NPRR #332 · Revision Request

NPRR332  Revise QSGR Processes for COP Reporting of QSGR Assigned Off-Line Non-Spin and Application of Emergency Operations Settlement

Approved sponsor ERCOT posted 2011-02-25 ercot.com
ReasonThe process changes included in this NPRR: Clarify the QSE’s responsibilities in regard to its QSGR Resources that are providing Off-Line Non-Spin; and Reduce the communications demands placed on the QSE and ERCOT Operators to accommodate the application of the emergency operations Settlement provisions.
Created2011-03-24
Approved2011-07-19
Sections Affected
3.8.33.9.16.4.66.6.9
Summary
This Nodal Protocol Revision Request (NPRR): Clarifies the COP reporting requirements for a Quick Start Generation Resource (QSGR) that is providing Off-Line Non-Spinning Reserve (Non--Spin) Service in an amount that is greater than High Sustained Limit (HSL) minus Low Sustained Limit (LSL); and Removes the requirement for a Qualified Scheduling Entity (QSE) to contact the ERCOT Operator to request a "manual override" when a QSGR it represents is first deployed by Security-Constrained Economic Dispatch (SCED) from a zero Base Point to a Base Point that is less than the QSGR’s physical LSL. Emergency operations Settlement provisions for QSGR deployments by SCED will be managed internally by ERCOT.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Apr 21 '11PRS To recommend approval of NPRR332 as amended by the 4/11/11 WMS comments and to instruct WMS to evaluate the implications of using Non-Spin Service in the manner envisioned by NPRR272, Definition and Participation of Quick Start Generation Resources.Passed
Jun 2 '11TAC To recommend approval of NPRR332 as recommended by PRS in the 5/19/11 PRS Report and as revised by TAC.Passed
Documents 9
NameTypePostedClassification
332NPRR-01 Revise QSGR Processes for COP Reporting of QSGR Assig doc Feb 25 '11 Revision Request
332NPRR-02 Impact Analysis 022511 doc Feb 25 '11 Staff Report
332NPRR-03 Revised Impact Analysis 030411 doc Mar 4 '11 Staff Report
332NPRR-04 PRS Report 032411 doc Mar 28 '11 Committee Report
332NPRR-05 WMS Comments 041111 doc Apr 11 '11 Revision Request Comments
332NPRR-06 PRS Report 042111 doc Apr 26 '11 Committee Report
332NPRR-07 PRS Report 051911 doc May 20 '11 Committee Report
332NPRR-08 TAC Report 060211 doc Jun 3 '11 Committee Report
332NPRR-09 Board Report 071911 doc Jul 19 '11 Committee Report
Meetings That Took It Up 8
DateMeetingCommitteeStatus
Jul 19 '11 Board of Directors Meeting BOARD Concluded
Jun 2 '11 TAC Meeting TAC Concluded
May 19 '11 PRS Meeting PRS Concluded
May 11 '11 WMS Meeting WMS Concluded
Apr 21 '11 PRS Meeting PRS Concluded
Apr 8 '11 WMS Meeting WMS Concluded
Apr 4 '11 QMWG Meeting QMWG Concluded
Mar 24 '11 PRS Meeting PRS Concluded