Meeting · PRS
PRS Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Room 206
Revision Requests On The Agenda
NPRR131NPRR153NPRR156NPRR164NPRR169NPRR181NPRR190NPRR194NPRR196PRR754PRR803PRR821PRR824PRR826PRR827PRR830PRR832PRR833PRR834PRR835PRR836PRR837
Agenda 14 items
- 1. Antitrust Admonition — S. Morris
-
2.
Approval of Minutes September 17, 2009 September 22, 2009 Vote
— S. Morris
- DRAFT Minutes PRS 20090917 · Meeting Minutes
- DRAFT Minutes PRS 20090922.Special · Meeting Minutes
- 3. Urgency Votes PRR834, ERCOT Load Forecast Accuracy - URGENT PRR835, Reactive Capability Requirement URGENT PRR836, Revised Minimum Ramp Rate for Balancing Energy Service Down to Comport with PRR803 - URGENT Vote — S. Morris
- 4. TAC and Board Reports — S. Morris
- 5. Project Update and Summary of Project Priority List (PPL) Activity to Date Parking Deck Vote — T. Anderson
- 6. Other Binding Documents Update — D. Seibert
- 7. Review of Recommendation Report, Impact Analysis and Cost/Benefit Analysis PRR821, Update of Section 21, Process for Protocol Revision PRR824, Primary Frequency Response from WGRs PRR827, Find Transaction and Find ESI ID Functions on the MIS NPRR196, Synchronization of Nodal Protocols with PRR827, Find Transaction and Find ESI ID Functions on the MIS Vote — S. Morris
- 8. Review of Protocol Revision Requests (PRRs) Language PRR826, Clarification of Resource Definitions and Resource Registration of Self-Serve Generators for Reliability Purposes, PRR830, Reactive Power Capability Requirement URGENT PRR832, Deletion of Schedule Control Error (SCR) Posting Requirement PRR833, Primary Frequency Response Requirement from Existing WGRs PRR834, ERCOT Load Forecast Accuracy - URGENT PRR835, Reactive Capability Requirement - URGENT PRR836, Revised Minimum Ramp Rate for Balancing Energy Service Down to Comport with PRR803 - URGENT Vote — S. Morris
- 9. Review of Nodal Protocol Revision Requests (NPRRs) Language NPRR190, Clarification of Resource Definitions and Resource Registration of Self-Serve Generators for Reliability Purposes NPRR194, Synchronization of Zonal Unannounced Generation Capacity Testing Process Vote — S. Morris
- 10. NPRRs with CEO Determination of Not Needed for Go-Live NPRR131, Ancillary Service Trades with ERCOT NPRR153, Generation Resource Fixed Quantity Block NPRR156, Transparency for PSS and Full Interconnection Studies NPRR164, Resubmitting Ancillary Service Offers in SASM NPRR169, Clarify the Calculation and Posting of LMPs for the Load Zone and LMPs for each Hub NPRR181, FIP Definition Revision Vote — S. Morris
- 11. Notice of Withdrawal — S. Morris
- 12. Other Business PRR754, Resource Settlement Due To Forced Transmission Outage Nodal Protocol/Reliability Standards Alignment (NPRSA) Task Force Discussion PRR837, Load Used in RMR Studies Vote — S. Morris D. Walker M. Wagner
- 13. Adjourn — S. Morris
- 14. Future PRS Meetings November 19, 2009 December 17, 2009
Documents 5
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| Additional 102209 PRS Meeting Materials | zip | Oct 19 '09 | |
| Additional 102209 PRS Meeting Materials - 2 | zip | Oct 22 '09 | |
| Agenda_PRS_Meeting_102209_Rev2 | Meeting Agenda | doc | Oct 19 '09 |
| APPROVED Minutes PRS 20091022 | Meeting Minutes | doc | Dec 27 '09 |
| October 22, 2009 PRS Meeting Materials | zip | Oct 15 '09 |