Revision Requests On The Agenda
NPRR826NPRR838NPRR849NPRR902NPRR903NPRR928NPRR933NPRR934NPRR937NPRR938NPRR941NPRR945NPRR946NPRR947NPRR953NPRR955NPRR956NPRR957NPRR963NPRR964NPRR965NPRR966NPRR967NPRR968NPRR969NPRR970NPRR971NPRR972NPRR973SCR800SCR805
Agenda 45 items
- 1. Antitrust Admonition — M. Henson
- 2. Approval of Minutes Vote — M. Henson
-
September 12, 2019
- Draft Minutes PRS 20190912 · Meeting Minutes
- 3. TAC and Board Reports — M. Henson
-
4.
Project Update and Summary of Project Priority List (PPL) Activity to Date
— T. Anderson
- PRS October 2019 Project Update · Project Documents
- 5. Review PRS Reports, Impact Analyses, and Prioritization (*) denotes no impact Vote — M. Henson
- NPRR849, Clarification of the Range of Voltage Set Points at a Generation Resource’s POI*
- NPRR902, ERCOT Critical Energy Infrastructure Information*
- NPRR937, Distribution Voltage Level Block Load Transfer (BLT) Deployment*
- NPRR941, Create a Lower Rio Grande Valley Hub
- NPRR957, RTF-4 Definition of Energy Storage Resource and Related Registration and Telemetry Requirements*
- NPRR965, GREDP Shutdown Exemption
- NPRR968, Revise EEA Level 3 Triggers from 1375 MW to 1430 MW to Align with New Most Severe Single Contingency Value
- NPRR969, Clean-up of Protocol 19.8, Retail Market Testing*
- SCR800, Addition of DC Tie Ramp to GTBD Calculation
- SCR805, Provide Early Access to Certain 60-Day Reports to TSPs Upon Request
- 6. Revision Requests Tabled at PRS Vote — M. Henson
-
NPRR826, Mitigated Offer Caps for RMR Resources
- NPRR826 Summary Oct 2019 · Committee Report
- NPRR838, Updated O&M Cost for RMR Resources
- NPRR903, Day-Ahead Market Timing Deviations
- NPRR928, Cybersecurity Incident Notification
- NPRR933, Reporting of Demand Response by Retail Electric Providers and Non-Opt-In Entities
- NPRR938, Distribution Voltage Level Block Load Transfer (BLT) Compensation
- NPRR945, Net Metering Requirements
- NPRR946, Allow TDSPs to Use 814_28, Complete Un-executable Transactions for 814_03 Switch Transactions Involved In A Mass Transition Event
- NPRR947, Clarification to Ancillary Service Supply Responsibility Definition and Improvements to Determining and Charging for Ancillary Service Failed Quantities
- NPRR953, Addition of Relay Loadability Rating Definition
- NPRR955, Define Limited Impact Remedial Action Scheme (RAS)
- NPRR956, Designation of Providers of Transmission Additions
- NPRR963, Creation of Generation and Controllable Load Resource Group (GCLR Group)
- NPRR964, Improvement of RMR Process and Removal of Synchronous Condenser Unit and Agreement
- NPRR966, Changes to Support Reactive Power Coordination Tool
- NPRR967, Allow Limited Duration Resource Energy Offer Curve Updates Near Real-Time and Remove the 10 MW Limit
- 7. Review of Revision Request Language Vote — M. Henson
- NPRR970, Reliability Unit Commitment (RUC) Fuel Dispute Process Clarification
- NPRR971, Changing Energy Offer Curve Caps for Make-Whole Calculation Purposes and Replacing the Real-Time Average Incremental Energy Cost
- NPRR972, Enhancing Existing CRR Transaction Limit Process
- NPRR973, Add Definitions for Generator Step-Up and Main Power Transformer
- 8. Notice of Withdrawal
- NPRR934, Advance Action Notice (AAN) and Clarify Process for Resource Outage Approval Withdrawal
- 9. Resource Definition Task Force (RTF) — B. Wittmeyer
- 10. Other Business — M. Henson
- 2020 Meeting Schedule
- 2020 Membership/Segment Elections
- Adjourn — M. Henson
Documents 4
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| APPROVED Minutes PRS 20191010 | Meeting Minutes | docx | Nov 25 '19 |
| Agenda PRS 20191010 | Meeting Agenda | doc | Oct 8 '19 |
| No Action Required PRS 20191010 | Committee Report | pptx | Oct 8 '19 |
| October 10, 2019 PRS Meeting Materials | zip | Oct 9 '19 |