NPRR #956 · Revision Request
NPRR956 Designation of Providers of Transmission Additions
ReasonRegulatory requirements
Created2019-07-17
Sections Affected
3.11.4.13.11.4.83.11.4.9
Summary
This Nodal Protocol Revision Request (NPRR) modifies Section 3.11.4.8 to align with section 37.056 of the Texas Utilities Code, as amended by SB1938 86(R), which became effective on May 16, 2019. As amended, section 37.056 authorizes the Public Utility Commission of Texas (PUCT) to grant a Certificate of Convenience and Necessity (CCN) only to a Transmission Service Provider (TSP) that owns the Facilities to which a proposed Transmission Facility addition will interconnect, or to the lawful designee of such a TSP. If more than one TSP owns Facilities to which a proposed addition will interconnect, the PUCT may issue a CCN to each such TSP to construct the needed Facilities in “separate and discrete equal parts,” unless the TSPs agree to a different allocation of responsibility. SB1938’s allocation of project responsibility based on ownership of the Facilities to which an addition interconnects is consistent with the Protocols’ longstanding assignment of responsibility based on ownership of the Facility endpoints. For the sake of consistency, however, ERCOT proposes to revise Section 3.11.4.8 to more closely comport with the language of the statute. ERCOT notes that revised Section 3.11.4.8 applies not only to those projects requiring a CCN, but also to other Tier 1 projects that may not require a CCN and therefore do not come within the coverage of section 37.056. This is consistent with the Protocols’ existing allocation rules, which have long assigned responsibility for all Tier 1 and 2 projects. ERCOT proposes to incorporate section 37.056’s assignment rules into a new paragraph (2). ERCOT proposes to modify paragraph (1) to recognize that ERCOT’s role, upon completing an independent review, is simply to identify the owners of the existing facilities, rather than to formally designate transmission providers. ERCOT also proposes to remove language from paragraph (1) which contemplates that ERCOT may determine project responsibility in the event of a disagreement between TSPs and may assign responsibility to a new TSP when the originally assigned TSP has not diligently pursued the project. Both of these provisions are inconsistent with SB1938, which contemplates no such role for ERCOT. ERCOT also proposes new paragraph (3), which would establish an explicit mandate that the TSP diligenty pursue the project. Although such a mandate is already implicit in provisions that establish the designation of providers, ERCOT suggests that stating this more explicitly will provide greater transparency that responsibility for a project entails a duty to pursue the completion of that project. ERCOT notes that “TSP” as used in the Protocols includes Municipally Owned Utilities (MOUs) and Electric Cooperatives (ECs). Finally, ERCOT proposes revisions to Section 3.11.4.9, Regional Planning Group Acceptance and ERCOT Endorsement, to provide that ERCOT will issue a Market Notice instead of sending an acceptance letter or endorsement letter, following Regional Planning Group (RPG) acceptance of Tier 3 projects, and ERCOT’s endorsement of Tier 1 and Tier 2 projects. This change will ensure that all TSPs (and other Market Participants) receive documentation showing completion of the ERCOT review process. ERCOT notes that because SB1938 is already effective, ERCOT must comply with the amended statute irrespective of the status of this NPRR. Thus, to the limited extent ERCOT’s existing Protocols conflict with the statute, ERCOT is already precluded from complying with those provisions. ERCOT is currently developing independent review reports for several projects and will ensure that its processes comport with the amended statute as it develops those reports over the next few months.
Action Log 1 milestones
-
Jul 17
PRSDeferred/Tabled→ Language Consideration
Documents 5
| Name | Type | Posted | Classification |
|---|---|---|---|
| 956NPRR-01 Designation of Providers of Transmission Additions 070219 | doc | Jul 5 '19 | Revision Request |
| 956NPRR-02 Impact Analysis 070219 | doc | Jul 2 '19 | Staff Report |
| 956NPRR-03 PRS Report 071719 | doc | Jul 22 '19 | Committee Report |
| 956NPRR-04 ERCOT Comments 111219 | doc | Nov 12 '19 | Revision Request Comments |
| 956NPRR-05 ERCOT Comments 092122 | docx | Sep 21 '22 | Revision Request Comments |
Meetings That Took It Up 168
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 15 '26 | PRS Meeting | PRS | Scheduled |
| Jul 9 '26 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 10 '26 | PRS Meeting | PRS | Concluded |
| Jun 4 '26 | ROS Meeting | ROS | Concluded |
| May 7 '26 | ROS Meeting | ROS | Concluded |
| May 6 '26 | PRS Meeting | PRS | Concluded |
| Apr 15 '26 | PRS Meeting | PRS | Concluded |
| Apr 2 '26 | ROS Meeting | ROS | Concluded |
| Mar 11 '26 | PRS Meeting | PRS | Concluded |
| Mar 5 '26 | ROS Meeting | ROS | Concluded |
| Feb 11 '26 | PRS Meeting | PRS | Concluded |
| Feb 5 '26 | ROS Meeting | ROS | Concluded |
| Jan 14 '26 | PRS Meeting | PRS | Concluded |
| Jan 8 '26 | ROS Meeting | ROS | Concluded |
| Dec 10 '25 | PRS Meeting | PRS | Concluded |
| Dec 4 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Nov 12 '25 | PRS Meeting | PRS | Concluded |
| Nov 6 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Oct 8 '25 | PRS Meeting | PRS | Concluded |
| Oct 2 '25 | ROS Meeting | ROS | Concluded |
| Sep 17 '25 | PRS Meeting | PRS | Concluded |
| Sep 11 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Aug 13 '25 | PRS Meeting | PRS | Concluded |
| Aug 7 '25 | ROS Meeting | ROS | Concluded |
| Jul 16 '25 | PRS Meeting | PRS | Concluded |
| Jul 10 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 11 '25 | PRS Meeting | PRS | Concluded |
| Jun 5 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| May 14 '25 | PRS Meeting | PRS | Concluded |
| May 1 '25 | ROS Meeting | ROS | Concluded |
| Apr 9 '25 | PRS Meeting | PRS | Concluded |
| Apr 3 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Mar 12 '25 | PRS Meeting | PRS | Concluded |
| Mar 6 '25 | ROS Meeting | ROS | Concluded |
| Feb 12 '25 | PRS Meeting | PRS | Concluded |
| Feb 6 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Jan 15 '25 | PRS Meeting | PRS | Concluded |
| Jan 9 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Dec 12 '24 | PRS Meeting | PRS | Concluded |
| Dec 5 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Nov 14 '24 | PRS Meeting | PRS | Concluded |
| Nov 7 '24 | ROS Meeting | ROS | Concluded |
| Oct 17 '24 | PRS Meeting | PRS | Concluded |
| Oct 3 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Sep 12 '24 | PRS Meeting | PRS | Concluded |
| Sep 9 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Aug 8 '24 | PRS Meeting | PRS | Concluded |
| Aug 1 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Jul 18 '24 | PRS Meeting - Webex Only | PRS | Concluded |
| Jul 11 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 13 '24 | PRS Meeting | PRS | Concluded |
| Jun 6 '24 | ROS Meeting | ROS | Concluded |
| May 9 '24 | PRS Meeting | PRS | Concluded |
| May 2 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Apr 5 '24 | PRS Meeting - Webex Only | PRS | Concluded |
| Apr 4 '24 | ROS Meeting | ROS | Concluded |
| Mar 20 '24 | PRS Meeting | PRS | Concluded |
| Mar 7 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Feb 8 '24 | PRS Meeting | PRS | Concluded |
| Feb 1 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Jan 11 '24 | PRS Meeting | PRS | Concluded |
| Jan 8 '24 | ROS Meeting | ROS | Concluded |
| Dec 15 '23 | PRS Meeting - Webex Only | PRS | Concluded |
| Dec 7 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Nov 9 '23 | PRS Meeting | PRS | Concluded |
| Nov 2 '23 | ROS Meeting | ROS | Concluded |
| Oct 12 '23 | PRS Meeting | PRS | Concluded |
| Oct 5 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Sep 13 '23 | PRS Meeting | PRS | Concluded |
| Sep 7 '23 | ROS Meeting | ROS | Concluded |
| Aug 10 '23 | PRS Meeting | PRS | Concluded |
| Aug 3 '23 | ROS Meeting | ROS | Concluded |
| Jul 13 '23 | PRS Meeting | PRS | Concluded |
| Jul 6 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 14 '23 | PRS Meeting | PRS | Concluded |
| Jun 8 '23 | ROS Meeting | ROS | Concluded |
| May 10 '23 | PRS Meeting | PRS | Concluded |
| May 4 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Apr 13 '23 | PRS Meeting | PRS | Concluded |
| Apr 6 '23 | ROS Meeting | ROS | Concluded |
| Mar 8 '23 | PRS Meeting | PRS | Concluded |
| Mar 2 '23 | ROS Meeting | ROS | Concluded |
| Feb 9 '23 | PRS Meeting - Webex Only | PRS | Concluded |
| Feb 8 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Jan 17 '23 | PRS Meeting | PRS | Concluded |
| Jan 5 '23 | ROS Meeting | ROS | Concluded |
| Dec 8 '22 | PRS Meeting By Webex Only | PRS | Concluded |
| Dec 1 '22 | ROS Meeting by Webex Only | ROS | Concluded |
| Nov 11 '22 | PRS Meeting by Webex Only | PRS | Concluded |
| Nov 7 '22 | ROS Meeting by Webex Only | ROS | Concluded |
| Oct 13 '22 | PRS Meeting | PRS | Concluded |
| Sep 29 '22 | ROS Meeting by Webex Only | ROS | Concluded |
| Sep 15 '22 | PRS Meeting | PRS | Concluded |
| Sep 1 '22 | ROS Meeting | ROS | Concluded |
| Aug 11 '22 | PRS Meeting | PRS | Concluded |
| Aug 10 '22 | ROS Meeting | ROS | Concluded |
| Jul 13 '22 | PRS Meeting | PRS | Concluded |
| Jun 9 '22 | PRS Meeting | PRS | Concluded |
| Jun 2 '22 | ROS Meeting | ROS | Concluded |
| May 11 '22 | PRS Meeting | PRS | Concluded |
| May 5 '22 | ROS Meeting | ROS | Concluded |
| Apr 14 '22 | PRS Meeting | PRS | Concluded |
| Apr 12 '22 | PLWG Meeting | PLWG | Concluded |
| Apr 7 '22 | ROS Meeting | ROS | Concluded |
| Mar 9 '22 | PRS Meeting by Webex Only | PRS | Concluded |
| Mar 3 '22 | ROS Meeting by Webex Only | ROS | Concluded |
| Feb 9 '22 | PRS Meeting by Webex Only | PRS | Concluded |
| Feb 7 '22 | ROS Meeting by Webex Only | ROS | Concluded |
| Jan 13 '22 | PRS Meeting by Webex Only | PRS | Concluded |
| Jan 6 '22 | ROS Meeting by Webex Only | ROS | Concluded |
| Dec 14 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Dec 2 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Nov 10 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Nov 4 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Oct 14 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Oct 7 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Sep 16 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Sep 2 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Aug 12 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Aug 5 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Jul 15 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Jul 8 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Jun 10 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Jun 3 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| May 13 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Apr 29 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Apr 15 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Apr 1 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Mar 11 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Mar 4 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Feb 11 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Feb 4 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Jan 14 '21 | PRS Meeting by Webex Only | PRS | Concluded |
| Jan 7 '21 | ROS Meeting by Webex Only | ROS | Concluded |
| Dec 10 '20 | PRS Meeting by Webex Only | PRS | Concluded |
| Dec 3 '20 | ROS Meeting by Webex Only | ROS | Concluded |
| Nov 11 '20 | PRS Meeting by Webex Only | PRS | Concluded |
| Nov 5 '20 | ROS Meeting by Webex Only | ROS | Concluded |
| Oct 15 '20 | PRS Meeting by Webex Only | PRS | Concluded |
| Oct 8 '20 | ROS Meeting by Webex Only | ROS | Concluded |
| Sep 10 '20 | PRS Meeting | PRS | Concluded |
| Sep 3 '20 | ROS Meeting | ROS | Concluded |
| Aug 13 '20 | PRS Meeting | PRS | Concluded |
| Aug 6 '20 | ROS Meeting | ROS | Concluded |
| Jul 16 '20 | PRS Meeting | PRS | Concluded |
| Jul 9 '20 | ROS Meeting | ROS | Concluded |
| Jun 11 '20 | PRS Meeting | PRS | Concluded |
| Jun 4 '20 | ROS Meeting | ROS | Concluded |
| May 13 '20 | PRS Meeting by Webex Only | PRS | Concluded |
| May 7 '20 | ROS Information Session - Webex Only | ROS | Concluded |
| Apr 16 '20 | PRS Information Session - WebEx Only | PRS | Concluded |
| Mar 25 '20 | PRS Information Session - WebEx only | PRS | Concluded |
| Mar 5 '20 | ROS Information Session by WebEx Only | ROS | Concluded |
| Feb 13 '20 | PRS Meeting | PRS | Concluded |
| Feb 6 '20 | ROS Meeting | ROS | Concluded |
| Jan 16 '20 | PRS Meeting | PRS | Concluded |
| Jan 9 '20 | ROS Meeting | ROS | Concluded |
| Dec 12 '19 | PRS Meeting | PRS | Concluded |
| Dec 5 '19 | ROS Meeting | ROS | Concluded |
| Nov 13 '19 | PRS Meeting | PRS | Concluded |
| Nov 7 '19 | ROS Meeting | ROS | Concluded |
| Oct 10 '19 | PRS Meeting | PRS | Concluded |
| Oct 3 '19 | ROS Meeting | ROS | Concluded |
| Sep 12 '19 | PRS Meeting | PRS | Concluded |
| Sep 5 '19 | ROS Meeting | ROS | Concluded |
| Aug 15 '19 | PRS Meeting | PRS | Concluded |
| Aug 8 '19 | ROS Meeting | ROS | Concluded |
| Jul 17 '19 | PRS Meeting | PRS | Concluded |