ReasonClarifying current practices and providing additional detail and other enhancements based on industry practices and market expectations, and addressing an existing risk to the ERCOT System.
Created2018-10-18
Approved2019-12-10
Sections Affected
1.31.3.11.3.1.11.3.1.21.3.21.3.31.3.2 (new)1.3.2.1 (new)1.3.2.2 (new)1.3.2.3 (new)1.3.3 (new)1.3.41.3.51.3.61.3.81.3.9 (delete)2.12.23.103.10.23.10.33.10.412.112.317.3.217.4
Summary
This Nodal Protocol Revision Request (NPRR) clarifies parties’ responsibilities regarding ERCOT Critical Energy Infrastructure Information (ECEII). This NPRR defines ECEII, adds lists of items that are considered ECEII, specifies the restrictions imposed upon parties that receive or create ECEII, and provides a framework for the submission of ECEII to ERCOT. A process has been created for contesting ERCOT determinations regarding confidentiality status. This NPRR also deletes language in Section 1.3.1.2 that is duplicative of paragraph (1)(b) of Planning Guide Section 5.5.4, Notification to ERCOT Concerning Certain Project Developments. The Federal Energy Regulatory Commission (FERC), in a series of orders issued in 2003, adopted a definition of Critical Energy Infrastructure Information (CEII) and established regulations for submitting CEII to and obtaining CEII from FERC. Subsequent FERC orders further refined these regulations. While the FERC regulations do not require ERCOT to adopt similar rules regarding the handling of CEII, the Protocols currently include a definition for CEII, closely based on the FERC definition, although there are only minimal requirements regarding CEII in the current Protocols. In practice, ERCOT restricts access to CEII, and strongly believes that limiting access and requiring secure handling of CEII is reasonable and appropriate in connection with its role as the recipient and producer of vast amounts of information, some of which is sensitive for commercial or security reasons. The rules proposed in this NPRR are based on a review of FERC’s CEII regulations and similar rules adopted by other Independent System Operators (ISOs) and Regional Transmission Organizations (RTOs). The Market Information System (MIS) Secure Area was intended to be used for ERCOT to provide routine Market Participant access to information that is sensitive for security reasons – i.e., ECEII. Paragraph (1) of Section 12.1 states in part that “[t]he MIS Secure Area provides restricted access to critical energy infrastructure information.” While much of the information currently required by the Protocols and Other Binding Documents to be posted on the MIS Secure Area does constitute ECEII, ERCOT Staff has identified several instances in which information required to be posted on the MIS Secure Area is not ECEII and thus would be more appropriately located on the MIS Public Area. As a follow-up to this NPRR, ERCOT Staff intends to conduct a more comprehensive review of items required to be posted on the MIS Secure Area, and expects to submit one or more additional Revision Requests to relocate those items that do not constitute ECEII. To provide Market Participants time to adjust their processes to account for the changes enacted through this NPRR, ERCOT proposes that the NPRR become effective on the first day of the seventh month following ERCOT Board approval (e.g., July 1, 2019 effective date if approved by the ERCOT Board at its December 2018 meeting).
Action Log 5 milestones
Amendments
DateBodyMotionResult
Sep 12 '19PRS to recommend approval of NPRR902 as amended by the 9/4/19 ERCOT commentsPassed
Oct 10 '19PRS to endorse and forward to TAC the 9/12/19 PRS Report and Revised Impact Analysis for NPRR902 with a recommended priority of 2020 and a rank of 2890Passed
Oct 23 '19TAC to recommend approval of NPRR902 as recommended by PRS in the 10/10/19 PRS Report as amended by the 10/16/19 ERCOT comments, with a revised rank of 2930 and a revised proposed effective date of upon system implementation but no earlier than July 1, 2020Passed
Documents 16
NameTypePostedClassification
902NPRR-01 ERCOT Critical Energy Infrastructure Information 092818 doc Sep 28 '18 Revision Request
902NPRR-02 Impact Analysis 092818 doc Sep 28 '18 Staff Report
902NPRR-03 PRS Report 101818 doc Oct 22 '18 Committee Report
902NPRR-04 ERCOT Comments 031319 doc Mar 13 '19 Revision Request Comments
902NPRR-05 Oncor Comments 050319 doc May 3 '19 Revision Request Comments
902NPRR-06 ERCOT Comments 060319 doc Jun 3 '19 Revision Request Comments
902NPRR-07 ERCOT Comments 070819 doc Jul 8 '19 Revision Request Comments
902NPRR-08 MSCGI Comments 071619 doc Jul 16 '19 Revision Request Comments
902NPRR-09 Joint NOIE Comments 080719 doc Aug 7 '19 Revision Request Comments
902NPRR-10 ERCOT Comments 090419 doc Sep 4 '19 Revision Request Comments
902NPRR-11 PRS Report 091219 doc Sep 16 '19 Committee Report
902NPRR-12 Revised Impact Analysis 100319 docx Oct 3 '19 Staff Report
902NPRR-13 PRS Report 101019 doc Oct 14 '19 Committee Report
902NPRR-14 ERCOT Comments 101619 doc Oct 16 '19 Revision Request Comments
902NPRR-15 TAC Report 102319.DOCX docx Oct 25 '19 Committee Report
902NPRR-16 Board Report 121019 docx Dec 12 '19 Committee Report
Meetings That Took It Up 31
DateMeetingCommitteeStatus
Jun 23 '21 TAC Meeting by Webex Only TAC Concluded
May 26 '21 TAC Meeting by Webex Only TAC Concluded
Apr 22 '21 NPRR902 Implementation Workshop by Webex Only Concluded
Mar 24 '21 TAC Meeting by Webex Only TAC Concluded
Jan 27 '21 TAC Meeting by Webex Only TAC Concluded
Sep 23 '20 TAC Meeting by Webex Only TAC Concluded
Aug 11 '20 Urgent Board of Directors Meeting – Teleconference Available by Webcast BOARD Concluded
Jun 24 '20 TAC Meeting TAC Concluded
Jun 11 '20 PRS Meeting PRS Concluded
May 13 '20 PRS Meeting by Webex Only PRS Concluded
Apr 16 '20 PRS Information Session - WebEx Only PRS Concluded
Mar 25 '20 PRS Information Session - WebEx only PRS Concluded
Feb 13 '20 PRS Meeting PRS Concluded
Dec 10 '19 Board of Directors Meeting BOARD Concluded
Oct 23 '19 TAC Meeting TAC Concluded
Oct 10 '19 PRS Meeting PRS Concluded
Sep 12 '19 PRS Meeting PRS Concluded
Aug 15 '19 PRS Meeting PRS Concluded
Jul 17 '19 PRS Meeting PRS Concluded
Jun 17 '19 NPRR902 Workshop III Concluded
Jun 13 '19 PRS Meeting PRS Concluded
May 9 '19 PRS Meeting PRS Concluded
Apr 11 '19 PRS Meeting PRS Concluded
Mar 14 '19 PRS Meeting PRS Concluded
Feb 14 '19 PRS Meeting PRS Concluded
Jan 31 '19 NPRR902 Workshop II Concluded
Jan 17 '19 PRS Meeting PRS Concluded
Dec 13 '18 PRS Meeting PRS Concluded
Dec 4 '18 NPRR902 Workshop Concluded
Nov 15 '18 PRS Meeting PRS Concluded