NOGRR #147 · Revision Request
NOGRR147 Reactive Power Testing Requirements
- ROS Dec 8 '15
- TAC Jan 28 '16
- BOARD Feb 9 '16
- PUCT —
ReasonRegulatory requirements
Created2015-07-23
Approved2016-02-09
Sections Affected
3.3.2.13.3.2.23.3.2.33.5
Summary
This Nodal Operating Guide Revision Request (NOGRR) revises the language in Section 3.3.2.1, Corrected Unit Reactive Limits (CURL), to harmonize the ERCOT reactive testing requirements with the recently approved North American Electric Reliability Corporation (NERC) Reliability Standards.
Timeline
-
Jun 29
ROSFiled by Luminant
- Jul 23
- Aug 20
-
Aug 31
Listed without action at 1 meeting
-
Sep 17
OWG OWG MeetingOWGRecommended for Approval Amended by the Sep 8 '15 Reactive Power Testing Requirements Workshop comments“To recommend approval of NOGRR147 as amended by the 9/8/15 Reactive Power Testing Requirements Workshop comments.” — Passed→ Impact Analysis Consideration
- Oct 22
-
Nov 17
OWG OWG MeetingOWGRecommended for Approval Forwarded → ROS priority 2016 · rank 1530“To endorse and forward to ROS the 10/22/15 OWG Report and the Impact Analysis for NOGRR147 with a recommended priority of 2016 and rank of 1530.” — Passed→ Revision Request Consideration
-
Dec 8
ROSEmail Vote / Unlisted MeetingROSRecommended for Approval“Voted via email vote to recommend approval of NOGRR147 as recommended by OWG in the 11/17/15 OWG Report.” — Passed→ Revision Request Consideration
- Dec 10
-
Jan 28
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NOGRR147 as recommended by ROS in the 12/8/15 ROS Report.” — Passed→ Revision Request Consideration
-
Feb 9
BOARD Board of Directors MeetingBOARDApproved“To approve NOGRR147 as recommended by TAC in the 1/28/16 TAC Report” — Passed
-
—
Posted since the last meeting