PGRR #140 · Revision Request
PGRR140 Related to NPRR1317, Creation of Non-Settled Generator (NSG) and Clarification of the Types, Usage, and Registration of Distributed Generation
- ROS now · Impact Analysis
- TAC
- BOARD
- PUCT
ReasonRegulatory requirements
Created2026-01-08
Sections Affected
5.2.15.2.25.2.45.2.95.3.15.3.25.3.2.15.3.2.4.15.3.45.3.55.4.2and 5.5
Summary
This Planning Guide Revision Request (PGRR) clarifies types and usage of “Distributed Generation” within the Planning Guide in alignment with NPRR1317.
Timeline
- Dec 19
-
Jan 8
ROS ROS MeetingROSDeferred/Tabled Referred → NDSWG Referred → PLWG“To table PGRR140 and refer the issue to the Network Data Support Working Group (NDSWG) and the Planning Working Group (PLWG)” — Passed→ ROS for consideration
- Feb 2
-
Feb 5
Listed without action at 3 meetings (Feb 5 '26 – Apr 2 '26)
- May 7
- Jun 4
-
Jul 9
Listed without action at 1 meeting
-
Aug 6
ROS ROS MeetingROSRecommended for Approval Amended by the May 6 '26 ERCOT comments“To recommend approval of PGRR140 as amended by the 5/6/26 ERCOT comments” — Passed→ ROS for Impact Analysis consideration
-
—
Posted since the last meeting