NPRR #972 · Revision Request
NPRR972 Enhancing Existing CRR Transaction Limit Process
ReasonMarket efficiencies or enhancements
Created2019-10-10
Approved2019-12-10
Sections Affected
7.5.2
Summary
This Nodal Protocol Revision Request (NPRR) provides ERCOT with authority to not open a transaction adjustment period for a CRR Auction, even if the total number of transactions submitted exceeds the transaction limit announced prior to the auction, as long as the total number of transactions submitted does not exceed the number of transactions that can be processed by ERCOT’s systems.
Action Log 4 milestones
-
Oct 10
PRSRecommended for Approval→ PRS for Impact Analysis consideration
-
Nov 13
PRSRecommended for Approval→ TAC for consideration
-
Nov 20
TACRecommended for Approval→ Board for consideration
-
Dec 10
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 972NPRR-01 Enhancing Existing CRR Transaction Limit Process 092519 | docx | Sep 25 '19 | Revision Request |
| 972NPRR-02 Impact Analysis 092519 | doc | Sep 25 '19 | Staff Report |
| 972NPRR-03 PRS Report 101019 | docx | Oct 14 '19 | Committee Report |
| 972NPRR-04 PRS Report 111319 | docx | Nov 13 '19 | Committee Report |
| 972NPRR-05 TAC Report 112019 | docx | Nov 21 '19 | Committee Report |
| 972NPRR-06 Board Report 121019 | docx | Dec 11 '19 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 10 '19 | Board of Directors Meeting | BOARD | Concluded |
| Nov 20 '19 | TAC Meeting | TAC | Concluded |
| Nov 13 '19 | PRS Meeting | PRS | Concluded |
| Oct 10 '19 | PRS Meeting | PRS | Concluded |