NPRR #1284 · Revision Request
NPRR1284 Guaranteed Reliability Load Process
ReasonStrategic Plan Objective 1
Created2025-06-11
Sections Affected
2.12.23.11.7 (new)3.11.7.1 (new)3.11.7.2 (new)3.11.7.3 (new)3.11.7.4 (new)3.11.7.5 (new)and 23T (new)
Summary
This Nodal Protocol Revision Request (NPRR) creates a “bridging solution” where Loads that are willing to be contractually bound to curtail all or a part of their Load or self-provide their Load from backup generation during certain conditions, will be allowed to have that action considered as a “Manual System Adjustment” when the Load is studied under Planning Guides Sections 4.1.1.2, Reliability Performance Criteria, and Section 4.1.1.8, Maintenance Outage Reliability Criteria, for interconnection to the ERCOT grid. During the bridging period if conditions noted by the studies warrant, the Load will be instructed to curtail up to its contracted amount until the noted constraint is alleviated. The interconnection studies will also be performed with the Load considered firm to provide the full list of upgrades that will be performed. Once the upgrades are completed the Load will be released from this obligation.
Action Log 1 milestones
-
Jun 11
PRSDeferred/Tabled→ PRS for consideration
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Dec 3 '25 | WMS | Motion Carries | 7.5 | 0 | 0 | xls |
| Jul 10 '25 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
| Jul 9 '25 | WMS | Motion Carries | 7.5 | 0 | 0 | xls |
| Jun 11 '25 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 10
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1284NPRR-01 Guaranteed Reliability Load Process 051225 | docx | May 12 '25 | Revision Request |
| 1284NPRR-02 PRS Ballot 061125 | xls | Jun 13 '25 | Revision Request Ballot |
| 1284NPRR-03 PRS Report 061125 | docx | Jun 13 '25 | Committee Report |
| 1284NPRR-04 WMS Ballot 070925 | xls | Jul 9 '25 | Revision Request Ballot |
| 1284NPRR-05 WMS Comments 070925 | docx | Jul 9 '25 | Revision Request Comments |
| 1284NPRR-06 Google Comments 071125 | docx | Jul 11 '25 | Revision Request Comments |
| 1284NPRR-07 ROS Ballot 071025 | xls | Jul 14 '25 | Revision Request Ballot |
| 1284NPRR-08 ROS Comments 071425 | docx | Jul 14 '25 | Revision Request Comments |
| 1284NPRR-09 WMS Ballot 120325 | xls | Dec 3 '25 | Revision Request Ballot |
| 1284NPRR-10 WMS Comments 120325 | docx | Dec 3 '25 | Revision Request Comments |
Meetings That Took It Up 56
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 15 '26 | PRS Meeting | PRS | Scheduled |
| Jul 9 '26 | ROS Meeting - Webex Only | ROS | Concluded |
| Jul 8 '26 | WMS Meeting - Webex Only | WMS | Concluded |
| Jun 22 '26 | PLWG Meeting | PLWG | Concluded |
| Jun 10 '26 | PRS Meeting | PRS | Concluded |
| Jun 4 '26 | ROS Meeting | ROS | Concluded |
| Jun 3 '26 | WMS Meeting | WMS | Concluded |
| May 11 '26 | PLWG Meeting | PLWG | Concluded |
| May 8 '26 | WMS Meeting | WMS | Concluded |
| May 7 '26 | ROS Meeting | ROS | Concluded |
| May 6 '26 | PRS Meeting | PRS | Concluded |
| Apr 15 '26 | PRS Meeting | PRS | Concluded |
| Apr 13 '26 | PLWG Meeting | PLWG | Concluded |
| Apr 2 '26 | ROS Meeting | ROS | Concluded |
| Apr 1 '26 | WMS Meeting | WMS | Concluded |
| Mar 11 '26 | PRS Meeting | PRS | Concluded |
| Mar 6 '26 | PLWG Meeting - Webex Only | PLWG | Concluded |
| Mar 5 '26 | ROS Meeting | ROS | Concluded |
| Mar 4 '26 | WMS Meeting | WMS | Concluded |
| Feb 11 '26 | PRS Meeting | PRS | Concluded |
| Feb 5 '26 | ROS Meeting | ROS | Concluded |
| Feb 4 '26 | WMS Meeting | WMS | Concluded |
| Feb 2 '26 | PLWG Meeting | PLWG | Concluded |
| Jan 16 '26 | PLWG Meeting | PLWG | Concluded |
| Jan 14 '26 | PRS Meeting | PRS | Concluded |
| Jan 8 '26 | ROS Meeting | ROS | Concluded |
| Jan 7 '26 | WMS Meeting | WMS | Concluded |
| Dec 16 '25 | PLWG Meeting | PLWG | Concluded |
| Dec 15 '25 | CMWG Meeting - Webex Only | CMWG | Concluded |
| Dec 10 '25 | PRS Meeting | PRS | Concluded |
| Dec 4 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Dec 3 '25 | WMS Meeting - Webex Only | WMS | Concluded |
| Nov 18 '25 | PLWG Meeting - Webex Only | PLWG | Concluded |
| Nov 12 '25 | PRS Meeting | PRS | Concluded |
| Nov 6 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Nov 5 '25 | WMS Meeting | WMS | Concluded |
| Nov 3 '25 | WMWG Meeting - Webex Only | WMWG | Concluded |
| Oct 28 '25 | PLWG Meeting | PLWG | Concluded |
| Oct 8 '25 | PRS Meeting | PRS | Concluded |
| Oct 3 '25 | WMS Meeting | WMS | Concluded |
| Oct 2 '25 | ROS Meeting | ROS | Concluded |
| Sep 25 '25 | PLWG Meeting | PLWG | Concluded |
| Sep 17 '25 | PRS Meeting | PRS | Concluded |
| Sep 11 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Sep 10 '25 | WMS Meeting | WMS | Concluded |
| Aug 26 '25 | PLWG Meeting | PLWG | Concluded |
| Aug 13 '25 | PRS Meeting | PRS | Concluded |
| Aug 7 '25 | ROS Meeting | ROS | Concluded |
| Aug 6 '25 | WMS Meeting - Webex Only | WMS | Concluded |
| Jul 29 '25 | PLWG Meeting | PLWG | Concluded |
| Jul 16 '25 | PRS Meeting | PRS | Concluded |
| Jul 10 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Jul 9 '25 | WMS Meeting | WMS | Concluded |
| Jun 11 '25 | PRS Meeting | PRS | Concluded |
| Jun 5 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| May 16 '25 | LLWG Meeting - Webex Only | LLWG | Concluded |