NPRR #333 · Revision Request
NPRR333 Removal of Redundant Reporting Requirement Related to Equipment Ratings
- PRS May 19 '11
- TAC Jun 2 '11
- BOARD Jul 19 '11
- PUCT —
ReasonThe reporting requirement in paragraph (3) of Section 3.10 is a subset of a similar reporting requirement in paragraph (4) of Section 3.10.4, ERCOT Responsibilities. ERCOT proposes to eliminate the smaller report required by Section 3.10 in favor of the report required by Section 3.10.4.
Created2011-03-24
Approved2011-07-19
Sections Affected
3.10
Summary
This Nodal Protocol Revision Request (NPRR) removes a redundant requirement for ERCOT to produce a report regarding equipment Ratings.
Timeline
- Feb 25
- Mar 24
-
Apr 21
PRS PRS MeetingPRSRecommended for Approval“To recommend approval of NPRR333 as submitted” — Passed→ PRS IA Review
-
May 19
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward the 4/21/11 PRS Report and Impact Analysis to TAC” — Passed→ TAC Consideration
-
Jun 2
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR333 as recommended by PRS in the 5/19/11 PRS Report” — Passed→ ERCOT Board Consideration
-
Jul 19
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR333 as recommended by TAC in the 6/2/11 TAC Report” — Passed