NPRR #194 · Revision Request

NPRR194  Synchronization of Zonal Unannounced Generation Capacity Testing Process

Approved sponsor ERCOT posted 2009-08-18 ercot.com
ReasonTo provide a mechanism for ERCOT to verify that reported HSLs truly reflect a Resource’s capability.
Created2009-08-25
Approved2010-01-19
Sections Affected
6.6.96.6.9.16.6.9.28.1.1.2
Summary
This Nodal Protocol Revision Request (NPRR) replaces the seasonal testing requirement with unannounced Generation Resource testing and adds a requirement for Qualified Scheduling Entities (QSEs) to seasonally update their Resources’ High Sustainable Limits (HSLs). The NPRR also leverages existing emergency operations Settlement functionality to provide a mechanism to compensate a Generation Resource for the additional energy above the pre-test Security-Constrained Economic Dispatch (SCED) Base Point during the unannounced Generation Resource test period. This NPRR synchronizes the Nodal Protocols with the process added to the zonal Protocols pursuant to Protocol Revision Request (PRR) 750, Unannounced Generation Capacity Testing.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Nov 19 '09PRS To recommend approval of NPRR194 as amended by the 11/17/09 Luminant Energy comments and as revised by PRS.Passed
Documents 17
NameTypePostedClassification
194NPRR-01 Synchronization of Zonal Unannounced Generation Capac doc Aug 18 '09 Revision Request
194NPRR-02 CEO Revision Request Review 081809 doc Aug 18 '09 Committee Report
194NPRR-03 Luminant Energy Comments 082409 doc Nov 12 '09 Revision Request Comments
194NPRR-04 PRS Action Report 082509 doc Aug 27 '09 Committee Report
194NPRR-05 ROS Comments 091109 doc Sep 11 '09 Revision Request Comments
194NPRR-06 Luminant Energy Comments 101409 doc Oct 14 '09 Revision Request Comments
194NPRR-07 ROS Comments 101909 doc Oct 19 '09 Revision Request Comments
194NPRR-08 CPS Energy Comments 101909 doc Oct 19 '09 Revision Request Comments
194NPRR-09 TMPA Comments 102009 doc Oct 20 '09 Revision Request Comments
194NPRR-10 PRS Action Report 102209 doc Oct 23 '09 Committee Report
194NPRR-11 Luminant Energy Comments 111209 doc Nov 12 '09 Revision Request Comments
194NPRR-12 Luminant Energy Comments 111709 doc Nov 17 '09 Revision Request Comments
194NPRR-13 PRS Recommendation Report 111909 doc Nov 23 '09 Committee Report
194NPRR-14 Impact Analysis 120109 doc Dec 1 '09 Staff Report
194NPRR-15 PRS Recommendation Report 121709 doc Dec 18 '09 Committee Report
194NPRR-16 TAC Report 010610 doc Jan 7 '10 Committee Report
194NPRR-17 Board Report 011910 doc Jan 19 '10 Committee Report
Meetings That Took It Up 8
DateMeetingCommitteeStatus
Jun 8 '10 QSE Managers Working Group Meeting QMWG Concluded
Jan 6 '10 TAC Meeting TAC Concluded
Dec 17 '09 PRS Meeting PRS Concluded
Nov 19 '09 PRS Meeting PRS Concluded
Oct 22 '09 PRS Meeting PRS Concluded
Oct 15 '09 ROS Meeting ROS Concluded
Sep 10 '09 ROS Meeting ROS Concluded
Aug 25 '09 PRS Meeting PRS Concluded