PGRR #140 · Revision Request

PGRR140  Related to NPRR1317, Creation of Non-Settled Generator (NSG) and Clarification of the Types, Usage, and Registration of Distributed Generation

Pending sponsor ERCOT posted 2025-12-19 next ROS for consideration (ROS) ercot.com
ReasonRegulatory requirements
Created2026-01-08
Sections Affected
5.2.15.2.25.2.45.2.95.3.15.3.25.3.2.15.3.2.4.15.3.45.3.55.4.2and 5.5
Summary
This Planning Guide Revision Request (PGRR) clarifies types and usage of “Distributed Generation” within the Planning Guide in alignment with NPRR1317.
Action Log 1 milestones
Ballots
DateBodyResultYesNoAbstain
Jan 8 '26 ROS Motion Carries 7.5 0 0 xls
Documents 7
NameTypePostedClassification
140PGRR-01 Related to NPRR1317, Creation of Non-Settled Generator (NSG) and Clarification of the Types, Usage, and Registration of Distributed Generation 121925 docx Dec 19 '25 Revision Request
140PGRR-02 Impact Analysis 121925 docx Dec 19 '25 Staff Report
140PGRR-03 ROS Ballot 010826 xls Jan 12 '26 Revision Request Ballot
140PGRR-04 ROS Report 010826 docx Jan 12 '26 Committee Report
140PGRR-05 ERCOT Comments 050626 docx May 6 '26 Revision Request Comments
140PGRR-06 Vistra Comments 052826 docx May 28 '26 Revision Request Comments
140PGRR-07 Priority Power Comments 060226 docx Jun 2 '26 Revision Request Comments
Meetings That Took It Up 8
DateMeetingCommitteeStatus
Jul 9 '26 ROS Meeting - Webex Only ROS Concluded
Jun 4 '26 ROS Meeting ROS Concluded
May 7 '26 ROS Meeting ROS Concluded
Apr 2 '26 ROS Meeting ROS Concluded
Mar 5 '26 ROS Meeting ROS Concluded
Feb 5 '26 ROS Meeting ROS Concluded
Feb 2 '26 PLWG Meeting PLWG Concluded
Jan 8 '26 ROS Meeting ROS Concluded