NPRR #156 · Revision Request

NPRR156  Transparency for PSS and Full Interconnection Studies

Approved sponsor Marguerite Wagner/PSEG Texas posted 2008-09-18 ercot.com
ReasonTo provide additional information for ERCOT and Market Participants related to generation equipment that affects stability limits and information about potential generation interconnections at the time a full interconnection study is requested.
Created2008-10-23
Approved2010-03-23
Sections Affected
1.3.1.1Items Considered Protected Information 1.3.1.2Items Not Considered Protected Information
Summary
Updates to Section 1 & 12 to provide transparency to status of Power System Stabilizer Equipment and interconnection requests.
Action Log 12 milestones
Amendments
DateBodyMotionResult
Jan 22 '09PRS To recommend approval of NPRR156 as amended by the 12/11/08 PSEG commentsPassed
Feb 18 '10PRS To recommend approval of NPRR156 as amended by the 2/11/10 Luminant comments and as revised by PRS.Passed
Mar 23 '10BOARD To approve NPRR156 as recommended by TAC in the 3/4/10 TAC Report and as amended by the 3/11/10 ERCOT comments.Passed
Apr 23 '09PRS To recommend approval of NPRR156 as amended by the 4/22/09 PSEG Texas comments.Passed
Mar 4 '10TAC To recommend approval of NPRR156 as amended by the 3/4/10 ERCOT comments, with the recognition that ERCOT will continue with Option 3, Manual Interim Option (described in the 3/4/10 ERCOT comments), to fulfill the requirement of item (7) of Section 3.15.3 until Option 2, Include PSS Status Information in the RARF, can be implemented to automate the solution.Passed
Documents 34
NameTypePostedClassification
156NPRR-01Transparency for PSS and Full Interconnection Studies doc Sep 19 '08 Revision Request
156NPRR-02 TPTF Comments 101608 doc Oct 16 '08 Revision Request Comments
156NPRR-03 TPTF Voting Ballot 101608 xls Feb 9 '09 Revision Request Ballot
156NPRR-04 TPTF Voting Ballot 101608 xls Feb 6 '09 Revision Request Ballot
156NPRR-05 PSEG Comments 102008 doc Oct 20 '08 Revision Request Comments
156NPRR-06 PRS Action Report 102308 doc Oct 27 '08 Committee Report
156NPRR-07 PSEG Texas Comments 111208 doc Nov 17 '08 Revision Request Comments
156NPRR-08 PRS Action Report 112008 doc Nov 25 '08 Committee Report
156NPRR-09 PSEG Texas Comments 121108 doc Dec 11 '08 Revision Request Comments
156NPRR-10 PRS Action Report 121808 doc Dec 19 '08 Committee Report
156NPRR-11 PRS Recommendation Report 012209 doc Jan 26 '09 Committee Report
156NPRR-12 ERCOT Comments 013009 doc Jan 30 '09 Revision Request Comments
156NPRR-13 TPTF Comments 022609 doc Feb 26 '09 Revision Request Comments
156NPRR-14 TPTF Voting Ballot 022609 xls Feb 23 '09 Revision Request Ballot
156NPRR-15 ERCOT Comments 041609 doc Apr 16 '09 Revision Request Comments
156NPRR-16 PSEG Texas Comments 042209 doc Apr 22 '09 Revision Request Comments
156NPRR-17 PRS Recommendation Report 042309 doc Apr 24 '09 Committee Report
156NPRR-18 CEO Revision Request Review 051109 doc May 11 '09 Revision Request Comments
156NPRR-19 PSEG TX Comments 052009 doc May 20 '09 Revision Request Comments
156NPRR-20 PRS Action Report 052109 doc May 22 '09 Committee Report
156NPRR-21 Impact Analysis 111609 doc Nov 16 '09 Staff Report
156NPRR-22 PRS Action Report 111909 doc Nov 23 '09 Committee Report
156NPRR-23 ERCOT Comments 120809 doc Dec 8 '09 Revision Request Comments
156NPRR-24 PRS Action Report 121709 doc Dec 21 '09 Committee Report
156NPRR-25 PRS Action Report 012110 doc Jan 22 '10 Committee Report
156NPRR-26 Luminant Energy Comments 021110 doc Feb 11 '10 Revision Request Comments
156NPRR-27 PRS Report 021810 doc Feb 23 '10 Committee Report
156NPRR-28 ERCOT Comments 022510 doc Feb 25 '10 Revision Request Comments
156NPRR-29 ERCOT Comments 030410 doc Mar 4 '10 Revision Request Comments
156NPRR-30 TAC Report 030410 doc Mar 7 '10 Committee Report
156NPRR-31 Revised CEO Revisio Request Review 030810 doc Mar 8 '10 Staff Report
156NPRR-32 Revised Impact Analysis 030910 doc Mar 9 '10 Staff Report
156NPRR-33 ERCOT Comments 031110 doc Mar 11 '10 Revision Request Comments
156NPRR-34 Board Report 032310 doc Mar 23 '10 Committee Report
Meetings That Took It Up 17
DateMeetingCommitteeStatus
Mar 4 '10 TAC Meeting TAC Concluded
Feb 18 '10 PRS Meeting PRS Concluded
Jan 21 '10 PRS Meeting PRS Concluded
Dec 17 '09 PRS Meeting PRS Concluded
Nov 19 '09 PRS Meeting PRS Concluded
Oct 22 '09 PRS Meeting PRS Concluded
May 21 '09 PRS Meeting PRS Concluded
Apr 23 '09 PRS Meeting PRS Concluded
Mar 19 '09 PRS Meeting PRS Concluded
Feb 23 '09 TPTF Meeting TPTF Concluded
Feb 19 '09 PRS Meeting PRS Concluded
Feb 19 '09 Credit Work Group Conference Call CREDITWG Concluded
Jan 22 '09 PRS Meeting PRS Concluded
Dec 18 '08 PRS Meeting PRS Concluded
Nov 20 '08 PRS Meeting PRS Concluded
Oct 23 '08 PRS Meeting PRS Concluded
Oct 13 '08 TPTF Meeting TPTF Concluded