/20 PRS Report and Impact Analysis for NPRR1019 with a recommended effective date of upon ERCOT Board approval for Sections 3.9.1, 6.6.12, 6.6.12.1, and paragraphs (4)(e)(iii)-(vi) of Section 6.5.7.3 and a recommended priority of 2020 and rank of 3030 for the remaining language” — Passed→ Revision Request Consideration
- May 27
-
May 29
TAC TAC Email Vote - May 29, 2020TACRecommended for Approval“to recommend approval of NPRR1019 as recommended by PRS in the 5/15/20 PRS Report” — Passed→ Revision Request Consideration
-
Jun 9
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved Amended by the Jun 1 '20 ERCOT comments“to approve NPRR1019 as recommended by TAC in the 5/29/20 TAC Report as amended by the 6/1/20 ERCOT comments” — Passed
-
—
Posted since the last meeting