NPRR #955 · Revision Request
NPRR955 Define Limited Impact Remedial Action Scheme (RAS)
- PRS Jan 16 '20
- TAC Jan 29 '20
- BOARD Feb 11 '20
- PUCT —
ReasonAddresses current operational issues
Created2019-07-17
Approved2020-02-11
Sections Affected
2.1
Summary
This Nodal Protocol Revision Request defines a Limited Impact RAS to accommodate North American Reliability Corporation (NERC) Reliability Standard PRC-012-2, Remedial Action Schemes.
Timeline
- Jun 28
-
Jul 17
PRS PRS MeetingPRSDeferred/Tabled Referred → ROS“to table NPRR955 and refer the issue to ROS” — Passed→ Language Consideration
- Jul 25
-
Aug 8
Listed without action at 1 meeting
- Aug 15
-
Aug 22
Listed without action at 11 meetings (Aug 22 '19 – Nov 21 '19)
- Dec 5
-
Dec 12
PRS PRS MeetingPRSRecommended for Approval Amended by the Dec 3 '19 ERCOT comments“to recommend approval of NPRR955 as amended by the 12/3/19 ERCOT comments” — Passed→ Impact Analysis Consideration
-
Jan 16
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 12/12/19 PRS Report and Impact Analysis for NPRR955, with a recommended effective date of October 1, 2020” — Passed→ Revision Request Consideration
-
Jan 29
TAC TAC MeetingTACRecommended for Approval“to recommend approval of NPRR955 as recommended by PRS in the 1/16/20 PRS Report” — Passed→ Revision Request Consideration
-
Feb 11
BOARD Board of Directors MeetingBOARDApproved“to approve NPRR955 as recommended by TAC in the 1/29/20 TAC Report” — Passed
-
—
Posted since the last meeting